Cities Index.
Proposal Opening Record

Fresno City Council
June 16, 2022

Document
Proposal Opening Record
Meeting
June 16, 2022
Body
Fresno City Council
Original file
361 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.

Proposal Opening Record

Date of opening:  March 22, 2019

The public opening of all responses received to the Request For Proposal #032119 for the procurement of HEAVY CONSTRUCTION EQUIPMENT WITH RELATED ACCESSORIES, ATTACHMENTS, AND SUPPLIES was witnessed by the following individuals:

Carol Jackson, Sourcewell
Sheila Christoffersen, Sourcewell
Kim Austin, Sourcewell
Steff Haataja, Sourcewell
Greg Grunig, Sourcewell
Craig West, Sourcewell
James Voelker, Sourcewell
Michael Munoz, Sourcewell
Scott Carr, Sourcewell
Chris Robinson, Sourcewell
Josh Meech, Sourcewell

Responses were received from the following:

BOMAG Americas, Inc. ‐ received 3/21/19 at 11:25:14 AM
Proposer deemed responsive
Caterpillar Inc. – received 3/15/19 at 11:08:37 AM
Proposer deemed responsive
CNH Industrial America LLC – received 3/15/19 at 11:08:27 AM Proposer deemed responsive
Doggett Heavy Machinery ‐ received 3/20/19 at 11:48:28 AM Proposer deemed Level‐One Non‐Responsive
Form A not completed
Form C not signed
Form P not completed
Doosan Infracore North America, LLC – received 3/19/19 at 11:33:03 AM Proposer deemed responsive
Dynapac North America LLC – received 3/20/19 at 11:05:58 AM Proposer deemed responsive
Certificate of Insurance omitted
Grove U.S. L.L.C. (dba Manitowac) ‐ received 3/19/19 at 11:17:18 AM Proposer deemed responsive
Hyundai Construction Equipment Americas, Inc. – received 3/20/19 at 11:05:26 AM Proposer deemed responsive
John Deere Construction Retail Sales ‐ received 3/19/19 at 11:17:12 AM Proposer deemed responsive
DocuSign Envelope ID: F01575AC-4F0C-4D2F-A021-11A3A57DBC2C

Kobelco Construction Machinery USA, Inc. – received 3/12/19 at 11:55:55 AM Proposer deemed responsive
Komatsu America Corp. – received 3/19/19 at 11:32:55 AM Proposer deemed responsive
Link Belt Cranes ‐ received 3/21/19 at 11:25:06 AM
Proposer deemed responsive
Roadtec, Inc – received 3/19/19 at 11:32:46 AM
Proposer deemed responsive
Volvo Construction Equipment North America, LLC – received 3/18/19 at 11:45:54 AM Proposer deemed responsive
Addendum One omitted
Volvo Construction Equipment North America, LLC – received 3/20/19 at 11:48:32 AM Proposer deemed responsive
Addendum One added to original proposal
Wirtgen America, Inc. – received 3/20/19 at 11:05:34 AM Proposer deemed responsive

Proposals are evaluated first on level‐one responsiveness and that determination is noted above. Level‐one responsiveness requires, among other things, that the response be received before the deadline for the submission and that the response include completed copies (with signatures) of the requested forms.

Proposers that are deemed level‐one responsive must provide any missing documentation or remedy a noted deficiency within a reasonable time in order to remain responsive. Respondents must not provide additional substantive information when sending missing documentation.

_____________________________________________                 _____________________________________ James Voelker, CPCM, CFCM, Procurement Lead Analyst               Carol Jackson, Procurement Analyst III

DocuSign Envelope ID: F01575AC-4F0C-4D2F-A021-11A3A57DBC2C

← All documents from this meeting