FISCAL IMPACT STATEMENT

PROGRAM: Midtown Fresno School Area Multimodal Interconnectivity Project PW00878 Bid No.3834

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $2,214,587

Indirect Cost $ 527,113

TOTAL COST $2,741,700

Additional
Revenue or Savings
Generated

Net City Cost $2,741,700

Amount Budgeted
(If none budgeted,
identify source) $2,389,000

Indirect Costs consist of:

Preliminary Engineering $167,100
Right of Way $ 3,600
Construction Engineering $115,700
Construction Materials $110,000
Construction Utilities $ 20,000
Contingency $ 258.309
Total $ 527,113

The Midtown Fresno School Area Multimodal Interconnectivity Project is state funded by an Active Transportation Program (ATP) grant. Required local match is funded by Bicycle and Pedestrian local funds, Traffic Signal Mitigation Impact Fee, and SB1 Road Maintenance and Rehabilitation Account (RMRA) funds.