FISCAL IMPACT STATEMENT

PROGRAM: Traffic Signal Left Turn Phasing Improvements at Sierra and West Avenues PW00917 BF3837

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $597,777

Indirect Cost $271,223

TOTAL COST $869,000

Additional
Revenue or Savings
Generated

Net City Cost $869,000

Amount Budgeted
(If none budgeted,
identify source) $653,800

Indirect cost consists of the following:

Preliminary Engineering $ 47,500
Right of Way $ 28,700
Construction Engineering $ 56,200
Construction Materials $ 59,000
Construction Utilities $ 20,000
Contingency $ 59,823
Total $271,223

This project is locally funded by
SB1 Road Maintenance and Rehabilitation Account (RMRA).