Evaluation Form With DBE Goal Rev. 07-2022
FISCAL IMPACT STATEMENT
PROGRAM: Fresno Street Corridor Improvements
Bid No. 12301137 PW00882
TOTAL OR ANNUALIZED
RECOMMENDATION CURRENT COST
Direct Cost $2,168,547.75
Indirect Cost $1,050,422.25
TOTAL COST $3,218,970.00
Additional
Revenue or Savings
Generated $0
Net City Cost $3,218,970.00
Amount Budgeted
(If none budgeted,
identify source) $2,428,600
Preliminary Engineering $350,000.00
Right of Way $128,600.00
Construction Utilities $ 9,200.00
Construction Materials $136,370.00
Construction Engineering $209,400.00
Contingency $216,852.25
Total $1,050,422.25
The Fresno Street Corridor Improvements Project is federally funded with a grant from Highway Safety Improvement Program (HSIP).