Ashlan Avenue Widening – Polk to Cornelia Avenues
Existing Conditions
• Currently one lane each for
westbound and eastbound traffic.
• Improve safety and traffic operations
Benefits
Funding
• STBG and local match via New Growth developer fee program Ashlan Avenue Widening – Polk to Cornelia Avenues
Project Schedule
• Complete Design – Summer 2025
• Complete Acquisition of Right-of-Way - Spring 2026
• Construction Funding Availability – Start of FY 27
• Start Construction – Fall 2026
• Complete Construction – Winter 2026
APN: 511-012-05S
• Property is located on the south side of West
Ashlan Avenue, east of North Polk Avenue
• Easements required for the Project:
• 0.07-acre (2,863 SF) in permanent easement
• 0.12-acre (5,100 SF) in permanent easement
• 0.08-acre (3,403.32 SF) in permanent easement
• 0.11-acre (4,638.93 SF) in temporary
construction easement