Project Change Request

Client Name: City of Fresno, CA Change Req. Number PCR-COF-0002

Client Project Manager: Dennis Jones Requested By (Name): Dennis Jones

Tyler Project Manager: Karen Lowe Request Date: 02/20/2023

X Place an “X” in this box if client has a Statement of Work included in the contract indicating that this change may require review by the Tyler Contracts team

Description of Proposed Change
Client is requesting a removal of the below listed Services item and then funds will re-allocated Implementation days and Travel Expenses budget line items:
.

The items to be removed are as follows:

1. Accounting Summary Actuals (3 years) – $3,500

2. Accounting Summary Budgets (3 years) - $3,500

3. Accounting Standard – Chart of Accounts - $4,000

4. Accounts Payaable – Check History (5 years) - $5,400

5. Accounts Payable – Invoice History (5 years) - $7,000

6. Capital Assets – Standard Master - $5,000

7. Contracts – Standard Master - $6,500

8. General Billing – Bills (5 years) - $6,000

9. General Billing – Recurring Invoices - $5,000

10. Project Grant Accounting – Summary Actuals (3 years) - $3,500

11. Project Grant Accounting – Summary Budgets (3 years) - $3,500

12. P-Card Custom Import Format - $5,500

Total being removed = $58,400

The items to be added are as follows:

1. 312 hours which equates to 39 Implementation days - $57,720

2. Add balance of $680 to travel expense budget

Total being added (reclassified) = $58,400

Impact on Project Scope

2 Project Scope was reduced by the using import tools and file layouts to convert data elements

Impact on Project Schedule
N/A

Impact on Project Resources
N/A
Impact on Current Milestones and Payment Schedules
N/A

Impact on Project Goals and Objectives
N/A

Impact on Project Budget
Training/Impl Conversion Forms Development Testing Other See Below
Budget Comments
No Overall Change to Overall Project Budget Totals/ Reallocation of Dollars from Conversion Services to Implementation Services. The amount being reallocated is $58.400

Client Project Manager: Date:

Client Project Sponsor: Date:

Client Project Manager Comments

Tyler Project Manager: Karen A Lowe Date: 02/20/2023