FISCAL IMPACT STATEMENT

PROGRAM: Chestnut Avenue Overlay from Kings Canyon Road to Butler Ave 209900242 Bid No. 12401042

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $ 1,484,956

Indirect Cost $ 558,644

TOTAL COST $ 2,043,600

Additional
Revenue or Savings
Generated

Net City Cost $ 2,043,600

Amount Budgeted
(If none budgeted,
identify source) $ 2,337,600

SUMMARY OF INDIRECT COSTS:

PE Costs $ 241,100
Right-of-way $ 8,950
Construction Engineering $ 160,000
Contingency $ 148,594
Total Indirect Cost $ 558,644

The Chestnut Avenue Overlay Project from Kings Canyon Road to Butler Avenue is 100% grant funded by the Surface Transportation Block Grant (STBG).