FISCAL IMPACT STATEMENT
PROGRAM:

TOTAL OR ANNUALIZED

RECOMMENDATION CURRENT COST
Direct Cost $5,525,000.00
Indirect Cost $901,500.00
TOTAL COST $6,426,500.00
Additional
Revenue or Savings
Generated
Net City Cost $6,426,500.00
Amount Budgeted
(If none budgeted,
identify source) $5,761,517.00

SUMARY OF INDIRECT COSTS
Project Management $ 131,000.00
Construction Management $ 218,000.00
Construction Contingency $ 552,500.00
TOTAL INDIRECT COST $ 901,500.00
The total budget allocation for Water Main Replacements in the area bound by Clinton, Teilman, University and West Avenues is $5,813,709.96. Of this amount. $46,861.58 was expended and encumbered by the end of Fiscal Year 2024. The remaining $5,761,517.00 was carried over to Fiscal Year 2025. Construction is fully funded and additional allocations will be included in Fiscal Year 2026 to account for construction management and closeout.