EVALUATION OF BID PROPOSALS Page 1
FOR: FRESNO YOSEMITE INTERNATIONAL AIRPORT TERMINAL EAST APRON
RECONFIGURATION PROJECT
Bid File No. 3859
Bid Opening: 04/12/2022
BIDDERS TOTAL NET BID AMOUNT
1. A. Teichert & Son, Inc. dba Teichert Construction $10,130,425.00 5771 S. Toyota Ave
Fresno, CA 93725
2. Security Paving Company, Inc. $10,854,000.00
3075 Townsgate Road, Suite 200
Westlake Village, CA 91361 .
3. Granite Construction Company $11,564,215.00
2716 Granite Court
Fresno, CA 93706
Each bidder has agreed to allow the City sixty-four (64) days from date bids are opened to accept or reject their bid proposal. Purchasing requests that you complete the following sections and return this bid evaluation to the Purchasing Division at the latest by Monday, May 9, 2022 5:00 P.M.
The Engineer's Estimate/Budget Allocation for this expenditure is $12,202,175.00. The contract price is 17% below the Engineer's Estimate/Budget Allocation. If the overage is greater than 10% or only one bid l was received, give explanation: ' I l
i
BACKGROUND OF PROJECT (To be completed by Evaluating Department/Division. Explain need for project/equipment): Reconfiguring the East Apron, used for aircraft circulation and parking in the concourse gate area, is enabling work necessary to accommodate the upcoming Terminal expansion lproject. In addition to expanding the existing asphalt and concrete aircraft apron to the east. the Project will include related infrastructure work such as storm drainage, underground utilities, lightning, signage, fencing and reconfigured on-airport service roadways.
DEPARTMENT CONCLUSIONS AND RECOMMENDATION:
W Award a contract in the amount of$ 10,130,425.00
to Teichert Construction
as the lowest responsive and responsible bidder.
Remarks:
L) Reject all bids. Reason:
Evaluallon Form VI/Ith DBE No Goal Rev. 01-2022
EVALUATION OF BID PROPOSALS Page 2
FOR: FRESNO YOSEMITE INTERNATIONAL AIRPORT TERMINAL EAST APRON
RECONFIGURATION PROJECT
Bid File No. 3859 I Bid Opening: 04/12/2022 I :
I
F
I
Department Head Approval
l I
The recommended Contractor complied with the DBE requirements pursuant to the bid specifications. o~ s~ s,1a,2022
DBE Program Coordinator
LX] Approve Dept. Recommendation Approve Finance/Purchasing Recommendation Ll Disapprove L] Disapprove
L] See Attachment
**PLA is applicable and was included in project specifications
FINANCE DEPARTMENT CITY MANAGER
~
Q5/16/2Q22
Date
E'valuatlon Form With DBE No Goal Rl'I, 01-2022
FISCAL IMPACT STATEMENT
PROGRAM:
RECOMMENDATION
Direct Cost-Construction Bid
Other Direct Cost
Indirect Cost
TOTAL COST
Additional
Revenue or Savings
Generated
Net City Cost
Amount Budgeted ·
(If none budgeted,
identify source)
Federal Aviation Administration
90.66%
Passenger Facility Charges
Total Funding
TOTAL OR
CURRENT
$10,130,425
$ 2,056,729
$12,187,154
0 0
.,:
$12,187,154
$11,048,874
$1,138,280
$12,187,154
ANNUALIZED
COST
0 0
0 0
0 0
0 0
0 0
:--