FISCAL IMPACT STATEMENT

PROGRAM: Cary and Vinland Park Improvements Project

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $578,657.31

Indirect Cost $401,200.20

TOTAL COST $979,857.51

Additional
Revenue or Savings
Generated

Net City Cost $979,857.51

Amount Budgeted
(If none budgeted,
identify source) $839,800.00

SUMMARY OF INDIRECT COST:

Cary Park

Preliminary Engineering $142,791.00
Construction Engineering $90,600.00
Contingency $9,939.00
Sub Total $243,330.00

Vinland Park

Preliminary Engineering $90,766.20
Construction Engineering $48,100.00
Contingency $19,004.00
Sub Total $157,870.20

Indirect Cost Total $401,200.20