Evaluation Form Rev. 07-2022

FISCAL IMPACT STATEMENT

PROGRAM:

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $817,314.75

Indirect Cost $303,154.00

TOTAL COST $1,120,468.75

Additional
Revenue or Savings
Generated

Net City Cost $1,120,468.75

Amount Budgeted
(If none budgeted,
identify source) $1,051,330.00

SUMMARY OF INDIRECT COST:

Maxie L. Community Park

Preliminary Engineering $49,208.00
Construction Engineering $43,000.00
Contingency $26,157.00
Sub Total $118,365.00

Neilson Park

Preliminary Engineering $75,561.00
Construction Engineering $53,700.00
Contingency $55,528.00
Sub Total $184,789.00

Indirect Cost Total $303,154.00
The total budget allocated for Maxie L. Community Park is $408,649 and for Neilson Park is $737,088, for a combined total budget amount of $1,145,737. Of this amount, $94,407 was expended and encumbered at the end Fiscal Year 2024. The remaining $1,051,330 was carried over to Fiscal Year 2025. This construction contract is fully funded.