10x Order #9316
Printed: 06/04/2025 02:18:59 pm
Ciehoski,Stephanie Diane
10X Order #9316 - H2O - NE Division SCADA Firewall Upgrade Project # 9316 Requested Date 04/09/2025
Type of 10X Order Placed Fiscal Year 2025
Purchase Order AT
10x Creator Juan Rios Contact Person Patrick Carter
Supervisor Rios-Ramos,Juan Dept Budget Officer Rios-Ramos,Juan Organization 411501 - Water Capital
Projects
Fund Code 40101
Yearly Cost Project Code WC00023
Activity Code IS Resource Type SCADA
GL String 4000-4001-4115-765-85
9333-41-0-0000-0000-
Project String 411500723 -PHASE_2
-CMAT -
Budget Type Unbudgeted Replacement? New Equipment
Quote
Qty Product Unit Amount
2 Cisco Secure 3K Series 300W AC Power Supply 1,330.74 2,661.48 4 10GBASE-LR SFP Module, Enterprise-Class 860.56 3,442.24 8 10GBASE-ZR SFP Module 5,930.99 47,447.92
1 Labor: Systems Engineer Security - Cisco Firepower 12,000.00 12,000.00 6 C9300-DNA-L-A-3Y - DNA Advantage 3 Year License 1,093.70 6,562.20 2 Cisco Secure 14,019.75 28,039.50
6 Catalyst 9300X 24x25G Fiber Ports, modular uplink Switch 13,603.18 81,619.08 6 CX Level 1 SW Sub C9300 DNA Advantage term license 36 months
283.20 1,699.20
2 SmartNet 8X5XNBD Cisco Secure Firewall 9,920.00 19,840.00 6 CX Level 1 8X7NCDCatalyst 9300X 24x25G fiber ports module 7,245.60 43,473.60 12 10GBASE-CU SFP+ Cable 1 Meter 59.28 711.36
1 Labor: Systems Engineer Security - Cisco Firepower - HA 5,000.00 5,000.00 6 Labor: Cisco Edge Switch Installation - Stackable 600.00 3,600.00 8 Labor: Project Manaager 200.00 1,600.00
80 Labor: Systems Engineer - Network reconfiguration 250.00 20,000.00 1 TAXES 14,777.90 14,777.90
6 715W AC 80+ platinum Config 1 SecondaryPower Supply 680.16 4,080.96 6 STACK-T1-50CM 54.41 326.46
6 Catalyst 3750X and 3850 Stack Power Cable 150 CM - Upgrade 54.41 326.46 6 Catalyst 9300 2 x 40G/100G Network Module QSFP+/QSFP28 1,387.53 8,325.18 10% Contigency 30,553.35
Total 336,086.894
Current Approvals
Approval Type Name Date Status
10x Created Juan Rios 04-09-2025 Submitted
Dept Budget Officer Rios-Ramos,Juan 04-09-2025 Approved ISD Quote Tooma,Michael K 04-25-2025 Approved
Manager Approval Rios-Ramos,Juan 04-28-2025 Approved
Dept Budget Officer Rios-Ramos,Juan 04-28-2025 Approved page 1 / 2
10x Order #9316
Printed: 06/04/2025 02:18:59 pm
Ciehoski,Stephanie Diane
Approval Type Name Date Status
ISD Places the order
Equipment Deployed
Location Jusification
Water Division SCADA The SCADA Segregation project was
commissioned as part of the Water Division’s
Cyber Security initiative. The mission of this project
is to isolate the Water Divisions 4 SCADA systems
and networks from the City of Fresno’s business
infrastructure for the sole goal of increasing our
security posture. This is a single project which is
broken down by location: Ground Water SCADA,
South East Treatment Facility and North East
Treatment Facility. Each of these systems are
independent yet are interconnected for the
purposes of administration and management. The
requested Cisco devices will allow us to inner-
connect all locations across dark fiber and not
across the City of Fresno’s enterprise networks.

Powered by TCPDF (www.tcpdf.org)
page 2 / 2

← All documents from this meeting