Third Amendment Compensation
Task 11.8 Engineering Services During Construction
TOTAL PROFESSIONAL SERVICES FEE
Second Amendment
Revised Fee Schedule (No compensation)
First Amendment Compensation
Tasks 10 and 11 Water and Sewer Design Services for Go-Biz Task 12 CEQA Support
TOTAL PROFESSIONAL SERVICES FEE
Original Contract Amount
Phase 1: Preliminary Field Investigation & Hydraulic Analysis Phase 2: Field Investigations, Capital Cost Estimates & Downtown Area Water & Wastewater Infrastructure Improvement Study $427,370.00
$427,370.00
$0.00
$1,859,478.00
$ 140,928.00
$2,000,406.00
$293,828.00
$443,045.00
TOTAL PROFESSIONAL SERVICES FEE
Total Amended Contract Amount
$736,873.00
$3,801,877.00
With a remaining contingency
amount not to exceed $374,000.00
SCHEDULE
Project Completion December 31, 2027
6