25-1743 Contract Change Order No. 4.pdf

Fresno City Council
January 15, 2026

Document
25-1743 Contract Change Order No. 4.pdf
Meeting
January 15, 2026
Body
Fresno City Council
Original file
134 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.

4 Oct 10, 2024
PROJECT: SHEET 1 of 1
12402799
N/A
Description:

I.

A.
$629,496.67
II.
$629,496.67
III.
200 Days
$629,496.67 Increase
Estimated -$ Decrease NUMBER
Exact X OF DAYS DATE
9,653,846.35$ Feb 10, 2025
46,598.70$ 175
Oct 16, 2025
676,095.37$ 200
230
Net change in Contract Price is 30
of the original Contract Price 7.0%
Oct 28, 2026
10,329,941.72$
Contractor:

Signed By: Title:

Approval
Recommended Date
Construction Manager
Authorized:  Chief Administrative Officer Date
(if change orders or total of change orders exceed 5% of contract price) Authorized:  City Council
(if change order or total change orders exceed 10% of contract price or if change order exceeds Fresno City Charter limit or Section 33422 Health and Safety Code for Agency contracts.) Approved:  Capital Projects Assistant Director Date Approved:  Capital Projects Director Date
Cc: Project Manager, Richard Madrigal
Senior Inspector, Devin Wiley
Chief Inspector, Brian Kujawaski
Total time extension days all CCO's
Provide all labor, materials, equipment, and incidentals for additional Geary Street improvements in accordance with the City of Fresno's RFP No. 6, dated September 3, 2025, and American Paving's Cost Proposal, dated September 22, 2025.

Weather Days through 11/29/2025
Cost of this Change Order

CONTRACT TIME
Change in Contract Time………………………………………………………………………………......

STATEMENT OF CONTRACT TIME
including this Change Order
Suspended Days
Extended Date for Completion
Substantial Completion
American Paving Co.

We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the price shown above.

Revised Contract Price
Minutes of Meeting Dated:

Jaime Macias
Accepted Date
Submitted By:

If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work.

Inspector
Total of all Contract Changes
Approved Cost Changes to Date
Original Contract Price Date of Notice to Proceed
Time extension days this CCO
Computed Date for Completion
Contract X Working Calendar Days
Increase to contract price shall include all costs for above noted work and shall be considered full compensation for all material, equipment, labor, applicable mark-up and overhead. All work noted above to be performed in accordance with the pertinent specifications.

EMAIL: [email protected]
CONTRACTOR/ADDRESS: American Paving Co. 525 W. Alluvial Avenue Fresno, CA 93711 You are hereby requested to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.

CHANGES TO CONTRACT PLANS AND SPECIFICATIONS

CONTRACT PRICE
Increase in Contract Price…...........................................................................................................

BID FILE NO.

City of Fresno
CONTRACT CHANGE ORDER NO.

Fresno, CA 93721

CAPITAL PROJECTS DEPARTMENT

CONSTRUCTION MANAGEMENT DIVISION
747 R Street, 2nd Floor
Increase in Contract Price…….……………………………………………...........................................

CITY COUNCIL REDEVELOPMENT AGENCY INFORMAL
NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED. Change requested by: CITY OF FRESNO CONTRACT:

CONTRACT AWARDED BY:

FEDERAL PROJ. ID.

DATE OF AWARD
South Peach Park
PROJECT I.D. 32500168 PC00213