Attachment A

ADDITIONAL SCOPE OF SERVICES
Consultant Service First Amendment to Agreement between City of Fresno (City) and AECOM Technical Services, Inc., (Consultant)
BNSF Blackstone McKinley Grade Separation Project

Additional Scope of Services includes, but is not limited to:

Additional Scope of Services

Project Management / Project Coordination
Project Management efforts in support of the additional services. This includes typical project management, invoicing, progress reports, budget management, meetings, and quality control.

Detoured Roadways
Development of alternatives for roadway staged construction. This includes development of realignments for McKinley and Blackstone Avenues temporarily as a form of staging construction and rerouting traffic around the primary activities of grade separation construction to reduce the duration of construction and pose less risk by avoiding greater commingling of construction with public traffic circulation. The additional effort for the detoured roadways was not part of the original scope. The detoured roadways will be incorporated into the design.

BNSF Coordination
Consultant will perform the necessary coordination with BNSF during the development of this project. This includes schedule meetings, prepare meeting agendas, conduct meetings, and produce draft and final meeting notes. Consultant will coordinate all design submittal reviews with BNSF and maintain a submittal and design/RFI log.

3D Visual Simulation (Used for Renderings)
This includes preparation of one three 3D visual simulation model and three versions of rendering exhibits for: the City of Fresno press conference, updates for the first community meeting, and updated again for the second community meeting.

Hydraulic Modeling
During design and in coordination with Fresno Municipal Flood Control District (FMFCD), it was requested that Consultant perform the Storm Drain System Modeling for the project.

Consultant to complete hydraulic model and coordinate reviews/acceptance with FMFCD.

Drainage System Temporary Relocation
During the development of the project, the City has requested to temporarily realign McKinley and Blackstone Avenues, which provide the opportunity to relocate the storm