FISCAL IMPACT STATEMENT

PROGRAM: Shaw Avenue Lighting Project
209900260 Inv# 12302722

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $649,865

Indirect Cost $234,535

TOTAL COST $884,400

Additional
Revenue or Savings
Generated

Net City Cost $ 884,400

Amount Budgeted
(If none budgeted,
identify source) $796,100

SUMMARY OF INDIRECT COSTS:

Preliminary Engineering $ 89,100
Construction Engineering $ 80,400
Contingency $ 65,035
Total $ 234,535

The Shaw Avenue Lighting project is 100% federally funded by a grant from the Surface Transportation Block Grant (STBG).