FISCAL IMPACT STATEMENT

PROGRAM: Southwest Fresno Trail - California Avenue to West Avenue 209900181 (PW00849) Invitation No. 12500364

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT
COST

Direct Cost
$ 2,099,923

Indirect Cost
$1,734,200

TOTAL COST
$ 3,834,123

Additional
Revenue or Savings
Generated

Net City Cost
$ 3,834,123

Amount Budgeted
(If none budgeted,
identify source)
$ 2,785,500

Indirect cost consists of the following:

Preliminary Engineering $ 555,400
Right of Way $ 203,500
Construction Utility $ 14,312
FID Canal Construction $ 594,994
Construction Engineering $ 156,000
Contingency
$ 209,994
Total $1,734,200

.

The Southwest Fresno Trail - California Avenue to West Avenue Project is grant funded by the Transformative Climate Communities (TCC) grant.