FISCAL IMPACT STATEMENT

PROGRAM: Ashlan and Shields Pedestrian Countdown Heads 209900403 PW01066 Bid No. 12501082

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $ 151,655

Indirect Cost $ 70,935

TOTAL COST $ 222,590

Additional
Revenue or Savings
Generated

Net City Cost $ 222,590

Amount Budgeted
(If none budgeted,
identify source) $ 183,400

SUMMARY OF INDIRECT COSTS:

Preliminary Engineering $ 23,500
Construction Engineering $ 32,200
Contingency $ 15,235
Total $ 70,935

The Ashlan and Shields Ped Countdown Heads project is grant funded by Local Highway Safety Improvement Program (HSIP) grant. The local match required is funded by SB1 Road Maintenance and Rehabilitation Account (RMRA) funds.