22-1389 Fiscal Impact Statement

Fresno City Council
September 29, 2022

Document
22-1389 Fiscal Impact Statement
Meeting
September 29, 2022
Body
Fresno City Council
Original file
80 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.

Evaluation Form With DBE Goal Rev. 07-2022

FISCAL IMPACT STATEMENT

PROGRAM: PW00923 VETERANS BOULEVARD NORTH EXTENSION

PROJECT

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $7,085,420.50

Indirect Cost $ 1,512,780.83

TOTAL COST $ 8,598,201.33

Additional
Revenue or Savings
Generated

Net City Cost $ 8,598,201.33

Amount Budgeted
(If none budgeted,
identify source) $8,689,800.00

Indirect cost consists of the following:

Construction Engineering including overhead $ 744,877.00 Construction Utilities $ 59,361.78
Contingency $ 708,542.05
Total $ 1,512,780.83*

*The indirect cost total does not include the costs associated with preliminary engineering or right- of-way acquisition since those costs are associated with the overall Veterans Boulevard P roject.

The Veterans Boulevard – North Extension construction package is funded by Local Measure “C”, Developer Fee Funding, and State Local Partnership Program grant. The design and Right of Way phases for the Veterans project were primarily funded by Local Measure “C”, Developer Fee Funding and a small federal grant from the Transportation, Community, and System Preservation Program (TCSP).