FISCAL IMPACT STATEMENT

PROGRAM: Marks Avenue Overlay from Ashlan Avenue to Dakota Avenue PW00834 Bid No. 3746

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $577,252.50

Indirect Cost $210,947.50

TOTAL COST $788,200.00

Additional
Revenue or Savings
Generated

Net City Cost $788,200.00

Amount Budgeted
(If none budgeted,
identify source) $632,200.00

Indirect cost consists of the following:

Preliminary Engineering $ 93,100.00
Construction Engineering $ 60,100.00
Contingency $ 57,747.50
Total $210,947.50

The Marks Avenue Overlay from Ashlan to Dakota Avenues Project is in Council District 1.

The project is locally funded by
SB1 Road Maintenance and Rehabilitation Account (RMRA).