WEST SHAW
TRANSIT-ORIENTED
DEVELOPMENT STUDY
(WSTOD)
CITY COUNCIL| June 19, 2025 ID 25-613
Overview
• August 2023 – Awarded Measure C Grant
• Transform West Shaw Corridor into a Transit-Oriented Community Center • Project Area
• 2.15 miles along West Shaw from Grantland to Golden State • Related Planning Documents
• West Area Neighborhood Specific Plan (WANSP)
• Policy LUH 1.4 - “Create a Small Area Plan for the West Shaw Avenue Town Center, which shall incorporate the Highway City Neighborhood Specific Plan Area, to further refine and support orderly, transit-oriented urban design and development.” • Active Transportation Plan (ATP)
• 6th Cycle Housing Element
• Program 5 – Large and Small Lot Development
• General Plan
2 Project Area
3 Housing Element Sites
4 Budget and Deliverables
• Consultant – Toole Design
• Budget - $400K
• Existing Conditions Assessment and Market Analysis
• Community Outreach – including Community Design Charrette • 30% Streetscape Design
• Trail Design Concept
• Station Area and Town Center Concepts
• Renderings and Proforma
• West Shaw And Town Center Recommendations Report
5 Proposed Timeline
• 3 years with ability to extend
6 Year 1 to 2
• Existing Conditions Assessment
• Initial Outreach and Engagement
• Draft Recommendations Report and Study
Year 2 to 3
• Community Review
• Finalization of documents
QUESTIONS AND COMMENTS?
Project liaisons:
Maya Mubarak, Planner
[email protected]
(559) 621-8075
Yamilex Nava, Planner
[email protected]
(559) 621-8028
7