FISCAL IMPACT STATEMENT

PROGRAM: First Street Cycle Track, Hazelwood Blvd. to Tulare St.

PW00906 BF3805

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $ 899,025

Indirect Cost $ 317,775

TOTAL COST $1,216,800

Additional
Revenue or Savings
Generated

Net City Cost $1,216,800

Amount Budgeted
(If none budgeted,
identify source) $1,212,600

Indirect cost consists of the following:

Preliminary Engineering $ 123,500
Construction Engineering $ 104,300
Contingency $ 89,975
Total $ 317,775

This project is funded by a State Active Transportation Program grant with the required local match is funding through Local Measure “C” Bike Facilities and the SB1 Road Maintenance and Rehabilitation Account (RMRA).