FISCAL IMPACT STATEMENT

PROGRAM: Fresno and Browning Traffic Signal
PW00908

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $ 816,000

Indirect Cost $ 429,540

TOTAL COST $1,245,540

Additional
Revenue or Savings
Generated $0

Net City Cost $1,245,540

Amount Budgeted
(If none budgeted,
identify source) $ 944,000

Indirect cost consists of the following:

Preliminary Engineering $155,900
Right of Way $ 28,200
Construction Utilities $ 7,640
Construction Materials $ 60,000
Construction Engineering $ 96,200
Contingency $ 81,600
Total $429,540

The Fresno and Browning Traffic Signal Project is grant funded by an Active Transportation Program (ATP) grant. Required local match is funded by SB1 Road Maintenance and Rehabilitation Account (RMRA) funds.