FISCAL IMPACT STATEMENT

PROGRAM: Blackstone Avenue Roadway Improvements Minarets To Nees . 209900248 PW00929 Bid No. 12500516

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST

Direct Cost $2,732,629

Indirect Cost $1,064,271

TOTAL COST $3,796,900

Additional
Revenue or Savings
Generated $0

Net City Cost $3,796,900

Amount Budgeted
(If none budgeted,
identify source) $2,128,100

Indirect cost consists of the following:

Preliminary Engineering $ 291,100
Right of Way $ 63,200
Construction Engineering $ 436,700
Contingency $ 273,271
Total $1,064,271

The Blackstone Avenue Roadway Improvements Minarets To Nees project is federally funded by Surface Transportation Block Grant (STBG), One-Time Coronavirus Response and Relief Supplemental Appropriations Act of 2021 (CRRSAA) and small local funding contribution from SB1 Road Maintenance and Rehabilitation Account (RMRA) funds .