Capital  Projects  Department

BUILDING A BETTER FRESNO
Community Workforce Agreement
Annual Review

Capital Projects Department
Annual Workshop – Community Workforce Agreement
Term of Agreement
• Fully executed on September 29, 2021
• Became effective 120 days later (January 27, 2022)
• Initial 5-year term
• Review of Local Hiring Program effectiveness at 2-year mark • Requires annual reports to the Council
2 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Goals of Agreement
• Employment and training opportunities
• Pathways into high-quality, sustainable construction careers • Create a pool of skilled construction labor
• Combat unemployment and underemployment
• Promote efficiency through skilled labor
• Diversity, workforce equity, open opportunity
• Recruitment, training and employment of local area residents • Local pre-apprenticeship and apprenticeship programs
• Timely and successful completion of City projects
3 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Key Provisions
• Applies to awarded construction contracts with Engineer’s Estimates of $1,000,000 and greater (with some exclusions) • Applies to work performed by craft workers, not products • Requires approval by the funding agency
• Pre-job conferences and Joint Administrative Committee • Recognizes the Unions as sole bargaining representative • Union referrals of employees to Contractors, with some ability for non-signatory Contractors to utilize Core Workers
• Payments by employers to Union vacation, pension, health benefit funds
• Apprentices
• Local Hiring Program
4 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Local Hiring Program
• Unions agreed to exert their utmost efforts to achieve the goals • Contractors to demonstrate satisfaction of percentage goals, or demonstrate a good faith effort
• Minimum 50% of journey-level project work hours by City of Fresno residents
• Minimum 55% of apprentice-level project work hours by City of Fresno residents
• Minimum 30% of apprentice-level project work hours performed by New Local Apprentices
5 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Active PLA Construction Contracts:
• Fresno Area Express Facility Improvement
Project (AMG & Associates, Inc.)
• Fresno Street Corridor (A-C Electric)
• Tulare Complete Streets (Agee Construction)
• Blackstone Ave and McKinley Avenue Transit
Oriented Development - Blackstone TOD
(Emmett’s Excavation)
• Barstow Ave Class IV Bikeway Project
(American Paving)
• Clean CA Downtown Neighborhood
Beautification and Cleanup Project (Granite
Construction)6
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Active PLA Construction Contracts, continued:
• Substation Expansion at the Regional Wastewater
Reclamation Facility (A-C Electric Company)
• Replacement and Repairs of Structural Components at
the RWRF Headworks Building – Phase 1
(Ashron Construction)
• Water Main Replacement Bounded by W. Clinton, W.

University, N. Fruit, and N. Teilman Avenues
(Dawson-Mauldin, LLC.)
• Rebid Requirements Contract to Furnish and Install
Polyethylene Water Service Replacements (West Valley
Construction)
7 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Completed PLA Construction Contracts as of August 23, 2024:
• Van Ness and Weldon Pocket Park (Bush Construction)
• Sewer Rehab Improvements – Area bound by Blackstone, Maroa, McKinley, and Clinton Ave (Emmett’s Excavation)
• Cleaning of Digester #1 and Cleaning/Rehabilitation of Digester #12 at the RWRF (F.D. Thomas)
• Water Main Replacement in Calwa Townsite, Phase 1 (West Valley Construction)
• Water Main Replacement along E Jensen Ave between S Clovis and S Fowler Avenues (Emmett’s Excavation)
8 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Local Hire Program Statistics – Since Inception of PLA
January 27, 2022 to January 31, 2024
Total PLA Contracts Awarded 26
Completed PLA Contracts 5 Full Time Equivalent
Total PLA Current Contract Amount $86,885,686.00 Job Results Total PLA Project Hours 129,513.89 62.3
Total PLA Journeyman Hours 108,111.53 52.0
Total PLA Apprentice Hours 20,714.73 10.0
Overall COF Resident Journeyman Hours 44,705.15 21.5
Target Value: Minimum 50% of Hours 42% - Goal not met
Overall COF Resident Apprentice Hours 6,047.35 2.9
Target Value: Minimum 55% of Hours 30% - Goal not met
Overall COF Resident New Apprentice Hours 4,959.00 2.4
Target Value: Minimum 30% of Hours 23% - Goal not Met
9 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Local Hire Program Statistics – 2023 to 2024 Reporting Year February 1, 2023 to January 31, 2024
Total PLA Contracts Awarded 15
Completed PLA Contracts 5 Full Time Equivalent
Total PLA Current Contract Amount $46,250,224.75 Job Results Total PLA Project Hours 80,848.07 38.9
Total PLA Journeyman Hours 62,463.79 30.0
Total PLA Apprentice Hours 13,990.48 6.7
Overall COF Resident Journeyman Hours 15,989.43 7.7
Target Value: Minimum 50% of Hours 26% - Goal not met
Overall COF Resident Apprentice Hours 3,442.60 1.7
Target Value: Minimum 55% of Hours 25% - Goal not met
Overall COF Resident New Apprentice Hours 2,990.60 1.4
Target Value: Minimum 30% of Hours 21% - Goal not Met
10 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Two-year Anniversary Written Notice
• Fresno, Madera, Kings and Tulare Counties Building and Construction Trades Council were provided written notice of percentage requirements not being met in July 2024.
• Subsequently, Trades Council and the City held a Meet and Confer conference on September 9, 2024 to discuss status and established desire to assess options to improve outcomes.
11 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Capital Projects Bidding Outlook
12 Projects to be Awarded in FY 25 or Later
95 Sum of all Construction
409,410,060$
Construction Value for PLA Projects
95 51
Construction Value by Threshold
95 51
95 21
95 12
Projects with Award Date of
FY 25 or Later
Number of Projects above $3 Million
Number of Projects above $5 Million
390,646,410$
390,646,410$
317,594,026$
286,963,847$
Project Breakout by Threshold Amount
Potentially Applicable for PLA
Total Project Count
Projects above $1 Million
Number of Projects above $1 Million
95 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Bidding Outlook - Project Category Distribution
13 $42,374,583 $33,130,815
$5,868,240
$42,883,141
$92,579,825
$192,573,457
$0
$50,000,000
$100,000,000
$150,000,000
$200,000,000
Parks (22) Trails  (5) Traffic  Signals (6) Utilities  (18) Roadways  (36) Large  Structures (8) Capital Projects Department
Annual Workshop – Community Workforce Agreement
Parks Category Projects (22 Total)
14 $6,503,977.40
$35,870,605.35
$28,188,229.35
$24,788,229.35
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
>$ 1 Million > $3  Million > $5  MillionNon‐PLA (< $1 Million) 14 Projects
8 Projects
3 Projects
2 Project
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Trails Category Projects (5 Total)
15 $707,395.00
$32,423,420.00
$28,094,700.00
$24,544,000.00
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
>$ 1 Million > $3  Million > $5  MillionNon‐PLA (< $1 Million) 1 Project
4 Projects
2 Projects
1 Project
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Traffic Signal Category Projects (6 Total)
16 $1,695,225.00
$4,173,015.00
$0.00 $0.00
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
>$ 1 Million > $3  Million > $5  MillionNon‐PLA (< $1 Million) 3 Projects
3 Projects
0 Projects 0 Projects
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Utility Infrastructure Category Projects (18 Total)
17 $5,235,347.93
$37,647,793.00
$28,305,100.00 $28,305,100.00
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
$30,000,000
$35,000,000
$40,000,000
$45,000,000
>$ 1 Million > $3  Million > $5  MillionNon‐PLA (< $1 Million) 9 Projects
9 Projects
3 Projects 3 Projects
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Roadway Category Projects (36 Total)
18 $3,441,400.00
$89,138,425.12
$41,612,845.00
$21,289,364.00
$0
$10,000,000
$20,000,000
$30,000,000
$40,000,000
$50,000,000
$60,000,000
$70,000,000
$80,000,000
$90,000,000
$100,000,000
>$ 1 Million > $3  Million > $5  MillionNon‐PLA (< $1 Million) 6 Projects
30 Projects
8 Projects
3 Projects
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Large Structures Category Projects (8 Total)
19 $1,180,305.00
$191,393,151.73 $191,393,151.73 $188,037,153.73
$0
$50,000,000
$100,000,000
$150,000,000
$200,000,000
$250,000,000
>$ 1 Million > $3  Million > $5  MillionNon‐PLA (< $1 Million) 2 Projects
6 Projects 6  Projects 5 Projects
Capital Projects Department
Annual Workshop – Community Workforce Agreement
Local Hiring Program – Next Steps for remainder of Agreement Year • Explore potential modifications to the Local Hiring Program with Trades Council to improve outcomes and meet percentage
requirements
• Continue to track PLA project labor implementation for three-year anniversary summary report
20 Capital Projects Department
Annual Workshop – Community Workforce Agreement
Local Hiring Program – PLA Agreement Timeline
• March 2025 – Three-year Annual PLA Report Issuance that will cover February 1, 2024 through January 31, 2025 Reporting Year If PLA targets are not met, City will issue Trades Council written notice.

At meet and confer, City and Trades Council will explore potential modifications to the Local Hiring Program to improve outcomes and meet percentage requirements.
• February 2026 – Four-year Annual PLA Report Issuance
Same process as above.
• February 27, 2027 – PLA Expiration
90 days prior to PLA expiration, at request of Trades Council or City, extension discussion can commence.
21 Annual Workshop – Community Workforce Agreement
Questions & Discussion
Capital  Projects  Department

BUILDING A BETTER FRESNO
22