FISCAL IMPACT STATEMENT

PROGRAM: Replacement of Fiber Optic Cabling at Regional Wastewater Reclamation Facility

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $217,286.89

Indirect Cost $ 61,156.00

TOTAL COST $278,442.89

Additional
Revenue or Savings
Generated $ 00.00

Net City Cost $278,442.89

Amount Budgeted
(If none budgeted,
identify source) $283,000.00

SUMMARY OF INDIRECT COSTS:

PE Costs $25,000.00
Construction Engi neering $31,806.00
Contingency $ 4,350.00
Total Indirect Cost $61,156.00

This project has no impact to the General Fund and is located in Council District 3. Funding for this project is included in the Fiscal Y ear 2024 Capital Improvem ent Budget within the Wastewater Management Division’s Sewer Enterprise Fund 40501 .