FISCAL IMPACT STATEMENT

PROGRAM: Roof Membrane Replacement at Fresno-Clovis Regional Wastewater Reclamation Facility (RWRF) Warehouse and Maintenance Building and Digester-13 Heating and Mixing Building
TC00180 12401198

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $324,889.00

Indirect Cost $ 38,000.00

TOTAL COST $362,889.00

Additional
Revenue or Savings
Generated

Net City Cost $362,889.00

Amount Budgeted
(If none budgeted,
identify source) $370,000.00

*Indirect Costs

Construction Management $ 28,000.00

Project Administration $ 8,000.00

Contingency $ 2,000.00

$ 38,000.00