Exhibit J
All vesting tentative maps are subject to the applicable provisions of the State Subdivision Map Act, Fresno Municipal Code, City policies, and City of Fresno Standard Specifications. The following specific conditions are applicable to this vesting tentative tract map.
NOTICE TO PROJECT APPLICANT
In accordance with the provisions of Government Code §66020(d)(1), the imposition of fees, dedications, reservations or exactions for this project are subject to protest by the project applicant at the time of approval or conditional approval of the development or within 90 days after the date of the imposition of the fees, dedications, reservations or exactions imposed on the development project.
URBAN GROWTH MANAGEMENT REQUIREMENTS (GENERAL)
The subdivider of property located within the UGM boundaries shall comply with all sewer, water and street requirements and pay all applicable UGM fees imposed under the Urban Growth Management process (with appropriate credit given for the installation of required UGM improvements) in accordance with the requirements of State Law as related to tentative tract maps.
GENERAL CONDITIONS
1. Upon conditional approval of Vesting Tentative Tract Map No. 6360 dated November 21, 2022, the subdivider may prepare a Final Map in accordance with the approved vesting tentative tract map.
2. Upon conditional approval of Vesting Tentative Tract Map No. 6360 dated November 21, 2022, the subdivider may prepare a Final Map in accordance with the approved vesting tentative tract map and Planned Development Application No. P22-00387 which establishes a planned development for the subject property.
CITY OF FRESNO
PLANNING AND DEVELOPMENT DEPARTMENT
CONDITIONS OF APPROVAL
JULY 3, 2024
VESTING TENTATIVE TRACT MAP NO. 6360
“A PLANNED DEVELOPMENT”
LOCATED ON THE NORTHEAST CORNER OF THE EAST MCKINLEY AVENUE ALIGNMENT AND
NORTH ARMSTRONG AVENUE
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
3. Upon conditional approval of Vesting Tentative Tract Map No. 6360 dated November 21, 2022, the subdivider may prepare a Final Map in accordance with the approved tentative tract map.
a. Approval of Vesting Tentative Tract Map No. 6360 is contingent upon City Council approval of Plan Amendment-Rezone Application No. P22-00388.
b. Approval of Vesting Tentative Tract Map No. 6360 is contingent upon City Council approval of related Planned Development Permit Application No. P22- 00387.
4. Prior to final map approval, the subdivider shall execute a “Right to Farm” covenant with the City of Fresno. Said covenant is to run with the land and shall acknowledge and agree that the subject property is in or near agricultural districts located in the City and/or County of Fresno and that the residents of the subject property should be prepared to accept the inconveniences and discomfort associated with normal farm activities. The “Right to Farm” covenant shall be recorded prior to or concurrent wit h the recording of any Final Map of Vesting Tentative Tract Map No. 6360.
5. The subdivider shall comply with Regulation VIII and Rule 8060 of the San Joaquin Valley Air Quality Pollution Control District for the control of particulate matter and fugitive dust during construction of this project.
6. Submit grading plans and a soils report to the City of Fresno Planning and Development Department for verificati on prior to Final Map approval . Grading plans shall indicate the location of any required walls and indicate the proposed width of required landscape easements or strips. Approval of the grading plan is required prior to Final Map approval.
7. At the time of Final Map submittal, the subdivider shall submit engineered construction plans to the City of Fresno Public Works, Public Utilities, and Planning and Development Departments for grading, public sanitary sewer system, public water system, street lighting system, public streets, and storm drainage, including other technical reports and engineered plans as necessary to construct the required public improvements and work and applicable processing fees.
8. All plans for on- site and off -site improvements included in the Conditions of Approval shall be submitted prior to the final map being processed for recordation.
9. Public utilities easements, as necessary, shall be shown on the Final Map and dedicated to the City of Fresno. Public utility easements beyond the limits of the Final Map, but required as a condition of development, shall be acquired at the subdivider’s cost and shall be dedicated by separate instrument at the time of Final Map approval. The relocation of existing utilities necessitated by the required Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
public improvements shall be paid for by the subdivider. The subdivider is responsible to contact the appropriate utility company for information.
10. Comply with the conditions, policies and standards set forth in the City of Fresno, Municipal Code, Chapter 15, “Land Divisions;” Resolution No. 68-187, “City Policy with Respect to Subdivisions;” and City of Fresno Standard Specifications, 2002 Edition, and any amendments thereto.
11. The developer/owner shall pay applicable fees for, but not limited to, plan checks for street improvements and other grading and construction; street trees, street signs, water and sewer service, and inspections in accordance with the City of Fresno Master Fee Schedule (City Resolution No. 79- 606 and No. 80- 420) and any amendments, modifications, or additions thereto; and in accordance with the requirements of State law as related to vesting tentative maps.
12. The subdivider shall furnish to the City acceptable security to guarantee the construction of the off-site street improvements in accordance with all applicable provisions of the Fresno Municipal Code (FMC) and the State Subdivision Map Act. The subdivider shall complete all the public improvements prior to the approval of the Final Map by the City. If, at the time of Final Map approval, any public improvements have not been completed and accepted in accordance with the standards of the City, the subdivider may elect to enter into an agreement with the City to thereafter guarantee the completion of the improvements.
13. As a condition of Final Map approval, the subdivider shall furnish to the City a subdivision guarantee listing all parties having any right, title or interest and the nature of their interest per State law.
14. Vesting Tentative Tract Map No. 6360 dated November 21, 202 2 is subject to approval of related Planned Development Permit Application No. P22-00387.
15. Planned Development Permit Application No. P22-00387, filed to establish a 326- lot planned development, shall be approved prior to final map approval.
16. Comply with the requirements of FMC Chapter 15, Article 40, relative to subdivisions that include common ownership, as appropriate.
MITIGATION MONITORING REQUIREMENTS
17. Vesting Tentative Tract Map No. 6360 dated November 21, 2022, is subject to compliance with the mitigation measures established by the certification of Final Environmental Impact Report (FEIR) State Clearinghouse (SCH) No. 2022080152 prepared for Vesting Tentative Tract Map No. 6360.
GENERAL INFORMATION
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
18. When the grading plan establishes a top of slope beyond the required landscape easement noted and the construction of the required wall is to be established coincident with the top of slope, then the required minimum easement width shall be expanded to include the full landscaped area up to the wall location.
19. The long- term maintenance of all the items listed below is the ultimate responsibility of the owner/developer.
a) The property owner shall be responsible for providing for the maintenance of all landscaping and hardscaping located within proposed Outlots associated with the proposed project.
b) The property owner shall be responsible for providing for the maintenance of all landscaping and hardscaping located in any entry median island or traffic medians located within the project.
c) The property owner shall be responsible for providing for the maintenance of the curbs and gutters, valley gutter, sidewalks, street lights and street signage within any local public street rights-of-way associated with the project.
d) The property owner shall be responsible for providing for the maintenance of all street trees within any local public street rights -of-way associated with the project.
20. Maintenance of the required landscape easements, streets, curbs and gutters, sidewalks, medians, and street furniture may be the responsibility of the City’s Community Facilities District. Contact the Public Works Department, Engineering Services Division, at 559-621-8695 for information regarding the City’s Community Facilities District. The property owners may petition the City for annexation to the City’s Community Facilities District prior to Final Map approval.
21. If the developer/subdivider elects to petition for annexation into the City’s Community Facilities District, the subdivider/owner shall be required to provide the City of Fresno, Department of Public Works, with copies of signed acknowledgments from each purchaser of a lot within the subdivision, attesting to the purchasers understanding that the lot will have an annual maintenance assessment and that he/she is aware of the estimated amount of the assessment.
The subdivider/owner shall execute and record a covenant on each lot providing notice that the subject property is subject to annual payment of the Community Facilities District assessment.
22. Should the City Council not approve the annexation of any or all of the maintenance items listed above, then the property owner/subdivider shall create a homeowners association for the maintenance of these items and proposed private streets, utilities, and walls/gates. The proposed Declaration of Covenants, Conditions, and Restrictions (CC&Rs) and the proposed instruments for the Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
homeowners association shall be submitted to the Planning and Development Department for review two weeks prior to Final Map approval. Said documents shall be recorded with the Final Map or alternatively submit recorded documents or documents for recording prior to final acceptance of subdivision improvements.
Said documents shall include assignment of responsibility to the homeowners association for landscaping and other provisions as stated in the Planning and Development Department Guidelines for preparation of CC&Rs dated January 11, 1985.
23. The proposed landscape and pedestrian easements along the major street frontages of the subdivision shall be identified as Outlots to be dedicated to the City of Fresno, in fee, for public landscape, pedestrian, and utility purposes on the Final Map. The City Engineer may discretionarily require modification to other public easements proposed when/where such easements are preferred to be identified as Outlots to be dedicated to the City, in fee.
Walls/Fences/Landscaping
24. Provide and dedicate an outlot for public bicycle, pedestrian, and landscape (trail) purposes (and irrigation system), pursuant to the requirements of the Department of Public Works memorandum dated April 24, 2024. This outlot shall be located adjacent and run parallel to East McKinley Avenue along the southern side of of the street between the bridge to Armstrong Avenue (as depicted on Vesting Tentative Tract Map No. 6360 dated November 21, 2022).
25. Provide and dedicate an outlot for private common space as depicted on Vesting Tentative Tract Map No. 6360 dated November 21, 2022.
26. Construct a minimum 6- foot decorative solid masonry wall (at finished grade of proposed site) pursuant to the solid wall requirements of Section 15- 2006 of the FMC. The decorative wall shall be located along the entirety of the subdivision boundary,
including along East McKinley and North Armstrong Avenues and east and north property lines, excepting openings for private entry gates. Said wall shall be depicted on the related site plan exhibits.
27. Landscaping, which is compliant with the City of Fresno “Anti-Graffiti Landscaped Buffer Development and Planting Standards,” shall be required adjacent to all required walls or fences that are accessible to the public and shall be maintained in accordance with the Maintenance Obligations stipulated herein below; or, in a manner which provides appropriate security and is deemed acceptable to both the City of Fresno Planning and Development and Public Works Departments.
28. The subdivider is required to provide street trees on all street frontages per Fresno Municipal Code standards and is responsible for the dedication of public planting and buffer landscape easements as determined by the Planning and Development and Public Works Departments.
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
a) Street trees shall be planted at the minimum rate of one tree for each 60 feet of street frontage; or, one tree per home (whichever is greater) by the developer.
i) The subdivider is required to provide irrigation for all street trees. The irrigation system shall comply with FMC Section 15-2309.
• NOTE: Irrigation systems shall comply with the requirements of the California Green Building Standards Code and/or the California Model Water Efficient Landscape Ordinance and/or California Plumbing Code as may be amended.
29. Provide a corner cut -off area at all street intersections in accordance with the requirements of the Fresno Municipal Code. Corner cut -offs are established to provide an unobstructed view for vehicular and pedestrian traffic approaching an intersection. They are a triangular area formed by the property lines and a diagonal line adjoining points on the property lines, measured a specific distance from the point of their intersection.
30. All proposed/required landscape easements, open space areas, pedestrian connection entryways, pathways and/or private on-site landscaping for street tree purposes shall be improved in accordance with landscape improvement plans, which are to be submitted to the Planning and Development and Public Works Departments for review and approval prior to Final Map approval.
• NOTE: Lighting and fence/wall details for any proposed/required open spaces areas or pedestrian connections shall be provided with the submittal of the landscape improvement plans.
a) Any proposed improvements within Pacific Gas & Electric (PG&E) or Fresno Irrigation District (FID) easement areas will require approval by the respective service provider/district agency prior to approval or acceptance by the City of Fresno.
i) Easement Encroachment Applications and/or Agreements will be required as dictated by the respective service provider/district agency and will be required to be executed prior to issuance of permits for improvements.
PROPERTY DEVELOPMENT STANDARDS
31. Development of the subject property shall comply with all development standards of the RS-5 zone district and FMC Sections 15-903, 15-904, and 15-905; and, all applicable requirements of the Fresno Municipal Code, unless otherwise specified in Exhibits A-1 to A-10 dated March 29, 2023.
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
a) Rear yard setbacks for lots abutting the north and east property lines (lots 132- 168) shall be a minimum of 10 feet to living space.
b) Side yard setback of lot abutting east property line (lot 169) shall be a minimum of 10 feet; or, a minimum of five feet if developed with a single-story home.
Provide a section in the CC&R’s for the Homeowners Association (HOA) prohibiting parking in driveways less than 18’ from garage to back of sidewalk (to prohibit parking over the sidewalk, if any). The CC&R’s must also state that the HOA is responsible for enforcement of said requirement.
*Buildings shall not be permitted to be located within a PUE
32. Each side of a building that is visible from a public street or park shall be designed with a complementary level of detailing and quality of materials (i.e., if the rear or side yard of a lot abuts a public street, a two-story structure should provide design features on the second story which are consistent with the primary façade).
Lot Dimensions
33. Lot dimensions shall match those depicted on Vesting Tentative Tract Map No. 6360 dated November 21, 2022, excepting changes as required per the conditions of approval.
Lot Coverage
34. Lot coverage shall comply with Exhibits A -1 to A -10 dated March 29, 2023.
Additionally, lot coverage shall comply with the requirements of the Fresno Metropolitan Flood Control District.
Building Height
35. The maximum building height allowed is 35 feet pursuant to the requirement of the FMC.
INFORMATION
36. Prior to the issuance of building permits for the subdivision, school construction fees shall be paid to the Clovis Unified School District in accordance with the school district’s adopted schedule of fees.
37. Contact the United States Postal Service for the location and type of mailboxes to be installed in this subdivision.
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
a) It is recommended that at least 6 months prior to the first occupancy, the Developer shall contact the local United States Postal Service representative to complete a Mode of Delivery Agreement for New Construction. The Mode of Delivery Agreement must hav e a District approval signature to be valid. In addition to completing the Agreement, the Developer shall provide a final map (with address details) to the local USPS representative. The Developer shall, at their own expense, procure, construct and install all mail receptacle facilities for each location as specified and approved by the USPS.
38. Pursuant to Section 66456.1 of the Subdivision Map Act, which states “The right of the subdivider to file multiple Final Maps shall not limit the authority of the local agency to impose reasonable conditions relating to the filing of multiple Final Maps,” multiple final maps filed by the subdivider on this tract shall fully and independently conform to all provisions of the Fresno Municipal Code, Subdivision of Real Property.
39. The developer/owner shall obtain any and all permits required for the removal or demolition of any existing building or structure located within the subdivision boundaries. The developer/owner shall also obtain any and all permits required for the proper abandonment/closure of any existing water well, septic tank/leach field or cesspool, and irrigation pipeline on the subject property. All such permits shall be obtained prior to commencement of tract grading work, in accordance with Chapter 13 of the Fresno Municipal Code.
40. If archaeological and/or animal fossil material is encountered during project surveying, grading, excavating, or construction, work shall stop immediately.
41. If there are suspected human remains, the Fresno County Coroner shall be immediately contacted (business hours: (559) 268- 0109; after hours the contact phone number is (559) 488-3111 for the Fresno County Sheriff’s Department). If remains or other archaeological material is possibly Native American in origin, the Native American Heritage Commission (phone number (916) 653- 4082) shall be immediately contacted, and the California Archaeological Inventory/Southern San Joaquin Valley Information Center (phone number (805) 644- 2289) shall be contacted to obtain a referral list of recognized archaeologists.
42. If animal fossils are uncovered, the Museum of Paleontology at the University of California, Berkeley shall be contacted to obtain a referral list of recognized paleontologists. An assessment shall be conducted by a paleontologist; if the paleontologist determines the material to be significant, a recommendation shall be made to the City as to any further site investigation or preservation measures.
43. Apportionment of Special Assessment: If, as part of this subdivision, a division will be made of any lot or parcel of land upon which there is an unpaid special assessment levied under any State or local law, including a division into condominium interest as defined in Section 783 of the Civil Code, the Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
developer/owner shall file a written application with the City of Fresno Director of Public Works, requesting apportionment of the unpaid portion of the assessment or pay off such assessment in full. If the subdivider elects to apportion the assessment, the application shall contain the following information:
a) A full description of each assessed lot, parcel or interest to be divided and of how such lot, parcel or interest will be divided;
b) A request that the Engineer apportion the amount remaining unpaid on the assessment in accordance with applicable law; and
c) Written consent of the owner(s) of each such lot, parcel, or interest to the requested apportionment.
d) The application shall be filed prior to the approval of the Final Map(s) by the City and shall be accompanied by a fee in an amount specified in the Master Fee Resolution for each separate lot, parcel, or interest into which the original assessed lot, parcel or interest is to be divided. The fee shall be in an amount sufficient to pay all costs of the City and the Engineer of Work responsible for determining the initial assessment in making the requested apportionment.
44. Solid waste disposal for the subdivision shall be provided by the City of Fresno.
The method of collection to be utilized in this tract shall be subject to approval of the Solid Waste Manager (see below-noted conditions).
RIGHT-OF-WAY ACQUISITION
45. The developer will be responsible for the acquisition of any necessary right-of-way to construct any of the required improvements.
46. Rights-of-way acquisition shall include any rights -of-way necessary for proper drainage, signing, pole relocation, and shoulder grading. In general, this will require right-of-way to be provided approximately 10 feet outside the travel lane.
The exact requirement must be determined at the project design stage based on the existing conditions and detailed design information.
47. In the event an acquisition of any easement or right-of-way is necessitated by the subject development, said acquisition will be accomplished prior to Final Map approval. The developer/owner should contact the Real Estate Section of the Public Works Department to receive procedural guidance in such acquisitions.
48. Should such acquisition not be accomplished by the subdivider prior to Final Map approval, the subdivider must request and grant to the City the full authority to attempt acquisition either through negotiation or through its power of eminent domain. The su bdivider shall furnish to the City Public Works Department, Engineering Division/Real Estate Section, an appraisal report or a request for an Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
estimated appraisal amount (to be determined by the City of Fresno Real Estate Section) prior to preparation of a Subdivision Agreement.
49. The subdivider/owner shall submit adequate security in the form of a cash deposit to guarantee payment of all costs associated with the acquisition, including staff time, attorney's fees, appraisal fees, court costs, and all related expenditures and costs necessary to effect the acquisition of such easements or rights-of-way.
STREETS AND RIGHTS-OF-WAY
50. The subdivider shall furnish to the City acceptable security to guarantee the construction of the off -site street improvements in accordance with all applicable provisions of the FMC and the State Subdivision Map Act.
51. The subdivider/owner shall make provisions for disabled persons in accordance with the Department of Public Works standards and as required by State law.
Handicap access ramps are required to be constructed in sidewalks at all corners within the limits of the tract. Where street furniture is located within the sidewalk area (fire hydrants, streetlights, etc.), a minimum of 48 inches of unobstructed path shall be maintained to satisfy the American Disabilities Act requirements. If necessary, dedicate a pedestrian easement to accommodate for the four foot minimum unobstructed path requirement.
52. All of the required street improvements shall be constructed and/or installed in accordance with the City of Fresno Standard Specifications (2002 Edition). The following shall be submitted as a single package to the Public Works Department for review and approval:
a. Signing and striping plans (per current California Department of Transportation standards);
b. Street Construction Plans;
c. Landscape and irrigation plans (median island and street trees within all parkways).
53. The subdivider shall construct an underground street lighting system per Public Works Standards within the limits of the tract. Spacing and design shall conform to Public Works Standards. Height, type, spacing, etc., of standards and luminaries shall be in accordance with Resolution No. 68-187, 78-522, 81-219, and 88-229 or any modification thereto approved by the City Traffic Engineer prior to Final Map approval. Upon completion of the work by the subdivider and acceptance of the work by the City, the street lighting system shall be dedicated to the City. Submit engineered construction plans to the Public Works Depar tment for approval.
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
54. All dead-end streets created by this subdivision shall be properly barricaded in accordance with City standards within seven days from the time the streets are surfaced or as directed by the City Engineer.
DEPARTMENT OF PUBLIC WORKS
55. Comply with all of the requirements included within the attached Public Works Department, Land Planning memorandum dated April 25 , 202 4 and redlined Exhibit A for Vesting Tentative Tract Map No. 6360 and Planned Development Permit Application No. P22-00387 dated November 21, 2022.
56. Comply with all of the requirements included within the Attached Public Works Department, Traffic Operations and Planning memorandum dated June 19, 2023.
57. Comply with all of the requirements included within the attached Public Works Department, Traffic Operations and Planning memorandum regarding maintenance/service requirements dated June 26, 2024.
58. Comply with all of the requirements included within the attached Public Works Department, Traffic Operations and Planning memorandum regarding street tree requirements dated March 8, 2023
DEPARTMENT OF PUBLIC UTILITIES
59. Comply with all of the requirements included within the attached Public Utilities Department memorandum dated December 16, 2022.
FIRE SERVICE
60. Comply with all of the requirements from the Fire Department memorandum dated December 18, 2022.
FRESNO COUNTY ENVIRONMENTAL HEALTH DIVISION
61. Comply with all of the requirements from the Fresno County Environmental Health Division memorandum dated December 12, 2022.
FLOOD CONTROL AND DRAINAGE (FMFCD)
62. Comply with all of the requirements from the F MFCD memorandum dated December 27, 2022.
FRESNO IRRIGATION DISTRICT (FID)
63. Comply with all of the requirements from the F ID memorandum dated December 19, 2022.
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
CLOVIS UNIFIED SCHOOL DISTRICT (CUSD)
64. Comply with all of the requirements from the C USD memorandum dated December 14, 2022.
PACIFIC, GAS & ELECTRIC (PG&E)
65. Comply with all of the requirements from the PG&E memorandum dated December 22, 2022.
DEVELOPMENT FEES AND CHARGES
66. The following fees are based on preliminary conceptual information. The exact fee obligation will be computed prior to Final Map approval by Public Works Department, Land Division & Engineering. The fee rates in effect at the time of Final Map approval, determined by the Master Fee Schedule, shall apply (Reso.
No. 2016-258).
SEWER CONNECTION CHARGES FEE RATE
a. Lateral Sewer Charge [1] $0.10/sq. ft. (to 100' depth)
b. Oversize Charge [1] $0.05/sq. ft. (to 100' depth)
c. Trunk Sewer Charge [2] $344/living unit
Service Area: Fowler
d. Wastewater Facilities Charge [3] $2,119/living unit
e. Fowler Trunk Sewer Interim Fee Surety [1] $893/living unit
f. House Branch Sewer Charge [2] N/A
WATER CONNECTION CHARGES FEE RATE
g. Service Connection Charge Fee based on service(s) and meter(s) sizes specified by
owner; fee for service(s) and
Meter(s) established by the
Master Fee Schedule.
h. Frontage Charge [1] $6.50/lineal foot
i. Water Capacity Fee* [1]
Conditions of Approval
Vesting Tentative Tract Map No. 6360
July 3, 2024
Single Family Residential $5,684/ 1” Meter/living unit
Irrigation $5,684/ 1” Meter
$7,106/ 1½” Meter
$14,206/ 2” Meter
*Fee based on meter(s) sizes specified by owner; fee for Water Capacity established by the Master Fee Schedule.
CITYWIDE DEVELOPMENT IMPACT FEES FEE RATE
j. Fire Facilities Impact Fee – Citywide [4] $2,285/living unit
k. Park Facility Impact Fee – Citywide [4] $3,566/living unit
l. Quimby Parkland Dedication Fee [2] $1,542/living unit
m. Police Facilities Impact Fee – Citywide [4] $948/living unit
o. Citywide Regional Street Fee [3] $8,783/adj. acre
p. New Growth Area Major Street Fee [3] $27,490/adj. acre
q. Traffic Signal Charge [1] $762/living unit
Notes:
The Board of Directors of the Fresno County Regional Transportation Mitigation Fee Agency approved Resolution No. 2009 – 01 requiring the payment of Regional Transportation Mitigation Fee. The effective date of this resolution is January 1, 2010.
Contact the Council of Fresno County Governments (FCOG) to determine this fee obligation. Confirmation by the FCOG is required before the City of Fresno can issue building permits.
On December 8, 2016, Fresno City Council adopted Resolution No. 2016- 258, effective July 1, 2018, administratively updating the impact fees adjusted by this resolution annually to the percentage change in the 20-City Construction Cost Index as reported in the Engineering News Record (ENR) for the 12- month period ending of May of the year of adjustment.
[1] Deferrable through Fee Deferral Covenant.
[2] Due at Final Map.
[3] Due at Building Permit.
[4] Due at Certificate of Occupancy.