Blackstone McKinley BNSF Grade Separation Project
Project Background
 Eliminates two at‐grade crossings
 Four Pedestrian/Motorist Fatalities in last 10 years
 Average Daily Delay of 2‐minute, 48‐second for each Motorist  Pedestrian and student risk and delay
Project Benefits
 Eliminate pedestrian and vehicle conflicts with trains  Improve safety and operations
 Decrease traffic and BRT interruptions, increase travel reliability  Elimina
te train horns at these two at‐grade crossings
Project Funding
 FCTA (Measure C) Funding
 $80 million State Transit and Intercity Rail Capital Program (TIRCP) Grant  Local Partnership Program (LPP) Grant

HOME AVE

PINE AVE

FLORADORA AVE

HOME AVE

UNIVERSITY AVE UNIVERSITY AVE

CALAVERAS ST

EFFIE ST

PERALTA WY

GLENN AVE

BLACKSTONE AVE

BNSF RR
McKINLEY AVE

FRESNO CITY COLLEGE

ACCESS ROAD
TO HWY 41
TO HWY 99
TO HWY 180
TO E. SHIELDS
SHOOFLY =FUTURE TRACK

BLACKSTONE AVE BRIDGES

PROPOSED PUMP

STATION LOCATION
McKINLEY AVE BRIDGES

• Complete Design –Summer/ Fall 2025
• Complete Acquisition of Right of Way
(Including site preparation) –Summer
2025
• Start Construction –Spring 2026
• Complete Construction‐Spring 2029