EX
HIBIT A
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 106 Proposed 570
• All rates in this section apply to land in the Urban Growth Management (UGM) area only. These fees are in addition to land use and construction requirements. • For parcels of land located in a land-use district not listed below, the Development Department Director shall fix a rate using the rate for a land-use district below which, in the Director's opinion, is most similar to the district.
Fire Station Service Area No. 2 Service Rate Delete
Per Gross Acre Delete
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 74.00 Delete S
-L*,R-1-B, R-1-C, R-1-B/PUD 122.00 Delete
R-
1-C/PUD, R-1, R-1/PUD 278.00 Delete
R
-2, R-2-A, M-H, T-P 555.00 Delete
R
-3, R-3-A, R-4 740.00 Delete
C
-1 through C-6, C-C, C-1-P, C-P, P, R-P 492.00 Delete
I
ndustrial 492.00 Delete
* O
n October 8, 1992, the Development Department Director made the determination that the C-P and R-P districts are most similar to the S-L district (Ordinance No. 91-102) for UGM fee rate purposes.
Fire Station Service Area No. 13 Service Rate Delete
Per Gross Acre Delete
S
-L, R-A, R-1, R-1-A, R-1-AH, R-1-B, R-1-C, R-1-E, R-1-EH 251.00 Delete R
-2, R-2-A 307.00 Delete
M
-H, R-3, R-3-A, T-P 340.00 Delete
R-
4 417.00 Delete
M-
1, M-1-P, M-2, M-3, C-R 600.00 Delete
C-
P 614.00 Delete
C
-M, R-P, R-P-L, 654.00 Delete
C
-1 through C-6, C-C, C-P P 742.00 Delete
AE-
5, AE-20, 0 No Fee Delete
PLANNING & DEVELOPMENT FEES
UGM FIRE STATION CAPITAL FEE (FMC 12-4.508)
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 107 Proposed 570
Fire Station Service Area No. 14 Service Rate Delete Accl. Rate Per Gross Acre Delete Per Gross Acre
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 87.00 Delete 169.00 S-L, R1-B, R-1-C 206.00 Delete 400.00
R-1 282.00 Delete 547.00
R-2-A, R-2, T-P 1,060.00 Delete 2,056.00
M-H, R-3-A, R-3, R-4 1,317.00 Delete 2,555.00
C-1 through C-6, C-C, C-P, C-R, C-L, C-M, M-1, 564.00 Delete 1,094.00 M-1-P, M-2, M-3, R-P, R-P-L Delete
Delete
Fire Station Service Area No. 15 Service Rate Delete Accl. Rate Per Gross Acre Delete Per Gross Acre
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 109.00 Delete 188.00 S-L, R-1-B, R-1-C 257.00 Delete 442.00
R-1 352.00 Delete 605.00
R-2-A, R-2, T-P 1,324.00 Delete 2,277.00
M-H, R-3-A, R-3, R-4 1,644.00 Delete 2,828.00
C-1 through C-6, C-P, C-L, C-R, C-M, C-C, M-1, 704.00 Delete 1,211.00 M-1-P, M-2, M-3, R-P, R-P-L Delete
Fire Station Service Area No. 16 Service Rate Semi Accl. Rate Delete Accl. Rate Per Gross Acre Per Gross Acre Delete Per Gross Acre
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 25.00 205.00 Delete 385.00 S-L, R-1-B, R-1-C 60.00 483.00 Delete 907.00
R-1 82.00 662.00 Delete 1,242.00
R-2-A, R-2, T-P 308.00 2,490.00 Delete 4,671.00
M-H, R-3, R-3-A, R-4 383.00 3,092.00 Delete 5,802.00
C-P, C-R, C-M, M-1, M-1-P, M-2, M-3, 164.00 1,324.00 Delete 2,485.00 R-P, R-P-L, P, C-1 through C-6, C-C, C-L
Fire Station Service Area No. 17 Service Rate Semi Accl. Rate Delete Accl. Rate Per Gross Acre Per Gross Acre Delete Per Gross Acre
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 23.00 136.00 Delete 250.00 S-L, R-1-B, R-1-C 63.00 321.00 Delete 589.00
R-1 73.00 440.00 Delete 807.00
R-2, R-2-A, T-P 274.00 1,655.00 Delete 3,036.00
M-H, R-3-A, R-3, R-4 340.00 2,055.00 Delete 3,770.00
C-P, C-R, C-M, M-1, M-1-P, M-2, M-3, 145.00 880.00 Delete 1,615.00 R-P, R-P-L, P, C-1 through C-6, C-C, C-L
PLANNING & DEVELOPMENT FEES
UGM FIRE STATION CAPITAL FEE (FMC 12-4.508)
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 108 Proposed 570
Fire Station Service Area No. 21 Service Rate Delete Accl. Rate Per Gross Acre Delete Per Gross Acre
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 114.00 Delete 370.00 S-L, R-1-B, R-1-C 187.00 Delete 610.00
R-1 411.00 Delete 1,388.00
R-2-A, R-2, T-P 855.00 Delete 2,775.00
M-H, R-3-A, R-3, R-4 1,140.00 Delete 3,700.00
C-P, C-R, C-M, M-1, M-1-P, M-2, M-3, 758.00 Delete 2,460.00 R-P, R-P-L, P, C-1 through C-6, C-C, C-L
Undesignated Service Area Service Rate Delete
Per Gross Acre Delete
AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH 250.00 Delete S-L, R-1-B, R-1-C, R-1-B/PUD 600.00 Delete
R-1, R-1-C/PUD, R-1/PUD 800.00 Delete
M-H, R-2, R-2-A, T-P 3,000.00 Delete
R-3, R-3-A, R-4 3,700.00 Delete
C-1 through C-6, C-C, C-M, C-1-P, C-P, P, 1,600.00 Delete R-P Delete
Industrial 1,600.00 Delete
Fire Impact Fee - Citywide**^ 551 570
Single family residential / per unit 2,061.00 2,285.00
Multi-family residential (>7.5 units/acre) fee per unit 1,556.00 1,743.00 Office fee per 1,000 Sq. Ft. of building 824.00 688.00
Retail fee per 1,000 Sq. Ft. of building 721.00 602.00
Industrial fee per 1,000 Sq. Ft. of building 413.00 344.00
PLANNING & DEVELOPMENT FEES
UGM FIRE STATION CAPITAL FEE (FMC 12-4.508)
** Accessory dwelling units (ADU) that are less than 750 sq. ft. are not charged Development Impact Fees.
ADUs larger than 750 sq. ft. pay the Multi-family residential rate. ** Fee applicable to map accepted for filing after August 30, 2005 and all Developers after November 27, 2005. ^ Adjusted on July 1 annually, beginning July 1, 2020, based on the 20-City Construction Cost Index as reported in the Engineering News Record for the 12-month period ending in May of the year of adjustment.
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 109 Proposed 570
Major Street Charge Fee Credits -- Prior to
Fees are per Linear Foot
Zones A, B, C 1978 1979 1980 1981/1982
Travel lane
Arterial 13.00 16.00 19.25 22.25
Collector 11.00 13.00 15.25 17.25
Travel lane with shoulder
Arterial 17.00 21.25 25.50 29.75
Collector 15.00 17.50 20.25 23.00
Travel lane with median curb
Arterial 17.50 21.50 25.25 29.25
Travel lane with median curb and shoulder
Arterial 22.00 27.00 31.75 36.75
Zones D-1, D-2
Travel lane
Arterial 10.50 13.00 15.50 18.00
Collector 8.75 10.75 12.50 14.50
Zones E-1, E-2, F
Travel lane with shoulder
Arterial 14.00 17.25 20.75 24.00
Collector 11.75 14.25 17.00 19.50
Zones E-3, E-4, E-5
Travel lane with median curb
Arterial 15.00 18.25 21.75 25.00
Travel lane with median curb and shoulder 18.50 22.50 26.75 31.00s Major Street Charge Fee Credits -- After October 22, 1982 Fee credits are based on 12-foot travel lanes, 4-foot shoulders, and 22-foot medians. Variances from these standards will be adjusted on a pro-rata basis.
Zones A, B, C-D-2, D-1/E-2, E-1, F Per Linear Foot
Travel lane
Arterial streets 19.50
Collector streets 14.50
Travel lane with shoulder
Arterial streets 24.50
Collector streets 19.50
Finished median with curbs 25.00
Graded median without curbs 11.00
Left-turn pocket with island curbs / each 19,000.00
PLANNING & DEVELOPMENT FEES
UGM MAJOR STREET CHARGE AND FEE CREDITS (FMC 12-226)
October 22, 1982
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 110 Proposed 570
Major Street Charge Fee Credits -- After October 22, 1982 (continued) Zones E-3, E-4, E-5 Per Linear Foot
Travel lane
Arterial streets 15.75
Collector streets 12.25
Travel lane with shoulder
Arterial streets 21.00
Collector streets 17.00
Finished median with curbs 21.00
Graded median without curbs 8.00
Left-turn pocket with island curbs / each 17,700.00
Charges and fee credits for projects approved during 1979, 1980, and 1981, represent the 1978 figures adjusted upwards by 22.3 percent for 1979, 44.7 percent for 1980, and 67.8 percent for 1981/1982 to reflect increased construction costs. In no event shall the total actual fee credit for such years be less than the total fee credit established for 1978.
Applicable to the year in which the major street improvements are accepted by the City. In the event of a reimbursement, the major street charges paid prior to October 22, 1982, shall be adjusted upward to reflect the rates established here. In no event shall the reimbursement be less then the reimbursement amount established for 1978.
Per Gross Acre (excludes area of major street)
1978 1979 1980 1981/1982
Zone A 650.00 795.00 940.00 1,085.00
Zone B 710.00 870.00 1,025.00 1,185.00
Zone C 855.00 1,095.00 1,235.00 1,430.00
Zone D-1 270.00 330.00 390.00 450.00
Zone D-2 270.00 330.00 390.00 450.00
Zone E-1 895.00 1,095.00 1,295.00 1,495.00
Zone E-2 680.00 830.00 895.00 1,135.00
Zone E-3 820.00 1,000.00 1,185.00 1,370.00
Zone E-4 700.00 855.00 1,015.00 1,170.00
Zone E-5 180.00 220.00 260.00 300.00
Zone F 895.00 1,095.00 1,295.00 1,495.00
PLANNING & DEVELOPMENT FEES
UGM MAJOR STREET CHARGE AND FEE CREDITS (FMC 12-226)
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 111 Proposed 570
Per Gross Acre
(excludes area of major streets)
Major Street Charges -- Applicable to all Building Permits issued 443 prior to July 1, 2007
Applicable to each lot created by a vesting subdivision map accepted for filing prior to January 23, 2007, and whose vesting rights have not expired.
Zone A -0- Delete
Zone B -0- Delete
Zone C/D-2 2,798.00 Delete
Zone D-1/E-2 3,161.00 Delete
Zone E-1 2,436.00 Delete
Zone E-3 4,053.00 Delete
Zone E-4 3,531.00 Delete
Zone E-5 -0- Delete
Zone F 3,625.00 Delete
All other zones, charges, and fees are established by the Public Works Director
Per Gross Acre
(excludes area of major streets)
Major Street Charges -- Applicable to all Building Permits issued 443 prior to July 1, 2007
Applicable to each lot created by a vesting subdivision map accepted for filing prior to January 23, 2007, and whose vesting rights have not expired.
Zone A -0- Delete
Zone B -0- Delete
Zone C/D-2 94.00 Delete
Zone D-1/E-2 304.00 Delete
Zone E-1 254.00 Delete
Zone E-3 232.00 Delete
Zone E-4 196.00 Delete
Zone E-5 -0- Delete
Zone F 72.00 Delete
All other zones, charges, and fees are established by the Public Works Director
PLANNING & DEVELOPMENT FEES
UGM MAJOR STREET CHARGE AND FEE CREDITS (FMC 12-226-1)
UGM MAJOR STREET BRIDGE CHARGE (FMC 11-226-1)
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 112 Proposed
Per Gross Acre
(excludes area of major streets)
Citywide Locally Regionally Significant Street Impact Fee ^ 529 570 Residential (Low-Medium) 8,752.00
Residential (Medium/High-High) 16,993.00
Commercial Retail 15,475.00
Commercial Office 16,390.00
Light Industrial 4,661.00
Heavy Industrial 2,865.00
Per Gross Acre
(excludes area of major streets)
New Growth Area Major Street Impact Fee ** ^ 529 570
Residential (Low-Medium) 24,090.00 27,490.00
Residential (Medium/High-High) 46,816.00 53,424.00
Commercial Retail 43,487.00 50,710.00
Commercial Office 41,162.00 47,189.00
Light Industrial 13,281.00 15,396.00
Heavy Industrial 8,058.00 9,196.00
PLANNING & DEVELOPMENT FEES
CITYWIDE LOCALLY REGIONALLY SIGNIFICANT STREET CHARGE (FMC 11-226.2) The Citywide Regional Street Impact Fee shall be applicable to all building permits issued after July 1, 2007, except for those lots that are protected under vesting map rights which have not expired. This fee would also be applicable to any lots created by subdivision whose map was accepted for filing after January 23, 2007. Fee shall be calculated on a net acreage basis - gross area less major street dedications.
NEW GROWTH AREA MAJOR STREET CHARGE (FMC 11-226.2)
The New Growth Area Major Street Impact Fee shall be applicable to all building permits issued after July 1, 2007, except for those lots that are protected under vesting map rights which have not expired. This fee would be applicalbe to any lots created by subdivision whose map was accepted for filing after January 23, 2007. Fee shall be calculates on a net acreage basis - gross area less major street dedications. * Includes Citywide local regionally signific ant street charge. ** Accessory dwelling units (ADU) that are less than 750 sq. ft. are not charged Development Impact Fees.
ADUs larger than 750 sq. ft. pay the Multi-family residential rate. ^Adjusted on July 1 annually, beginning July 1, 2018, based on the 20-City Construction Cost Index as reported in the Engineering News Record for the 12-month period ending in May of the year of adjustment. 8,783.00
17,054.00
15,769.00
16,517.00
4,728.00
2,874.00
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 113 Proposed 570
For parcels of land located in a land-use district not listed below, the Development Department Director shall fix a rate using the rate for a land-use district below which, in the Director's opinion, is most similar to the district.
Service Rate Delete Accl. Rate
Per Gross Acre Per Gross Acre
Park Service Area No. 1
Zone District Classification
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 213.00 Delete 426.00 R-1-B, R-1-C 352.00 Delete 705.00
MH, R-1 799.00 Delete 1,598.00
R-2-A, R-2, T-P 1,598.00 Delete 3,196.00
R-3-A, R-3, R-4 2,131.00 Delete 4,263.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 400.00 Delete 800.00 M-1-P, M-1, M-2, M-3 213.00 Delete 426.00
Park Service Area No. 2 Delete
Zone District Classification Delete
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 319.00 Delete 638.00 R-1-B, R-1-C 526.00 Delete 1,053.00
MH, R-1 1,196.00 Delete 2,392.00
R-2-A, R-2, T-P 2,392.00 Delete 4,785.00
R-3-A, R-3, R-4 3,190.00 Delete 6,380.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 599.00 Delete 1,198.00 M-1-P, M-1, M-2, M-3 319.00 Delete 638.00
Park Service Area No. 3 Delete
Zone District Classification Delete
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 429.00 Delete 858.00 R-1-B, R-1-C 708.00 Delete 1,415.00
MH, R-1 1,609.00 Delete 3,219.00
R-2-A, R-2, T-P 3,219.00 Delete 6,438.00
R-3-A, R-3, R-4 4,292.00 Delete 8,584.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 805.00 Delete 1,609.00 M-1-P, M-1, M-2, M-3 429.00 Delete 858.00
Park Service Area No. 4 Delete
Zone District Classification Delete
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 238.00 Delete 476.00 R-1-B, R-1-C 393.00 Delete 786.00
MH, R-1 892.00 Delete 1,783.00
R-2-A, R-2, T-P 1,783.00 Delete 3,567.00
R-3-A, R-3, R-4 2,378.00 Delete 4,756.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 447.00 Delete 893.00 M-1-P, M-1, M-2, M-3 238.00 Delete 476.00
PLANNING & DEVELOPMENT FEES
UGM PARK FEES (FMC 12-4.509)
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 114 Proposed 570.00
Service Rate Accl. Rate
Per Gross Acre Per Gross Acre
Park Service Area No. 5 Delete
Zone District Classification Delete
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 328.00 Delete 655.00 R-1-B, R-1-C 541.00 Delete 1,082.00
MH, R-1 1,230.00 Delete 2,459.00
R-2-A, R-2, T-P 2,458.00 Delete 4,915.00
R-3-A, R-3, R-4 3,277.00 Delete 6,554.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 615.00 Delete 1,230.00 M-1-P, M-1, M-2, M-3 328.00 Delete 655.00e ete
Park Service Area No. 6 Delete
Zone District Classification Delete
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 219.00 Delete 438.00 R-1-B, R-1-C 361.00 Delete 722.00
MH, R-1 821.00 Delete 1,641.00
R-2-A, R-2, T-P 1,641.00 Delete 3,283.00
R-3-A, R-3, R-4 2,188.00 Delete 4,376.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 410.00 Delete 821.00 M-1-P, M-1, M-2, M-3 219.00 Delete 438.00
Park Service Area No. 7 Delete
Zone District Classification Delete
S-L, AE-5, AE-20, R-A, R-1-A, R-1-AH, R-1-E, R-1-EH, O 490.00 Delete 980.00 R-1-B, R-1-C 809.00 Delete 1,618.00
MH, R-1 1,225.00 Delete 2,450.00
R-2-A, R-2, T-P 3,676.00 Delete 7,351.00
R-3-A, R-3, R-4 4,901.00 Delete 9,801.00
C-1 through C-6, C-C, CL, CM, C-P, C-R, P, R-P 919.00 Delete 1,838.00 M-1-P, M-1, M-2, M-3 490.00 Delete 980.00
Park Facility Impact Fee - Citywide**^~ Per Unit
Park Facility Fee
Park Quimby
Fee (Land)
Total Park
Fee,
Facility+
Quimby
Single Family Dwelling*** 3,061.00 1,324.00 4,385.00 Multi-Family Dwelling (>7.5 units/Acre)*** 2,308.00 999.00 3,307.00 Quimby Parkland Dedication Fee***^~ Per Unit
(Applicable to land divisions only)
Single Family Dwelling**** 1,324.00
Multi-Family Dwelling**** 999.00
UGM PARK FEES (FMC 12-4.509)
**Fee applicable to maps accepted for filing after August 30, 2005 and all developments after November 20, 2005. ^Adjusted on July 1 annually, beginning July 1, 2018, based on the 20-City Construction Cost Index as reported in the Engineering News Record for the 12-month period ending in May of the year of adjustment. ~MFS Amendment #529, effective 2/06/2017.
**** This amount if paid is creditable against the Park Facility Impact Fee. *** Fee applicable to maps accepted for filing after August 30, 2005. Effective date of collection October 27, 2005.
PLANNING & DEVELOPMENT FEES
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 115 Proposed 570
Service Rate Per Gross Acre
(except area of major streets)
Grade Separation Fee 417
Service area
Zone E-4-A 443.00
Cornelia Trunk Service Area Grantland Trunk Service Area Zone District classifications: (except area of major streets) (except area of major streets) S-L, R-A, AE-5, AE-20 80.00 86.00
R-1-A, R-1-AH, R-1-E, R-1-EH 200.00 215.00
R-1-B, R-1-C 326.00 356.00
R-1 445.00 482.00
C-1, C-2 490.00 702.00
C-M, M-1, M-1-P, M-2 504.00 546.00
C-3 through C-6, C-R 792.00 858.00
C-P, R-P, R-P-L 1,257.00 1,362.00
R-2, R-2-A, R-3, R-3-A, R-4, TP, MH 1,257.00 1,362.00
Minimum / per lot 70.00 70.00
All other zones, rates established by the Public Works Director based on estimated sewer flow
PLANNING & DEVELOPMENT FEES
UGM GRADE SEPARATION FEES (FMC 11-227)
UGM GRADE SEPARATION FEES (FMC 11-227)
Rates shall apply only to tentative maps deemed to be complete prior to July 31, 1990, and to all other entitlements approved prior to July 31, 1990, where the developer shows evidence to the satisfaction of the Development Department Director that a construction loan commitment was secured prior to September 30, 1990, and to final maps approved prior to September 30, 1990, for which covenants have been executed deferring fees to issuance of building permit.
Per Gross Acre Per Gross Acre
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 116 Millbrook Overlay Sewer Service Area (Reso 87-376)
Area north of Shepherd Avenue (except Dominion Planned 393.00 per Gross Acre (except Community) area of major streets)
Remaining undeveloped land in Woodward Lakes 695.00 per Gross Acre (except area of major streets)
Dominion Planned Community area 44.00 per Residential Unit in excess of approved densities for
each village or 2,377 total units
(Ord. 90-43) effective 05/18/90
Area south of Shepherd Avenue 240.00 per Gross Acre (except area of major streets)
Fee Description & Unit/Time
Current Proposed Amnd
Traffic Signal Mitigation Impact Fees^ 529 570
Single Family Residential / per Single Family Dwelling Unit 546.00 762.00 Multi-Family Residential / per Multi-Family Dwelling Unit 381.00 591.00 Assisted Living1/ per number of Beds 158.00 334.00 Lodging2/ per number of Rooms 510.00 987.00
Health/Fitness Club3/ per 1,000 sq feet 1,890.00 2,662.00 Industrial4/ per 1,000 sq feet 399.00 400.00 Warehouse / per 1,000 feet 204.00 140.00
UG
M TRAFFIC SIGNAL CHARGE (FMC 11-226 12-411)
PLANNING & DEVELOPMENT FEES
UGM TRUNK SEWER CHARGE (FMC 9-503; RESOLUTION 83-40)
^Adjusted on July 1 annually, beginning July 1, 2018, based on the 20-City Construction Cost Index as reported in the Engineering News Record for the 12-month period ending in May of the year of adjustment.
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 117 UGM TRAFFIC SIGNAL CHARGE (FMC 11-226 12-411)
Fee Description & Unit/Time Current Proposed Amnd
Traffic Signal Mitigation Impact Fees ( Continued)^ 529 570 Institutional
Elementary School5/ per number of Students 74.00 153.00 Middle/Jr High School5/ per number of Students 92.00 172.00 High School5/ per number of Students 97.00 164.00 Private School (K-12)/ per number of Students 141.00 200.00 Community College/ per number of Students 71.00 93.00 University/ per number of Students 97.00 126.00 Place of Worship/ per number of Seats 36.00 51.00 Day Care Center/Preschool/ per number of Students 250.00 330.00 Library/ per 1,000 sq feet 3,223.00 5,817.00
Hospital/ number of Beds 742.00 1,802.00
Clinic/ per 1,000 sq feet 1,801.00 3,081.00
Medical/Dental Office/ per 1,000 sq feet 2,070.00 2,809.00 Office6/ per 1,000 sq feet 632.00 786.00
Commercial 570
Discount Store7/ per 1,000 sq feet 2,094.00 2,906.00 General Retail8/ per 1,000 sq feet 2,445.00 3,048.00 Supermarket/ per 1,000 sq feet 3,640.00 5,517.00 Discount Club/ per 1,000 sq feet 2,396.00 2,126.00 Home Improvement Store9/ per 1,000 sq feet 916.00 1,439.00 Pharmacy10/ per 1,000 sq feet 2,831.00 4,494.00
Restaurant11/ per 1,000 sq feet 4,151.00 5,162.00 Fast-Food Restaurant/ per 1,000 sq feet 14,212.00 19,010.00 Convenience Market w/Gas Station/ per number of Fueling 4,104.00 7,295.00 Convenience Market (no pumps)/ per 1,000 sq feet 4,104.00 7,295.00 Bank12/ per number of Drive-in Lanes 4,229.00 7,050.00 Tire Store/per number of Service Bays 1,751.00 2,466.00 Automobile Care Center/ per number of Service Bays 714.00 1,008.00 Car Wash / per number of Stalls 6,188.00 8,719.00 ^The Traffic Signal Mitigation Impact Fees will be adjusted annually on July 1st each year beginning July 1, 2018. The adjustment will be based on the 20-City Construction Cost Index as reported in the Engineering News Record (ENR) for the 12-month period ending in May of the year of the adjustment.
PLANNING & DEVELOPMENT FEES
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) 6/13/20225:52 PM Page 118 UGM TRAFFIC SIGNAL CHARGE (FMC 11-226 12-411)
Fee Description & Unit/Time Current Proposed Amnd
Traffic Signal Mitigation Impact Fees ( Continued) ** ^ 529 570
56.00 80.73
1 Includes nursing home & assisted living uses
2 Includes hotel, all suite hotel, business hotel & motel 3 Includes racquet/tennis clud, health/fitness club & athletic club 4 Includes light, heavy & industrial park
5 Public, private, or charter schools
6 Includes general office, office park, business park, and R& D center 7 Includes super store
8 Includes specialty retail and shopping centers over 150,000 sq feet 9 Includes building materials/lumber store & hardware/paint stores 10 With or without drive-through
11 Includes high-turnover and quality
12 If no drive-in lanes, use square footage as variable ** Accessory dwelling units (ADU) that are less than 750 sq. ft. are not charged Development Impact Fees.
ADUs larger than 750 sq. ft. pay the Multi-family residential rate. ^Adjusted on July 1 annually, beginning July 1, 2018, based on the 20-City Construction Cost Index as reported in the Engineering News Record for the 12-month period ending in May of the year of adjustment.
PLANNING & DEVELOPMENT FEES
Uses not included above shall be based upon a trip
generation analysis, to be approved by the City Traffic Engineer/ per Average Daily Trip(s).
CITY OF FRESNO
MASTER FEE SCHEDULE
All fees effective 07/01/2022 unless otherwise noted
MFS Amendment #565 (January 2022) [6/13/20225:51 PM] Page 144
GENERAL FEES
Fee Description & Unit/Time Current Proposed Amnd
Graffiti Abatement/Vacant Boarded Buildings 464
Fees based on actual cost 239.00
Miscellaneous Permit Application Review 401
Includes, but is not limited to: Amusement devices; 328.00/each dance permits; hotel/rooming house permits; billiard
parlor permits; special events permits; bingo permits;
etc.
Detective Review of Miscellaneous Permits 204.00/each
Monthly Statistical Report 4.00
Parade Route Policing
Dowtown 5,456.00 546
Fulton Route 5,703.00
Olive/Hedges Loop 3,913.00
O Street Route 3,913.00
Olive Route 2,232.00
City Hall Loop 2,673.00
China Town Route 2,094.00
Mariposa Route 1,819.00
Photographs 401
3 ½ x 5 print - color 5.00
4 x 5 print - black and white 2.50
8 x 10 print - color 7.00
8 x 10 print - black and white 2.50
Mug shot - color 3.00
Compact Disc Copy 16.00
Police Bomb Team 393
Explosive handling and detonation
Minimum per disposal 345.00
Response Fee 816.00
Police Facilities Impact Fee - Citywide *^ ** Option II 529 570 Single Family Resident / per unit 673.00 948.00
Multi-Family Resident / per unit 507.00 723.00
Office / fee per 1,000 sq. ft. of Building 682.00 844.00 Retail / fee per 1,000 sq. ft. of Building 717.00 886.00 Industrial / fee per 1,000 sq. ft. of Building 340.00 422.00
POLICE DEPARTMENT
* Fees applicable to all maps accepted for filing after August 30, 2005 and all developments after November 27, 2005. ** Accessory dwelling units (ADU) that are less than 750 sq. ft. are not charged Development Impact Fees.
ADUs larger than 750 sq. ft. pay the Multi-family residential rate. ^Adjusted on July 1 annually, beginning July 1, 2018, based on the 20-City Construction Cost Index as reported in the Engineering News Record for the 12-month period ending in May of the year of adjustment.