Traffic Installation at Church and Walnut Intersection
Existing Conditions
• The intersection at Church Avenue and Walnut Avenue
operates as a four-way stop.
Benefits
• Improve safety and traffic operations
• Improvements will benefit residents in the surrounding area, including those at the new Fresno City College
campus located on the southeast corner.
Funding
• Senate Bill 1(SB1) Road Maintenance and
Rehabilitation Account (RMRA)
Traffic Installation at Church and Walnut Intersection
Project Schedule
• Complete Design – Summer 2025
• Complete Acquisition of Right-of-Way - Spring 2026
• Construction Funding Availability – Start of FY 27
• Start Construction – Spring 2027
• Complete Construction – Summer 2027
APN: 477-030-27
• Property is located on the southwest corner of the
Church Avenue and Walnut Avenue intersection
• 1249.22 square feet of right-of-way is needed to
accommodate the proposed traffic signal poles