1 AWARD DATE 2/23/23
Contract Awarded By: X City Council Informal
PROJECT: SHEET 1 of 1
,
Q&D Construction ,CONTRACTOR
Change requested by: City of Fresno - Airports Department I.

A. $2,506,060.55
Project _AC 00413_ GL_439900061-CCNT 4200-4230-9999-871-757507-43-0 $2,506,060.55
III. CONTRACT TIME
Purchase Order Adjustment Project Mgr: Date
Line 1 Fund Org Project Resource Finance: Date Line 2 Fund Org Project Resource CIP PO Increase Statement of Contract Time No. Days Date
Estimated X Exact 2,506,060.55$ Decrease Date of Notice to Proceed Apr 10, 2023 126,868,863.00$ Contract Working X Calendar Days 852 -$ Computed Date for Completion Aug 9, 2025 Time extension days this CCO 140
Total time extension days all CCO's 140
Net change in Contract Price is Weather Days thru Dec. 5, 2025 0 percent of the original Contract Price 1.975% Suspended Days through Dec. 5, 2025 0 Revised Contract Price 129,374,923.55$ Extended Date for Completion Dec. 27, 2025 Dec. 27, 2025
Accepted Date: Contractor:

Signed By: Title:

If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work.

Approval Recommended Date
Airports Construction Manager
Authorized:  City Manager/Designee
(if change orders or total of change orders exceed 5 percent of contract price) Authorized:  City Council Meeting Dated: ___ __________________ (if change order or total change orders exceed 10 percent of contract price or if individual change order) exceeds Fresno City Charter limit or Section 33422 Health and Safety Code for Agency contracts.) Approved:  Director of Aviation Date
FAT Terminal Expansion Project
PROJECT ID NOS: 32300404
following described work not included in the plans and specifications on this contract.

NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED.

CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.

Cost of this Change Order

Mary Boyajian
Jarred Garza
ADD One Hundred and Forty (140) Days in this change order City of Fresno - Airports Department
CONTRACT CHANGE ORDER NO.

Airports Projects Division 4995 E. Clinton Way Fresno, CA 93727 Phone (559) 621-4534 You are hereby requested to make the herein descr ibed changes from the plans and specifications or do the TO:

Submitted By
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the price shown above.

BID FILE NO.P.O. NO:
2,506,060.55$
including this Change Order
Total Contract Changes
Substantial Completion
II. CONTRACT PRICE
Additional extra scope added to expand FIS Arrivals Hall and Plaza Inspector
Approved Cost Changes to Date
Original Contract Price
S:\Shizen Office Folder\TERMINAL Project File Structure\7.0 Cost Management\7.4 Change Orders\7.4.2 Construction Phase\7.4.2.2 Contract Change Orders (CCO)\Council Change Order\CCO 1 FAT Terminal Expansion.xls TAB: A 11/5/2024 4:27 PM