25-438 BSFN Neuro 250228 B007B - February Baseline Update

Fresno City Council
April 10, 2025

Document
25-438 BSFN Neuro 250228 B007B - February Baseline Update
Meeting
April 10, 2025
Body
Fresno City Council
Original file
479 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.

ID % Complete Task Name Duration Start Finish Resource
Names
1 9% Bob Smittcamp Family Neurosciences Institute 501 days Wed 5/8/24 Fri 4/24/26 2 18% PRECONSTRUCTION 338 days Wed 5/8/24 Wed 9/3/25
130 11% CONSTRUCTION (Site) 287 days Mon 1/6/25 Thu 2/19/26 131 100% Mobilization 5 days Mon 1/6/25 Fri 1/10/25
132 34% Phase 1 70 days Mon 1/6/25 Fri 4/11/25
133 46% Phase 1A 70 days Mon 1/6/25 Fri 4/11/25
134 97% Phase 1A - Demo & Grading 40 days Mon 1/6/25 Fri 2/28/25 135 100% Temp Fence setup 2 days Mon 1/6/25 Tue 1/7/25 Quiring 136 100% Safe Off Existing Utilities 5 days Mon 1/6/25 Fri 1/10/25 137 100% SWPPP Implementation 3 days Wed 1/8/25 Fri 1/10/25 Quiring 138 100% PG&E removal of gas service 0 days Sat 2/15/25 Sat 2/15/25 PG&E 139 100% PG&E De-energize and remove transformer 0 days Fri 2/21/25 Fri 2/21/25 PG&E 140 100% Clear and Grub 3 days Mon 1/13/25 Wed 1/15/25 Cencal 141 100% Demo - Building 5 days Thu 1/16/25 Wed 1/22/25 Cencal 142 100% Demo - Site 2 days Thu 1/23/25 Fri 1/24/25 Cencal 143 100% Survey - Fill qty., controls & mark offsite demo limits 1 day Thu 1/30/25 Thu 1/30/25 Bedrock 144 100% Survey - Rough grade & SD POC & phase 3 parking lot SD 1 day Mon 2/10/25 Mon 2/10/25 Bedrock 145 100% Over-Ex & Rough Grading 5 days Mon 2/17/25 Fri 2/21/25 Emmett 146 100% Demo remaining utility pad 1 day Mon 2/24/25 Mon 2/24/25 Cencal 147 75% Over-Ex & Rough grade @ Gas & Elect'l utilities 4 days Tue 2/25/25 Fri 2/28/25 Emmett 148 100% Phase 1A - Wet Utilities 12 days Mon 2/10/25 Tue 2/25/25 149 100% Storm Drain 12 days Mon 2/10/25 Tue 2/25/25
150 100% Survey SD 1 day Mon 2/10/25 Mon 2/10/25 Bedrock 151 100% *Sawcut asphalt at phase 3 parking lot for SD install 1 day Sat 2/15/25 Sat 2/15/25 Cencal 152 100% Storm Drain 4 days Thu 2/20/25 Tue 2/25/25 Grizzly 153 100% *Storm drain tie-in (Weekend Work) 2 days Sat 2/22/25 Sun 2/23/25 Grizzly 154 100% Backfill & Compact 1 day Tue 2/25/25 Tue 2/25/25 Grizzly 155 100% SD Inspection Phase 1 complete 0 days Tue 2/25/25 Tue 2/25/25 City Of Fresno 156 0% Phase 1A - Dry Utilities 25 days Mon 3/3/25 Fri 4/4/25 157 0% Site Electrical 25 days Mon 3/3/25 Fri 4/4/25
158 0% Survey light pole bases 1 day Mon 3/3/25 Mon 3/3/25 Bedrock 159 0% Site electrical & Security conduits 2 days Tue 3/4/25 Wed 3/5/25 Westech 160 0% Elect'l Underground inspection 0 days Wed 3/5/25 Wed 3/5/25 City Of Fresno 161 0% Backfill & Compact elect'l trenches 1 day Thu 3/6/25 Thu 3/6/25 Westech 162 0% Light pole bases 3 days Fri 3/7/25 Tue 3/11/25 Westech 163 0% Set site light poles 2 days Thu 4/3/25 Fri 4/4/25 Westech 164 8% Phase 1A - Site Concrete 13 days Fri 2/28/25 Tue 3/18/25 165 100% Survey C&G 1 day Fri 2/28/25 Fri 2/28/25 Bedrock 166 0% Curb & Gutter 7 days Mon 3/3/25 Tue 3/11/25 Heritage 167 0% Backfill Planter areas 2 days Wed 3/12/25 Thu 3/13/25 Emmett 168 0% Flatwork 3 days Fri 3/14/25 Tue 3/18/25 Heritage 169 0% Phase 1A - Landscaping 17 days Mon 3/10/25 Tue 4/1/25 170 0% Irrigation sleeves 3 days Mon 3/10/25 Wed 3/12/25 LDI 171 0% Fencing 5 days Fri 3/14/25 Thu 3/20/25 LDI
172 0% Landscape & irrigation 10 days Wed 3/19/25 Tue 4/1/25 LDI 173 0% Phase 1A - Grading & Paving Operations 8 days Wed 4/2/25 Fri 4/11/25 174 0% Baserock and paving 5 days Wed 4/2/25 Tue 4/8/25 Emmett 175 0% Striping and Signage 3 days Wed 4/9/25 Fri 4/11/25 TnT 176 0% Phase 1B 12 days Wed 3/19/25 Thu 4/3/25
177 0% Temp Fence Adjustment 1 day Wed 3/19/25 Wed 3/19/25 Quiring 178 0% Traffic control & sidewalk closure at Fresno and Herwaldt Dr. 1 day Thu 3/20/25 Thu 3/20/25 Quiring 179 0% Remove existing street light for re-install 2 days Fri 3/21/25 Mon 3/24/25 Westech 180 0% Drive approaches & Sidewalk at Fresno and N. Herwaldt Dr. 8 days Fri 3/21/25 Tue 4/1/25 Heritage 181 0% Reinstall light post 1 day Wed 4/2/25 Wed 4/2/25 Westech Bob Smittcamp Family Neurosciences Institute

PRECONSTRUCTION
CONSTRUCTION (Site)
1/6 Mobilization
Phase 1
Phase 1A
Phase 1A - Demo & Grading
1/6 Temp Fence setup
1/6 Safe Off Existing Utilities
1/8 SWPPP Implementation
2/15 PG&E removal of gas service
2/21 PG&E De-energize and remove transformer
1/13 Clear and Grub
1/16 Demo - Building
1/23 Demo - Site
1/30 Survey - Fill qty., controls & mark offsite demo limits 2/10 Survey - Rough grade & SD POC & phase 3 parking lot SD 2/17 Over-Ex & Rough Grading
2/24 Demo remaining utility pad
2/25 Over-Ex & Rough grade @ Gas & Elect'l utilities
Phase 1A - Wet Utilities
Storm Drain
2/10 Survey SD
2/15 *Sawcut asphalt at phase 3 parking lot for SD install 2/20 Storm Drain
2/22 *Storm drain tie-in (Weekend Work)
2/25 Backfill & Compact
2/25 SD Inspection Phase 1 complete
Phase 1A - Dry Utilities
Site Electrical
3/3 Survey light pole bases
3/4 Site electrical & Security conduits
3/5 Elect'l Underground inspection
3/6 Backfill & Compact elect'l trenches
3/7 Light pole bases
4/3 Set site light poles
Phase 1A - Site Concrete
2/28 Survey C&G
3/3 Curb & Gutter
3/12 Backfill Planter areas
3/14 Flatwork
Phase 1A - Landscaping
3/10 Irrigation sleeves
3/14 Fencing
3/19 Landscape & irrigation
Phase 1A - Grading & Paving Operations
4/2 Baserock and paving
4/9 Striping and Signage
Phase 1B
3/19 Temp Fence Adjustment
3/20 Traffic control & sidewalk closure at Fresno and Herwaldt Dr. 3/21 Remove existing street light for re-install
3/21 Drive approaches & Sidewalk at Fresno and N. Herwaldt Dr. 4/2 Reinstall light post
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 1
ID % Complete Task Name Duration Start Finish Resource
Names
182 0% AC plugs at Fresno & Herwaldt Dr. 1 day Wed 4/2/25 Wed 4/2/25 Emmett 183 0% Remove traffic control from Fresno st. 0 days Thu 4/3/25 Thu 4/3/25 Quiring 184 0% Phase 1C 8 days Wed 4/2/25 Fri 4/11/25
185 0% Temp Fence Adjustment 1 day Wed 4/2/25 Wed 4/2/25 Quiring 186 0% Grade and Pave temp walk path 5 days Wed 4/2/25 Tue 4/8/25 Emmett 187 0% New drive approach for patient drop off at Herwaldt Dr. 5 days Thu 4/3/25 Wed 4/9/25 Heritage 188 0% Remove approach and patchback sidewalk at McKenzie Ave. 5 days Mon 4/7/25 Fri 4/11/25 Heritage 189 0% *Re-stripe Temp Handicap Parking Stalls (Weekend Work) 2 days Thu 4/10/25 Fri 4/11/25 TnT 190 0% Phase 1 complete 0 days Fri 4/11/25 Fri 4/11/25
191 0% Phase 2 43 days Mon 4/14/25 Thu 6/12/25
192 0% Phase 2 - Demo & Grading 10 days Mon 4/14/25 Fri 4/25/25 193 0% Temp fence relocation 1 day Mon 4/14/25 Mon 4/14/25 Quiring 194 0% SWPPP Implementation 2 days Tue 4/15/25 Wed 4/16/25 Quiring 195 0% Safe Off Existing Utilities 1 day Tue 4/15/25 Tue 4/15/25 Westech 196 0% Clear and Grub 1 day Wed 4/16/25 Wed 4/16/25 Cencal 197 0% Demo 3 days Thu 4/17/25 Mon 4/21/25 Cencal
198 0% Survey staking rough grade 1 day Tue 4/22/25 Tue 4/22/25 Bedrock 199 0% Rough Grading 3 days Wed 4/23/25 Fri 4/25/25 Emmett 200 0% Phase 2 - Wet Utilities 5 days Mon 4/28/25 Fri 5/2/25 201 0% Survey SD 1 day Mon 4/28/25 Mon 4/28/25 Bedrock
202 0% Storm Drain 3 days Mon 4/28/25 Wed 4/30/25 Grizzly 203 0% SD Inspection 0 days Wed 4/30/25 Wed 4/30/25 City Of Fresno 204 0% Backfill & Compact 2 days Thu 5/1/25 Fri 5/2/25 Grizzly 205 0% *Storm drain tie-in (weekend work) 2 days Thu 5/1/25 Fri 5/2/25 Grizzly 206 0% Phase 2 - Dry Utilities 25 days Mon 4/28/25 Mon 6/2/25 207 0% Survey Light pole bases 1 day Mon 4/28/25 Mon 4/28/25 Bedrock 208 0% Site electrical conduit (Site lighting, security & Access control) 3 days Thu 5/1/25 Mon 5/5/25 Westech 209 0% UG Electrical Inspection 0 days Mon 5/5/25 Mon 5/5/25 City Of Fresno 210 0% Backfill & Compact elect'l trenches 1 day Tue 5/6/25 Tue 5/6/25 Westech 211 0% Bollards 5 days Tue 5/6/25 Mon 5/12/25 Westech
212 0% Light pole bases 3 days Mon 5/12/25 Wed 5/14/25 Westech 213 0% Set Light Poles 2 days Fri 5/30/25 Mon 6/2/25 Westech 214 0% Phase 2 - Site Concrete 24 days Mon 4/28/25 Fri 5/30/25 215 0% Survey concrete seat wall 1 day Mon 4/28/25 Mon 4/28/25 Bedrock 216 0% Cast-in-Place Concrete Seat wall 5 days Tue 4/29/25 Mon 5/5/25 Heritage 217 0% Survey C&G 1 day Tue 5/6/25 Tue 5/6/25 Bedrock
218 0% Curb and Gutter 5 days Wed 5/7/25 Tue 5/13/25 Heritage 219 0% Backfill planters 2 days Wed 5/14/25 Thu 5/15/25 Emmett 220 0% Flatwork 6 days Fri 5/16/25 Fri 5/23/25 Heritage 221 0% Concrete @ ADA parking stalls 4 days Tue 5/27/25 Fri 5/30/25 Heritage 222 0% Phase 2 - Landscaping 18 days Wed 5/7/25 Mon 6/2/25 223 0% Irrigation sleeves 2 days Wed 5/7/25 Thu 5/8/25 LDI 224 0% Fencing & Pedestrian Gate 5 days Thu 5/15/25 Wed 5/21/25 LDI 225 0% Irrigation & Landscape 5 days Tue 5/27/25 Mon 6/2/25 LDI 226 0% Phase 2 - Grading & Paving 8 days Tue 6/3/25 Thu 6/12/25 227 0% Baserock and Paving 3 days Tue 6/3/25 Thu 6/5/25 Emmett 228 0% *Paving (Weekend Work includes drive aisle from Herwaldt) 2 days Fri 6/6/25 Mon 6/9/25 Emmett 229 0% Striping & Signage 3 days Tue 6/10/25 Thu 6/12/25 TnT 230 0% Phase 2 Complete 0 days Thu 6/12/25 Thu 6/12/25
231 0% Phase 3 35 days Fri 6/13/25 Fri 8/1/25
232 0% Temp fence relocation 1 day Fri 6/13/25 Fri 6/13/25 Quiring 233 0% SWPPP Implementation 1 day Mon 6/16/25 Mon 6/16/25 Quiring 234 0% Safe Off Existing Utilities 1 day Mon 6/16/25 Mon 6/16/25 235 0% Demo 3 days Tue 6/17/25 Thu 6/19/25 Cencal
4/2 AC plugs at Fresno & Herwaldt Dr.
4/3 Remove traffic control from Fresno st.

Phase 1C
4/2 Temp Fence Adjustment
4/2 Grade and Pave temp walk path
4/3 New drive approach for patient drop off at Herwaldt Dr. 4/7 Remove approach and patchback sidewalk at McKenzie Ave. 4/10 *Re-stripe Temp Handicap Parking Stalls (Weekend Work) 4/11 Phase 1 complete
Phase 2
Phase 2 - Demo & Grading
4/14 Temp fence relocation
4/15 SWPPP Implementation
4/15 Safe Off Existing Utilities
4/16 Clear and Grub
4/17 Demo
4/22 Survey staking rough grade
4/23 Rough Grading
Phase 2 - Wet Utilities
4/28 Survey SD
4/28 Storm Drain
4/30 SD Inspection
5/1 Backfill & Compact
5/1 *Storm drain tie-in (weekend work)
Phase 2 - Dry Utilities
4/28 Survey Light pole bases
5/1 Site electrical conduit (Site lighting, security & Access control) 5/5 UG Electrical Inspection
5/6 Backfill & Compact elect'l trenches
5/6 Bollards
5/12 Light pole bases
5/30 Set Light Poles
Phase 2 - Site Concrete
4/28 Survey concrete seat wall
4/29 Cast-in-Place Concrete Seat wall
5/6 Survey C&G
5/7 Curb and Gutter
5/14 Backfill planters
5/16 Flatwork
5/27 Concrete @ ADA parking stalls
Phase 2 - Landscaping
5/7 Irrigation sleeves
5/15 Fencing & Pedestrian Gate
5/27 Irrigation & Landscape
Phase 2 - Grading & Paving
6/3 Baserock and Paving
6/6 *Paving (Weekend Work includes drive aisle from Herwaldt) 6/10 Striping & Signage
6/12 Phase 2 Complete
Phase 3
6/13 Temp fence relocation
6/16 SWPPP Implementation
6/16 Safe Off Existing Utilities
6/17 Demo
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 2
ID % Complete Task Name Duration Start Finish Resource
Names
236 0% (Phase 3A) Traffic control / sidewalk closure at Herwaldt street 2 days Tue 6/17/25 Wed 6/18/25 Quiring 237 0% Demo Approach & Pour back city sidewalk 5 days Thu 6/19/25 Wed 6/25/25 Heritage 238 0% Rough Grading of Site 5 days Fri 6/20/25 Thu 6/26/25 Emmett 239 0% Site Utilities (site lighting & monument signage) 5 days Fri 6/27/25 Thu 7/3/25 Westech 240 0% Seat wall footing 5 days Mon 7/7/25 Fri 7/11/25 Heritage 241 0% CMU at Seat wall 5 days Mon 7/14/25 Fri 7/18/25 McCurley 242 0% Curb and Gutter 5 days Mon 7/7/25 Fri 7/11/25 Heritage 243 0% Flatwork 5 days Mon 7/14/25 Fri 7/18/25 Heritage 244 0% Landscaping 5 days Mon 7/21/25 Fri 7/25/25 LDI
245 0% Base & Paving 3 days Mon 7/28/25 Wed 7/30/25 Emmett 246 0% Striping & Signage 2 days Thu 7/31/25 Fri 8/1/25 TnT 247 0% Phase 3 Complete 0 days Fri 8/1/25 Fri 8/1/25
248 0% Phase 4A 164 days Mon 6/16/25 Fri 2/6/26
249 0% Temp fence relocation 1 day Mon 6/16/25 Mon 6/16/25 Quiring 250 0% SWPPP Implementation 2 days Tue 6/17/25 Wed 6/18/25 Quiring 251 0% Safe Off Existing Utilities 3 days Tue 6/17/25 Thu 6/19/25 252 0% Demo 5 days Fri 6/20/25 Thu 6/26/25 Cencal
253 0% Rough Grading of Site 5 days Fri 6/27/25 Thu 7/3/25 Emmett 254 0% Site Utilities (storm drain, site lighting, bollards, landscape lighting)
10 days Mon 7/7/25 Fri 7/18/25
255 0% Fountain 60 days Tue 10/14/25 Fri 1/9/26 Vineyard 256 0% Curb and Gutter 10 days Tue 10/21/25 Mon 11/3/25 Heritage 257 0% Bollards 5 days Tue 11/4/25 Mon 11/10/25 Westech 258 0% Seat walls & Flatwork 15 days Tue 11/11/25 Wed 12/3/25 Heritage 259 0% Landscaping 15 days Mon 1/12/26 Fri 1/30/26 LDI
260 0% Baserock and Paving 3 days Mon 2/2/26 Wed 2/4/26 Emmett 261 0% Striping & Signage 2 days Thu 2/5/26 Fri 2/6/26 TnT 262 0% Phase 4B 9 days Mon 2/9/26 Thu 2/19/26
263 0% Temp Fence relocation 1 day Mon 2/9/26 Mon 2/9/26 264 0% Demo from main entrance north 2 days Tue 2/10/26 Wed 2/11/26 265 0% Flatwork from main entrance north 5 days Thu 2/12/26 Wed 2/18/26 266 0% Demo from main entrance south (*Weekend Work) 1 day Wed 2/18/26 Wed 2/18/26 267 0% Flatwork from main entrance south (*Weekend work) 2 days Wed 2/18/26 Thu 2/19/26 268 0% Phase 4 Complete 0 days Thu 2/19/26 Thu 2/19/26
269 0% CONSTRUCTION (Building) 293 days Mon 3/3/25 Fri 4/24/26 270 0% Interior Build Out 243 days Mon 3/3/25 Fri 2/13/26 271 0% Level 5 241 days Mon 3/3/25 Wed 2/11/26
272 0% Level 5 - Demo 18 days Mon 3/3/25 Wed 3/26/25
273 0% Containment-5 3 days Mon 3/3/25 Wed 3/5/25 Quiring 274 0% Safe Off-5 5 days Thu 3/6/25 Wed 3/12/25 MEP
275 0% Demo-5 10 days Thu 3/13/25 Wed 3/26/25 Bowen
276 0% Level 5 - Interior Framing 67 days Thu 3/27/25 Mon 6/30/25 277 0% Layout-5 5 days Thu 3/27/25 Wed 4/2/25 JMC
278 0% Z-clips, Hangers & Wires-5 8 days Tue 4/1/25 Thu 4/10/25 JMC 279 0% Supplemental steel for scales and deck openings-5 10 days Tue 4/1/25 Mon 4/14/25 Powers 280 0% Fireproofing-5 5 days Fri 4/11/25 Thu 4/17/25 ALcal 281 0% Priority Wall Framing / H.O.W-5 10 days Fri 4/18/25 Thu 5/1/25 JMC 282 0% Interior Framing-5 15 days Fri 5/23/25 Fri 6/13/25 JMC 283 0% Frame Inspection Milestone-5 0 days Mon 6/30/25 Mon 6/30/25 City Of Fresno 284 0% Level 5 - MEPF Rough-in 40 days Fri 5/2/25 Fri 6/27/25 285 0% Priority Overhead MEP-5 15 days Fri 5/2/25 Thu 5/22/25 MEP 286 0% In-Wall MEP Rough-5 15 days Mon 6/9/25 Fri 6/27/25 MEP 287 0% MEP rough inspections complete-5 0 days Fri 6/27/25 Fri 6/27/25 City Of Fresno 288 0% Level 5 - Interior Finishes 167 days Mon 6/16/25 Wed 2/11/26 289 0% Insulation & Drywall 36 days Tue 7/1/25 Wed 8/20/25 6/17 (Phase 3A) Traffic control / sidewalk closure at Herwaldt street 6/19 Demo Approach & Pour back city sidewalk
6/20 Rough Grading of Site
6/27 Site Utilities (site lighting & monument signage)
7/7 Seat wall footing
7/14 CMU at Seat wall
7/7 Curb and Gutter
7/14 Flatwork
7/21 Landscaping
7/28 Base & Paving
7/31 Striping & Signage
8/1 Phase 3 Complete
Phase 4A
6/16 Temp fence relocation
6/17 SWPPP Implementation
6/17 Safe Off Existing Utilities
6/20 Demo
6/27 Rough Grading of Site
7/7 Site Utilities (storm drain, site lighting, bollards, landscape lighting) 10/14 Fountain
10/21 Curb and Gutter
11/4 Bollards
11/11 Seat walls & Flatwork
1/12 Landscaping
2/2 Baserock and Paving
2/5 Striping & Signage
Phase 4B
2/9 Temp Fence relocation
2/10 Demo from main entrance north
2/12 Flatwork from main entrance north
2/18 Demo from main entrance south (*Weekend Work)
2/18 Flatwork from main entrance south (*Weekend work)
2/19 Phase 4 Complete
CONSTRUCTION (Building)
Interior Build Out
Level 5
Level 5 - Demo
3/3 Containment-5
3/6 Safe Off-5
3/13 Demo-5
Level 5 - Interior Framing
3/27 Layout-5
4/1 Z-clips, Hangers & Wires-5
4/1 Supplemental steel for scales and deck openings-5
4/11 Fireproofing-5
4/18 Priority Wall Framing / H.O.W-5
5/23 Interior Framing-5
6/30 Frame Inspection Milestone-5
Level 5 - MEPF Rough-in
5/2 Priority Overhead MEP-5
6/9 In-Wall MEP Rough-5
6/27 MEP rough inspections complete-5
Level 5 - Interior Finishes
Insulation & Drywall
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 3
ID % Complete Task Name Duration Start Finish Resource
Names
290 0% One Side Drywall-5 10 days Tue 7/1/25 Tue 7/15/25 JMC 291 0% Insulation-5 8 days Mon 7/7/25 Wed 7/16/25 CBP
292 0% Second Side Drywall-5 10 days Thu 7/17/25 Wed 7/30/25 JMC 293 0% Taping & Finishing-5 20 days Thu 7/24/25 Wed 8/20/25 JMC 294 0% Painting 20 days Thu 8/14/25 Thu 9/11/25
295 0% Prime & Paint-5 20 days Thu 8/14/25 Thu 9/11/25 Duration 296 0% Acoustical Ceilings 42 days Fri 9/5/25 Mon 11/3/25 297 0% Ceiling Grid-5 20 days Fri 9/5/25 Thu 10/2/25 Genesis 298 0% Ceiling Devices-5 15 days Tue 9/23/25 Mon 10/13/25 MEP 299 0% Above Ceiling Milestone-5 0 days Mon 10/13/25 Mon 10/13/25 City Of Fresno 300 0% Wood Ceilings-5 15 days Tue 10/14/25 Mon 11/3/25 Genesis 301 0% Drop Ceiling Tiles-5 10 days Tue 10/14/25 Mon 10/27/25 Genesis 302 0% Casework 30 days Tue 10/7/25 Mon 11/17/25
303 0% Casework and countertops-5 30 days Tue 10/7/25 Mon 11/17/25 CVC 304 0% Flooring & Wall Finishes 77 days Fri 9/5/25 Wed 12/24/25 305 0% Restroom Tile (Floor and wall)-5 15 days Fri 9/5/25 Thu 9/25/25 VCT 306 0% Sheet Vinyl flooring-5 20 days Tue 10/21/25 Mon 11/17/25 Amparan 307 0% Ceramic Tile @ lobby, waiting room & corridor-5 20 days Tue 11/4/25 Wed 12/3/25 VCT 308 0% Resilient Tile Flooring-5 10 days Tue 11/18/25 Wed 12/3/25 Amparan 309 0% Wall protection-5 15 days Thu 12/4/25 Wed 12/24/25 Genesis 310 0% Doors, Frames & Hardware 159 days Mon 6/16/25 Fri 1/30/26 311 0% Hollow Metal Door Frames-5 3 days Mon 6/16/25 Wed 6/18/25 KC&S 312 0% Aluminum Door Frames-5 10 days Fri 9/12/25 Thu 9/25/25 KC&S 313 0% Swing Doors and Install Hardware-5 10 days Fri 12/26/25 Fri 1/9/26 KC&S 314 0% Install Sliding Doors & Hardware-5 15 days Mon 1/12/26 Fri 1/30/26 KC&S 315 0% Accessories & Specialties 59 days Fri 10/10/25 Tue 1/6/26 316 0% Toilet Accessories-5 8 days Fri 10/10/25 Tue 10/21/25 Shelco 317 0% Corner guards-5 5 days Fri 12/26/25 Fri 1/2/26 Genesis 318 0% Markerboards-5 2 days Mon 1/5/26 Tue 1/6/26 Atascadero 319 0% MEPF Finish 77 days Fri 9/26/25 Fri 1/16/26
320 0% Restroom fixtures-5 10 days Fri 9/26/25 Thu 10/9/25 NESM 321 0% Fire Sprinkler Finish Trim-5 10 days Tue 10/28/25 Mon 11/10/25 RLH 322 0% HVAC Finish trim-5 10 days Fri 12/26/25 Fri 1/9/26 NESM 323 0% Electrical Finish-5 15 days Fri 12/26/25 Fri 1/16/26 Westech 324 0% Plumbing Finish-5 15 days Fri 12/26/25 Fri 1/16/26 NESM 325 0% Equipment Installation 18 days Mon 1/19/26 Wed 2/11/26 326 0% Appliances-5 3 days Mon 1/19/26 Wed 1/21/26
327 0% OFCI equipment-5 15 days Thu 1/22/26 Wed 2/11/26 328 0% Level 4 237 days Thu 3/6/25 Tue 2/10/26
329 0% Level 4 - Demo 25 days Thu 3/6/25 Wed 4/9/25
330 0% Containment-4 5 days Thu 3/6/25 Wed 3/12/25 Quiring 331 0% Safe off-4 5 days Thu 3/13/25 Wed 3/19/25 MEP
332 0% Demo-4 10 days Thu 3/27/25 Wed 4/9/25 Bowen
333 0% Level 4 - Interior Framing 62 days Thu 4/10/25 Tue 7/8/25 334 0% Layout-4 3 days Thu 4/10/25 Mon 4/14/25 JMC
335 0% Z-clips, Hangers & Wires-4 4 days Tue 4/15/25 Fri 4/18/25 JMC 336 0% Supplemental Steel-4 5 days Tue 4/15/25 Mon 4/21/25 Powers 337 0% Support beam for Operable partition-4 5 days Tue 4/22/25 Mon 4/28/25 Powers 338 0% Fireproofing-4 3 days Tue 4/29/25 Thu 5/1/25 ALcal 339 0% Priority Wall Framing/ HOW-4 10 days Fri 5/2/25 Thu 5/15/25 JMC 340 0% Interior Framing-4 10 days Mon 6/9/25 Fri 6/20/25 JMC 341 0% Frame Inspection Milestone-4 0 days Tue 7/8/25 Tue 7/8/25 City Of Fresno 342 0% Level 4 - MEPF Rough-in 30 days Fri 5/23/25 Mon 7/7/25 343 0% Priority Overhead MEP-4 10 days Fri 5/23/25 Fri 6/6/25 MEP 7/1 One Side Drywall-5
7/7 Insulation-5
7/17 Second Side Drywall-5
7/24 Taping & Finishing-5
Painting
8/14 Prime & Paint-5
Acoustical Ceilings
9/5 Ceiling Grid-5
9/23 Ceiling Devices-5
10/13 Above Ceiling Milestone-5
10/14 Wood Ceilings-5
10/14 Drop Ceiling Tiles-5
Casework
10/7 Casework and countertops-5
Flooring & Wall Finishes
9/5 Restroom Tile (Floor and wall)-5
10/21 Sheet Vinyl flooring-5
11/4 Ceramic Tile @ lobby, waiting room & corridor-5
11/18 Resilient Tile Flooring-5
12/4 Wall protection-5
Doors, Frames & Hardware
6/16 Hollow Metal Door Frames-5
9/12 Aluminum Door Frames-5
12/26 Swing Doors and Install Hardware-5
1/12 Install Sliding Doors & Hardware-5
Accessories & Specialties
10/10 Toilet Accessories-5
12/26 Corner guards-5
1/5 Markerboards-5
MEPF Finish
9/26 Restroom fixtures-5
10/28 Fire Sprinkler Finish Trim-5
12/26 HVAC Finish trim-5
12/26 Electrical Finish-5
12/26 Plumbing Finish-5
Equipment Installation
1/19 Appliances-5
1/22 OFCI equipment-5
Level 4
Level 4 - Demo
3/6 Containment-4
3/13 Safe off-4
3/27 Demo-4
Level 4 - Interior Framing
4/10 Layout-4
4/15 Z-clips, Hangers & Wires-4
4/15 Supplemental Steel-4
4/22 Support beam for Operable partition-4
4/29 Fireproofing-4
5/2 Priority Wall Framing/ HOW-4
6/9 Interior Framing-4
7/8 Frame Inspection Milestone-4
Level 4 - MEPF Rough-in
5/23 Priority Overhead MEP-4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 4
ID % Complete Task Name Duration Start Finish Resource
Names
344 0% In-Wall MEP Rough-4 10 days Mon 6/23/25 Mon 7/7/25 MEP 345 0% MEP rough inspections complete-4 0 days Mon 7/7/25 Mon 7/7/25 City Of Fresno 346 0% Level 4 - Interior Finishes 161 days Mon 6/23/25 Tue 2/10/26 347 0% Insulation & Drywall 35 days Thu 7/31/25 Thu 9/18/25 348 0% One side Drywall-4 8 days Thu 7/31/25 Mon 8/11/25 JMC 349 0% Insulation-4 4 days Tue 8/12/25 Fri 8/15/25 CBP
350 0% Second side Drywall-4 8 days Mon 8/18/25 Wed 8/27/25 JMC 351 0% Taping & Finishing-4 15 days Thu 8/28/25 Thu 9/18/25 JMC 352 0% Painting 15 days Fri 9/19/25 Thu 10/9/25
353 0% Prime & Paint-4 15 days Fri 9/19/25 Thu 10/9/25 Duration 354 0% Acoustical Ceilings 36 days Fri 10/10/25 Tue 12/2/25 355 0% Ceiling Grid-4 15 days Fri 10/10/25 Thu 10/30/25 Genesis 356 0% Ceiling Devices-4 10 days Fri 10/24/25 Thu 11/6/25 MEP 357 0% Above Ceiling Milestone-4 0 days Thu 11/6/25 Thu 11/6/25 City Of Fresno 358 0% Drop Ceiling Tiles-4 10 days Fri 11/7/25 Thu 11/20/25 Genesis 359 0% Wood Ceilings-4 8 days Wed 11/19/25 Tue 12/2/25 Genesis 360 0% Casework 15 days Tue 11/18/25 Wed 12/10/25
361 0% Casework and countertops-4 15 days Tue 11/18/25 Wed 12/10/25 CVC 362 0% Flooring & Wall Treatments 61 days Mon 10/13/25 Fri 1/9/26 363 0% Restroom Tile (Floor and wall)-4 10 days Mon 10/13/25 Fri 10/24/25 VCT 364 0% Ceramic Tile @ lobby, waiting room & corridor-4 15 days Thu 12/4/25 Wed 12/24/25 VCT 365 0% Sheet Vinyl flooring-4 2 days Thu 12/4/25 Fri 12/5/25 Amparan 366 0% Resilient Tile Flooring-4 10 days Mon 12/8/25 Fri 12/19/25 Amparan 367 0% Carpet-4 4 days Mon 12/22/25 Fri 12/26/25 Amparan 368 0% Wall protection-4 10 days Fri 12/26/25 Fri 1/9/26 Genesis 369 0% Doors Frames & Hardware 154 days Mon 6/23/25 Fri 1/30/26 370 0% Hollow Metal Door Frames-4 2 days Mon 6/23/25 Tue 6/24/25 KC&S 371 0% Aluminum Door Frames-4 8 days Fri 10/10/25 Tue 10/21/25 KC&S 372 0% Install Operable Partition-4 5 days Mon 12/29/25 Mon 1/5/26 373 0% Install Glass walls & Doors-4 15 days Tue 1/6/26 Mon 1/26/26 Atascadero 374 0% Swing Doors and Install Hardware-4 15 days Mon 1/12/26 Fri 1/30/26 KC&S 375 0% Accessories & Specialties 53 days Mon 11/3/25 Tue 1/20/26 376 0% Toilet Partitions-4 3 days Mon 11/3/25 Wed 11/5/25 Shelco 377 0% Toilet Accessories-4 5 days Thu 11/6/25 Wed 11/12/25 Shelco 378 0% Corner guards-4 5 days Mon 1/12/26 Fri 1/16/26 Genesis 379 0% Markerboards-4 2 days Mon 1/19/26 Tue 1/20/26 Atascadero 380 0% MEPF Finish 61 days Mon 10/27/25 Fri 1/23/26
381 0% Restroom fixtures-4 5 days Mon 10/27/25 Fri 10/31/25 NESM 382 0% Fire Sprinkler Finish Trim-4 8 days Fri 11/21/25 Thu 12/4/25 RLH 383 0% HVAC Finish trim-4 10 days Mon 1/12/26 Fri 1/23/26 NESM 384 0% Electrical Finish-4 10 days Mon 1/12/26 Fri 1/23/26 Westech 385 0% Plumbing Finish-4 10 days Mon 1/12/26 Fri 1/23/26 NESM 386 0% Equipment Installation 12 days Mon 1/26/26 Tue 2/10/26 387 0% Appliances-4 2 days Mon 1/26/26 Tue 1/27/26
388 0% OFCI equipment-4 10 days Wed 1/28/26 Tue 2/10/26 389 0% Level 3 111 days Wed 6/25/25 Tue 12/2/25
390 0% Level 3 - Demo 13 days Wed 6/25/25 Mon 7/14/25
391 0% Containment-3 2 days Wed 6/25/25 Thu 6/26/25 Quiring 392 0% Safe off-3 2 days Fri 6/27/25 Mon 6/30/25 MEP
393 0% Demo-3 4 days Wed 7/9/25 Mon 7/14/25 Bowen
394 0% Level 3 - Interior Framing 40 days Tue 7/15/25 Tue 9/9/25 395 0% Layout-3 2 days Tue 7/15/25 Wed 7/16/25 JMC
396 0% Z-clips, Hangers & Wires-3 2 days Thu 7/17/25 Fri 7/18/25 JMC 397 0% Fireproofing-3 2 days Mon 7/21/25 Tue 7/22/25 ALcal 6/23 In-Wall MEP Rough-4
7/7 MEP rough inspections complete-4
Level 4 - Interior Finishes
Insulation & Drywall
7/31 One side Drywall-4
8/12 Insulation-4
8/18 Second side Drywall-4
8/28 Taping & Finishing-4
Painting
9/19 Prime & Paint-4
Acoustical Ceilings
10/10 Ceiling Grid-4
10/24 Ceiling Devices-4
11/6 Above Ceiling Milestone-4
11/7 Drop Ceiling Tiles-4
11/19 Wood Ceilings-4
Casework
11/18 Casework and countertops-4
Flooring & Wall Treatments
10/13 Restroom Tile (Floor and wall)-4
12/4 Ceramic Tile @ lobby, waiting room & corridor-4
12/4 Sheet Vinyl flooring-4
12/8 Resilient Tile Flooring-4
12/22 Carpet-4
12/26 Wall protection-4
Doors Frames & Hardware
6/23 Hollow Metal Door Frames-4
10/10 Aluminum Door Frames-4
12/29 Install Operable Partition-4
1/6 Install Glass walls & Doors-4
1/12 Swing Doors and Install Hardware-4
Accessories & Specialties
11/3 Toilet Partitions-4
11/6 Toilet Accessories-4
1/12 Corner guards-4
1/19 Markerboards-4
MEPF Finish
10/27 Restroom fixtures-4
11/21 Fire Sprinkler Finish Trim-4
1/12 HVAC Finish trim-4
1/12 Electrical Finish-4
1/12 Plumbing Finish-4
Equipment Installation
1/26 Appliances-4
1/28 OFCI equipment-4
Level 3
Level 3 - Demo
6/25 Containment-3
6/27 Safe off-3
7/9 Demo-3
Level 3 - Interior Framing
7/15 Layout-3
7/17 Z-clips, Hangers & Wires-3
7/21 Fireproofing-3
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 5
ID % Complete Task Name Duration Start Finish Resource
Names
398 0% Interior Framing-3 2 days Wed 7/23/25 Thu 7/24/25 JMC 399 0% Framing Inspection Milestone-3 0 days Tue 9/9/25 Tue 9/9/25 City Of Fresno 400 0% Level 3 - MEPF Rough-in 32 days Fri 7/25/25 Tue 9/9/25 401 0% In-Wall MEP Rough-3 3 days Fri 7/25/25 Tue 7/29/25 MEP 402 0% Overhead MEP Rough-3 5 days Wed 9/3/25 Tue 9/9/25 MEP 403 0% MEP Rough Inspections Complete-3 0 days Tue 9/9/25 Tue 9/9/25 City Of Fresno 404 0% Level 3 - Interior Finishes 50 days Mon 9/22/25 Tue 12/2/25 405 0% Insulation & Drywall 14 days Mon 9/22/25 Thu 10/9/25 406 0% One Side Drywall-3 1 day Mon 9/22/25 Mon 9/22/25 JMC 407 0% Insulation-3 1 day Tue 9/23/25 Tue 9/23/25 CBP
408 0% Insulation Inspection-3 0 days Tue 9/23/25 Tue 9/23/25 City Of Fresno 409 0% Second Side Drywall-3 2 days Wed 9/24/25 Thu 9/25/25 JMC 410 0% Taping & Finishing-3 5 days Fri 10/3/25 Thu 10/9/25 JMC 411 0% Painting 5 days Fri 10/10/25 Thu 10/16/25
412 0% Prime & Paint-3 5 days Fri 10/10/25 Thu 10/16/25 Duration 413 0% Acoustical Ceilings 9 days Fri 10/17/25 Wed 10/29/25 414 0% Ceiling Grid-3 3 days Fri 10/17/25 Tue 10/21/25 Genesis 415 0% Ceiling Devices-3 3 days Wed 10/22/25 Fri 10/24/25 MEP 416 0% Above Ceiling Milestone-3 0 days Fri 10/24/25 Fri 10/24/25 City Of Fresno 417 0% Drop Ceiling Tiles-3 3 days Mon 10/27/25 Wed 10/29/25 Genesis 418 0% Casework 2 days Thu 10/30/25 Fri 10/31/25
419 0% Casework & Countertop relocation-3 2 days Thu 10/30/25 Fri 10/31/25 CVC 420 0% Flooring & Wall Protection 10 days Mon 11/3/25 Fri 11/14/25 421 0% Sheet Vinyl Flooring-3 5 days Mon 11/3/25 Fri 11/7/25 Amparan 422 0% Wall Protection-3 5 days Mon 11/10/25 Fri 11/14/25 Genesis 423 0% Doors Frames & Hardware 18 days Fri 10/17/25 Tue 11/11/25 424 0% Aluminum Door Frames-3 1 day Fri 10/17/25 Fri 10/17/25 KC&S 425 0% Hang doors & Install Hardware 2 days Mon 11/10/25 Tue 11/11/25 KC&S 426 0% MEPF Finish 8 days Mon 11/17/25 Wed 11/26/25
427 0% MEP Finish Trim-3 8 days Mon 11/17/25 Wed 11/26/25 MEP 428 0% Equipment Installation 2 days Mon 12/1/25 Tue 12/2/25 429 0% OFCI equipment-3 2 days Mon 12/1/25 Tue 12/2/25
430 0% Level 2 110 days Mon 6/23/25 Tue 11/25/25
431 0% Level 2 - Demo 11 days Mon 6/23/25 Tue 7/8/25
432 0% Containment-2 2 days Mon 6/23/25 Tue 6/24/25 Quiring 433 0% Safe off-2 2 days Wed 6/25/25 Thu 6/26/25 MEP
434 0% Demo-2 7 days Fri 6/27/25 Tue 7/8/25 Bowen
435 0% Level 2 - Interior Framing 37 days Fri 7/11/25 Tue 9/2/25 436 0% Layout-2 2 days Fri 7/11/25 Mon 7/14/25 JMC
437 0% Z-clips, Hangers & Wires-2 2 days Tue 7/15/25 Wed 7/16/25 JMC 438 0% Fireproofing-2 2 days Thu 7/17/25 Fri 7/18/25 ALcal 439 0% Interior Framing-2 2 days Mon 7/21/25 Tue 7/22/25 JMC 440 0% Frame Inspection Milestone-2 0 days Tue 9/2/25 Tue 9/2/25 City Of Fresno 441 0% Level 2 - MEPF Rough-in 29 days Wed 7/23/25 Tue 9/2/25 442 0% In-Wall MEP Rough in-2 5 days Wed 7/23/25 Tue 7/29/25 MEP 443 0% Overhead MEPF Rough in-2 7 days Fri 8/22/25 Tue 9/2/25 MEPF 444 0% MEP Rough in Complete 0 days Tue 9/2/25 Tue 9/2/25 City Of Fresno 445 0% Level 2 - Interior Finishes 53 days Fri 9/12/25 Tue 11/25/25 446 0% Insulation & Drywall 15 days Fri 9/12/25 Thu 10/2/25 447 0% One Side Drywall-2 2 days Fri 9/12/25 Mon 9/15/25 JMC 448 0% Insulation-2 1 day Tue 9/16/25 Tue 9/16/25 CBP
449 0% Insulation Inspection 0 days Wed 9/17/25 Wed 9/17/25 City Of Fresno 450 0% Second Side Drywall-2 2 days Thu 9/18/25 Fri 9/19/25 JMC 451 0% Taping & Finishing-2 5 days Fri 9/26/25 Thu 10/2/25 JMC 7/23 Interior Framing-3
9/9 Framing Inspection Milestone-3
Level 3 - MEPF Rough-in
7/25 In-Wall MEP Rough-3
9/3 Overhead MEP Rough-3
9/9 MEP Rough Inspections Complete-3
Level 3 - Interior Finishes
Insulation & Drywall
9/22 One Side Drywall-3
9/23 Insulation-3
9/23 Insulation Inspection-3
9/24 Second Side Drywall-3
10/3 Taping & Finishing-3
Painting
10/10 Prime & Paint-3
Acoustical Ceilings
10/17 Ceiling Grid-3
10/22 Ceiling Devices-3
10/24 Above Ceiling Milestone-3
10/27 Drop Ceiling Tiles-3
Casework
10/30 Casework & Countertop relocation-3
Flooring & Wall Protection
11/3 Sheet Vinyl Flooring-3
11/10 Wall Protection-3
Doors Frames & Hardware
10/17 Aluminum Door Frames-3
11/10 Hang doors & Install Hardware
MEPF Finish
11/17 MEP Finish Trim-3
Equipment Installation
12/1 OFCI equipment-3
Level 2
Level 2 - Demo
6/23 Containment-2
6/25 Safe off-2
6/27 Demo-2
Level 2 - Interior Framing
7/11 Layout-2
7/15 Z-clips, Hangers & Wires-2
7/17 Fireproofing-2
7/21 Interior Framing-2
9/2 Frame Inspection Milestone-2
Level 2 - MEPF Rough-in
7/23 In-Wall MEP Rough in-2
8/22 Overhead MEPF Rough in-2
9/2 MEP Rough in Complete
Level 2 - Interior Finishes
Insulation & Drywall
9/12 One Side Drywall-2
9/16 Insulation-2
9/17 Insulation Inspection
9/18 Second Side Drywall-2
9/26 Taping & Finishing-2
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 6
ID % Complete Task Name Duration Start Finish Resource
Names
452 0% Painting 5 days Fri 10/3/25 Thu 10/9/25
453 0% Prime & Paint-2 5 days Fri 10/3/25 Thu 10/9/25 Duration 454 0% Acoustical Ceilings 8 days Fri 10/10/25 Tue 10/21/25 455 0% Ceiling Grid-2 3 days Fri 10/10/25 Tue 10/14/25 Genesis 456 0% Ceiling Devices-2 3 days Wed 10/15/25 Fri 10/17/25 MEP 457 0% Above Ceiling Milestone-2 0 days Fri 10/17/25 Fri 10/17/25 City Of Fresno 458 0% Drop Ceiling Tiles-2 2 days Mon 10/20/25 Tue 10/21/25 Genesis 459 0% Casework 2 days Wed 10/22/25 Thu 10/23/25
460 0% Casework & Countertops-2 2 days Wed 10/22/25 Thu 10/23/25 CVC 461 0% Flooring & Wall Treatments 16 days Fri 10/24/25 Fri 11/14/25 462 0% Resilient Tile Flooring-2 1 day Fri 10/24/25 Fri 10/24/25 Amparan 463 0% Ceramic Tile Flooring-2 5 days Mon 10/27/25 Fri 10/31/25 VCT 464 0% Wall treatments-2 10 days Mon 11/3/25 Fri 11/14/25 Genesis 465 0% Doors, Frames & Hardware 17 days Fri 10/10/25 Mon 11/3/25 466 0% Aluminum Frames-2 1 day Fri 10/10/25 Fri 10/10/25 KC&S 467 0% Hang Doors & Install Hardware-2 1 day Mon 11/3/25 Mon 11/3/25 KC&S 468 0% MEPF Finish 5 days Mon 11/17/25 Fri 11/21/25
469 0% MEP Finish trim 5 days Mon 11/17/25 Fri 11/21/25 MEP 470 0% Equipment Installation 2 days Mon 11/24/25 Tue 11/25/25 471 0% OFCI equipment-2 2 days Mon 11/24/25 Tue 11/25/25 472 0% Level 1 235 days Thu 3/13/25 Fri 2/13/26
473 0% Level 1 Area B - (1502, 1503, 1307, 1308) 59 days Thu 3/13/25 Wed 6/4/25 474 0% Setup Containment / Temp wall at corridor 2 days Thu 3/13/25 Fri 3/14/25 Quiring 475 0% wall demo at GL 5 for (N) corridor / vestibule 1 day Mon 3/17/25 Mon 3/17/25 Bowen 476 0% MEPF Overhead Rough-in 8 days Mon 3/17/25 Wed 3/26/25 MEPF 477 0% Underground plumbing 5 days Thu 3/27/25 Wed 4/2/25 NESM 478 0% underground plumbing inspection 0 days Wed 4/2/25 Wed 4/2/25 City Of Fresno 479 0% Backfill plumbing trenches 1 day Thu 4/3/25 Thu 4/3/25 NESM 480 0% Vapor barrier, sand, rebar 3 days Fri 4/4/25 Tue 4/8/25 Heritage 481 0% S.O.G. Reinforcement Inspection 0 days Tue 4/8/25 Tue 4/8/25 City Of Fresno 482 0% Pour S.O.G. 1 day Wed 4/9/25 Wed 4/9/25 Heritage 483 0% Layout and wall framing 3 days Fri 4/11/25 Tue 4/15/25 JMC 484 0% Hollow metal door frames 1 day Wed 4/16/25 Wed 4/16/25 KC&S 485 0% MEP In-wall rough 5 days Wed 4/16/25 Tue 4/22/25 MEP 486 0% MEP Rough / top out inspections complete 0 days Tue 4/22/25 Tue 4/22/25 City Of Fresno 487 0% Framing inspection 0 days Wed 4/23/25 Wed 4/23/25 City Of Fresno 488 0% Insulation 1 day Thu 4/24/25 Thu 4/24/25 CBP
489 0% Insulation Inspection 0 days Fri 4/25/25 Fri 4/25/25 City Of Fresno 490 0% Drywall and Tile backer 3 days Mon 4/28/25 Wed 4/30/25 JMC 491 0% Tape & Finish 5 days Thu 5/1/25 Wed 5/7/25 JMC
492 0% Painting 3 days Thu 5/8/25 Mon 5/12/25 Duration
493 0% Install Aluminum Door Frames 1 day Tue 5/13/25 Tue 5/13/25 KC&S 494 0% Tile 5 days Wed 5/14/25 Tue 5/20/25 VCT
495 0% Plumbing Fixtures 3 days Wed 5/21/25 Fri 5/23/25 NESM 496 0% Partitions & Toilet Accessories 3 days Tue 5/27/25 Thu 5/29/25 Shelco 497 0% Acoustical ceiling grid 2 days Tue 5/13/25 Wed 5/14/25 Genesis 498 0% Ceiling Devices 2 days Thu 5/15/25 Fri 5/16/25 Genesis 499 0% Casework and Countertops 7 days Thu 5/15/25 Fri 5/23/25 CVC 500 0% Above ceiling inspection 0 days Fri 5/16/25 Fri 5/16/25 City Of Fresno 501 0% Drop ceiling tiles 1 day Mon 5/19/25 Mon 5/19/25 Genesis 502 0% MEPF Finish Trim 3 days Tue 5/20/25 Thu 5/22/25 MEPF 503 0% Lockers at Staff lounge 3 days Thu 5/22/25 Tue 5/27/25 CVC 504 0% Resilient Flooring & Base 2 days Wed 5/28/25 Thu 5/29/25 Amparan 505 0% Staff lounge appliances 1 day Fri 5/30/25 Fri 5/30/25 Painting
10/3 Prime & Paint-2
Acoustical Ceilings
10/10 Ceiling Grid-2
10/15 Ceiling Devices-2
10/17 Above Ceiling Milestone-2
10/20 Drop Ceiling Tiles-2
Casework
10/22 Casework & Countertops-2
Flooring & Wall Treatments
10/24 Resilient Tile Flooring-2
10/27 Ceramic Tile Flooring-2
11/3 Wall treatments-2
Doors, Frames & Hardware
10/10 Aluminum Frames-2
11/3 Hang Doors & Install Hardware-2
MEPF Finish
11/17 MEP Finish trim
Equipment Installation
11/24 OFCI equipment-2
Level 1
Level 1 Area B - (1502, 1503, 1307, 1308)
3/13 Setup Containment / Temp wall at corridor
3/17 wall demo at GL 5 for (N) corridor / vestibule
3/17 MEPF Overhead Rough-in
3/27 Underground plumbing
4/2 underground plumbing inspection
4/3 Backfill plumbing trenches
4/4 Vapor barrier, sand, rebar
4/8 S.O.G. Reinforcement Inspection
4/9 Pour S.O.G.
4/11 Layout and wall framing
4/16 Hollow metal door frames
4/16 MEP In-wall rough
4/22 MEP Rough / top out inspections complete
4/23 Framing inspection
4/24 Insulation
4/25 Insulation Inspection
4/28 Drywall and Tile backer
5/1 Tape & Finish
5/8 Painting
5/13 Install Aluminum Door Frames
5/14 Tile
5/21 Plumbing Fixtures
5/27 Partitions & Toilet Accessories
5/13 Acoustical ceiling grid
5/15 Ceiling Devices
5/15 Casework and Countertops
5/16 Above ceiling inspection
5/19 Drop ceiling tiles
5/20 MEPF Finish Trim
5/22 Lockers at Staff lounge
5/28 Resilient Flooring & Base
5/30 Staff lounge appliances
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 7
ID % Complete Task Name Duration Start Finish Resource
Names
506 0% Doors & Hardware 2 days Fri 5/30/25 Mon 6/2/25 KC&S 507 0% Punch list for rooms 1502, 1503, 1303, 1304, 1305, 1307 & 1308
2 days Tue 6/3/25 Wed 6/4/25 HGA
508 0% Final Inspections at toilet rooms 1502 & 1503 2 days Tue 6/3/25 Wed 6/4/25 City Of Fresno 509 0% (N) Toilet rooms open to public 0 days Wed 6/4/25 Wed 6/4/25 510 0% Back of House Upgrades - Level 1 Area E/D 28 days Tue 4/22/25 Fri 5/30/25 511 0% Exterior 26 days Tue 4/22/25 Wed 5/28/25
512 0% Demo 2 days Tue 4/22/25 Wed 4/23/25 Bowen
513 0% Structural Steel & Metal decking 5 days Thu 4/24/25 Wed 4/30/25 Powers 514 0% Fireproofing 2 days Thu 5/1/25 Fri 5/2/25 ALcal
515 0% Exterior sheathing 1 day Mon 5/5/25 Mon 5/5/25 JMC 516 0% Sheet metal counter flashing 1 day Tue 5/6/25 Tue 5/6/25 NESM 517 0% Plaster patching 5 days Wed 5/7/25 Tue 5/13/25 Frontline 518 0% Light gauge metal framing & sheathing 3 days Wed 5/14/25 Fri 5/16/25 JMC 519 0% Gutter install 2 days Mon 5/19/25 Tue 5/20/25 NESM 520 0% TPO Roofing 2 days Wed 5/21/25 Thu 5/22/25 ALlstate 521 0% Exterior metal paneling at Canopy 3 days Fri 5/23/25 Wed 5/28/25 JMC 522 0% Interior 26 days Thu 4/24/25 Fri 5/30/25
523 0% Electrical & access control rough-in for auto operator 2 days Thu 4/24/25 Fri 4/25/25 Westech 524 0% Install new doors, frame & hardware 2 days Mon 5/5/25 Tue 5/6/25 Atascadero 525 0% Drywall touchup & Paint 5 days Wed 5/7/25 Tue 5/13/25 JMC 526 0% Ceiling Grid repairs 2 days Wed 5/14/25 Thu 5/15/25 Genesis 527 0% Drop (N) ceiling tiles 2 days Fri 5/16/25 Mon 5/19/25 Genesis 528 0% Flooring & Base 5 days Tue 5/20/25 Tue 5/27/25 Amparan 529 0% Wall protection & Corner guards 3 days Wed 5/28/25 Fri 5/30/25 Genesis 530 0% Level 1 Back of House upgrades complete 0 days Fri 5/30/25 Fri 5/30/25 531 0% New Lobby - Level 1 Area A 176 days Thu 6/5/25 Fri 2/13/26 532 0% Containment 2 days Thu 6/5/25 Fri 6/6/25 Quiring 533 0% Demo between GL 5 & 8 and C & D 3 days Mon 6/9/25 Wed 6/11/25 Bowen 534 0% Saw cut & Demo for depressed slab @ entrances 2 days Thu 6/12/25 Fri 6/13/25 Bowen 535 0% Underground plumbing 5 days Mon 6/16/25 Fri 6/20/25 NESM 536 0% underground plumbing inspection 0 days Fri 6/20/25 Fri 6/20/25 City Of Fresno 537 0% Backfill plumbing trenches 2 days Mon 6/23/25 Tue 6/24/25 NESM 538 0% Vapor barrier, sand, rebar 8 days Wed 6/25/25 Mon 7/7/25 Heritage 539 0% S.O.G. Reinforcement Inspection 0 days Mon 7/7/25 Mon 7/7/25 City Of Fresno 540 0% Pour S.O.G. 1 day Tue 7/8/25 Tue 7/8/25 Heritage 541 0% MEPF Overhead Rough-in 20 days Wed 7/16/25 Tue 8/12/25 MEPF 542 0% Layout and wall framing 8 days Tue 8/5/25 Thu 8/14/25 JMC 543 0% Ceiling & Soffit framing 8 days Fri 8/15/25 Tue 8/26/25 JMC 544 0% Hollow metal door frames 1 day Fri 8/15/25 Fri 8/15/25 KC&S 545 0% MEP In-wall rough 8 days Fri 8/15/25 Tue 8/26/25 MEP 546 0% MEP Rough / top out inspections complete 0 days Tue 8/26/25 Tue 8/26/25 City Of Fresno 547 0% Framing inspection 0 days Wed 8/27/25 Wed 8/27/25 City Of Fresno 548 0% Insulation 2 days Thu 8/28/25 Fri 8/29/25 CBP
549 0% Drywall 8 days Tue 9/2/25 Thu 9/11/25 JMC
550 0% Taping & Finishing 10 days Fri 9/12/25 Thu 9/25/25 JMC 551 0% Prime & Paint 10 days Fri 9/26/25 Thu 10/9/25 Duration 552 0% Ceiling grid 10 days Fri 10/10/25 Thu 10/23/25 Genesis 553 0% Above ceiling inspection 0 days Thu 10/23/25 Thu 10/23/25 City Of Fresno 554 0% Install ceiling planks 10 days Fri 10/24/25 Thu 11/6/25 Genesis 555 0% Casework & Countertops 10 days Fri 11/7/25 Thu 11/20/25 CVC 556 0% MEPF Finish 15 days Fri 11/21/25 Mon 12/15/25 MEPF 557 0% Acoustical Ceiling treatments 7 days Tue 12/16/25 Wed 12/24/25 Acoustech 558 0% Tile Flooring 15 days Fri 12/26/25 Fri 1/16/26 VCT 559 0% Install doors & hardware 3 days Mon 1/19/26 Wed 1/21/26 KC&S 5/30 Doors & Hardware
6/3 Punch list for rooms 1502, 1503, 1303, 1304, 1305, 1307 & 1308 6/3 Final Inspections at toilet rooms 1502 & 1503
6/4 (N) Toilet rooms open to public
Back of House Upgrades - Level 1 Area E/D
Exterior
4/22 Demo
4/24 Structural Steel & Metal decking
5/1 Fireproofing
5/5 Exterior sheathing
5/6 Sheet metal counter flashing
5/7 Plaster patching
5/14 Light gauge metal framing & sheathing
5/19 Gutter install
5/21 TPO Roofing
5/23 Exterior metal paneling at Canopy
Interior
4/24 Electrical & access control rough-in for auto operator 5/5 Install new doors, frame & hardware
5/7 Drywall touchup & Paint
5/14 Ceiling Grid repairs
5/16 Drop (N) ceiling tiles
5/20 Flooring & Base
5/28 Wall protection & Corner guards
5/30 Level 1 Back of House upgrades complete
New Lobby - Level 1 Area A
6/5 Containment
6/9 Demo between GL 5 & 8 and C & D
6/12 Saw cut & Demo for depressed slab @ entrances
6/16 Underground plumbing
6/20 underground plumbing inspection
6/23 Backfill plumbing trenches
6/25 Vapor barrier, sand, rebar
7/7 S.O.G. Reinforcement Inspection
7/8 Pour S.O.G.
7/16 MEPF Overhead Rough-in
8/5 Layout and wall framing
8/15 Ceiling & Soffit framing
8/15 Hollow metal door frames
8/15 MEP In-wall rough
8/26 MEP Rough / top out inspections complete
8/27 Framing inspection
8/28 Insulation
9/2 Drywall
9/12 Taping & Finishing
9/26 Prime & Paint
10/10 Ceiling grid
10/23 Above ceiling inspection
10/24 Install ceiling planks
11/7 Casework & Countertops
11/21 MEPF Finish
12/16 Acoustical Ceiling treatments
12/26 Tile Flooring
1/19 Install doors & hardware
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 8
ID % Complete Task Name Duration Start Finish Resource
Names
560 0% Wall treatments 15 days Mon 1/19/26 Fri 2/6/26 CVC 561 0% Equipment Install 5 days Mon 2/9/26 Fri 2/13/26
562 0% Elevator 166 days Wed 5/21/25 Fri 1/16/26
563 0% Elevator level 1 35 days Wed 5/21/25 Thu 7/10/25 564 0% Pit Layout 3 days Wed 5/21/25 Fri 5/23/25
565 0% Relocate overhead utilities at shaft location 5 days Tue 5/27/25 Mon 6/2/25 MEPF 566 0% Supplemental Steel for elevator shaft opening @ Level 2 5 days Tue 6/3/25 Mon 6/9/25 Powers 567 0% Fireproofing 2 days Tue 6/10/25 Wed 6/11/25 ALcal 568 0% Pit excavation 3 days Thu 6/12/25 Mon 6/16/25 Heritage 569 0% Form & Pour elevator pit 8 days Tue 6/17/25 Thu 6/26/25 Heritage 570 0% Guiderail Supports level 1 3 days Fri 6/27/25 Tue 7/1/25 Powers 571 0% Shaftwall Framing 3 days Wed 7/2/25 Mon 7/7/25 JMC 572 0% Pit Ladder 1 day Tue 7/8/25 Tue 7/8/25 Powers
573 0% Pit Light 2 days Wed 7/9/25 Thu 7/10/25 Westech
574 0% Elevator level 2 22 days Tue 6/10/25 Thu 7/10/25 575 0% Supplemental Steel for elevator shaft opening @ level 3 5 days Tue 6/10/25 Mon 6/16/25 Powers 576 0% Fireproofing 2 days Tue 6/17/25 Wed 6/18/25 ALcal 577 0% Guiderail Supports level 2 3 days Wed 7/2/25 Mon 7/7/25 Powers 578 0% Shaftwall Framing 3 days Tue 7/8/25 Thu 7/10/25 JMC 579 0% Elevator level 3 20 days Tue 6/17/25 Tue 7/15/25 580 0% Supplemental Steel for elevator shaft opening @ level 4 5 days Tue 6/17/25 Mon 6/23/25 Powers 581 0% Fireproofing 2 days Tue 6/24/25 Wed 6/25/25 ALcal 582 0% Guiderail Supports level 3 3 days Tue 7/8/25 Thu 7/10/25 Powers 583 0% Shaftwall Framing 3 days Fri 7/11/25 Tue 7/15/25 JMC 584 0% Elevator level 4 18 days Tue 6/24/25 Fri 7/18/25 585 0% Supplemental Steel for elevator shaft opening @ level 5 5 days Tue 6/24/25 Mon 6/30/25 Powers 586 0% Fireproofing 2 days Tue 7/1/25 Wed 7/2/25 ALcal
587 0% Guiderail Supports level 4 3 days Fri 7/11/25 Tue 7/15/25 Powers 588 0% Shaftwall Framing 3 days Wed 7/16/25 Fri 7/18/25 JMC 589 0% Elevator level 5 16 days Tue 7/1/25 Wed 7/23/25
590 0% Supplemental Steel for elevator shaft opening @ roof 5 days Tue 7/1/25 Tue 7/8/25 Powers 591 0% Fireproofing 2 days Wed 7/9/25 Thu 7/10/25 ALcal 592 0% Guiderail Supports level 5 3 days Wed 7/16/25 Fri 7/18/25 Powers 593 0% Shaftwall Framing 3 days Mon 7/21/25 Wed 7/23/25 JMC 594 0% Preinstall Inspection 0 days Thu 7/24/25 Thu 7/24/25 Schindler 595 0% Install 60 days Thu 9/4/25 Wed 11/26/25 Schindler 596 0% Elevator smoke screens 3 days Mon 11/24/25 Wed 11/26/25 597 0% State Elevator Testing 0 days Fri 1/16/26 Fri 1/16/26 598 0% Exterior Canopy & Porte Cochere 155 days Fri 6/13/25 Fri 1/23/26 599 0% Interior Protection and Temp walls at Levels 1-3 10 days Fri 6/13/25 Fri 6/27/25 Quiring 600 0% Demo exterior Façade 8 days Fri 6/27/25 Wed 7/9/25 Bowen 601 0% Survey column lines 1 day Thu 7/10/25 Thu 7/10/25 Bedrock 602 0% Footings & Grade beam for (N) Entry canopy 15 days Fri 7/11/25 Thu 7/31/25 Heritage 603 0% Structural Steel 15 days Fri 8/1/25 Thu 8/21/25 Powers 604 0% Metal decking 5 days Fri 8/22/25 Thu 8/28/25 Powers 605 0% Fireproofing 5 days Fri 8/29/25 Fri 9/5/25 ALcal 606 0% Exterior Framing 10 days Mon 9/8/25 Fri 9/19/25 JMC 607 0% Exterior MEPF rough-in 5 days Mon 9/22/25 Fri 9/26/25 MEP 608 0% Storefront and Curtain Wall system 30 days Mon 9/22/25 Fri 10/31/25 Atascadero 609 0% Exterior framing complete - ready for sheathing 0 days Fri 9/26/25 Fri 9/26/25 City Of Fresno 610 0% Exterior Sheathing 5 days Mon 9/29/25 Fri 10/3/25 JMC 611 0% Air Barrier 3 days Mon 10/6/25 Wed 10/8/25
612 0% Install reglet and J-mold 3 days Thu 10/9/25 Mon 10/13/25 Frontline 613 0% TPO Roofing 5 days Tue 10/14/25 Mon 10/20/25 ALlstate 1/19 Wall treatments
2/9 Equipment Install
Elevator
Elevator level 1
5/21 Pit Layout
5/27 Relocate overhead utilities at shaft location
6/3 Supplemental Steel for elevator shaft opening @ Level 2 6/10 Fireproofing
6/12 Pit excavation
6/17 Form & Pour elevator pit
6/27 Guiderail Supports level 1
7/2 Shaftwall Framing
7/8 Pit Ladder
7/9 Pit Light
Elevator level 2
6/10 Supplemental Steel for elevator shaft opening @ level 3 6/17 Fireproofing
7/2 Guiderail Supports level 2
7/8 Shaftwall Framing
Elevator level 3
6/17 Supplemental Steel for elevator shaft opening @ level 4 6/24 Fireproofing
7/8 Guiderail Supports level 3
7/11 Shaftwall Framing
Elevator level 4
6/24 Supplemental Steel for elevator shaft opening @ level 5 7/1 Fireproofing
7/11 Guiderail Supports level 4
7/16 Shaftwall Framing
Elevator level 5
7/1 Supplemental Steel for elevator shaft opening @ roof 7/9 Fireproofing
7/16 Guiderail Supports level 5
7/21 Shaftwall Framing
7/24 Preinstall Inspection
9/4 Install
11/24 Elevator smoke screens
1/16 State Elevator Testing
Exterior Canopy & Porte Cochere
6/13 Interior Protection and Temp walls at Levels 1-3
6/27 Demo exterior Façade
7/10 Survey column lines
7/11 Footings & Grade beam for (N) Entry canopy
8/1 Structural Steel
8/22 Metal decking
8/29 Fireproofing
9/8 Exterior Framing
9/22 Exterior MEPF rough-in
9/22 Storefront and Curtain Wall system
9/26 Exterior framing complete - ready for sheathing
9/29 Exterior Sheathing
10/6 Air Barrier
10/9 Install reglet and J-mold
10/14 TPO Roofing
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 9
ID % Complete Task Name Duration Start Finish Resource
Names
614 0% Automatic Entrance doors 5 days Thu 12/4/25 Wed 12/10/25 Atascadero 615 0% Metal Paneling & Trim 25 days Thu 12/4/25 Fri 1/9/26 NESM 616 0% Signage - Building Lettering 10 days Mon 1/12/26 Fri 1/23/26 Pro-screen 617 0% Column covers 5 days Mon 1/12/26 Fri 1/16/26 NESM 618 0% Finals and Closeout 50 days Mon 2/16/26 Fri 4/24/26 619 0% Startup & Testing 20 days Mon 2/16/26 Fri 3/13/26 MEP 620 0% Exterior Final Punch 10 days Fri 2/20/26 Thu 3/5/26 621 0% Air Balancing & Title 24 20 days Mon 3/2/26 Fri 3/27/26 NESM 622 0% Construction Clean 15 days Mon 3/9/26 Fri 3/27/26 CCC 623 0% Lighting controls, Programming & Title 24 15 days Mon 3/16/26 Fri 4/3/26 Westech 624 0% Tenant Improvement Punch 15 days Mon 3/30/26 Fri 4/17/26 625 0% Final Inspections 15 days Mon 4/6/26 Fri 4/24/26 City Of Fresno 626 0% Certificate of Occupancy 0 days Fri 4/24/26 Fri 4/24/26 12/4 Automatic Entrance doors
12/4 Metal Paneling & Trim
1/12 Signage - Building Lettering
1/12 Column covers
Finals and Closeout
2/16 Startup & Testing
2/20 Exterior Final Punch
3/2 Air Balancing & Title 24
3/9 Construction Clean
3/16 Lighting controls, Programming & Title 24
3/30 Tenant Improvement Punch
4/6 Final Inspections
4/24 Certificate of Occupancy
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 202 6 Qtr 2, 2026 Qtr 3, 2026 Bob Smittcamp Family Neurosciences Institute at North Medical Pla za Baseline Schedule
Fri 2/28/25
Fri 2/28/25 Page 10