Cities Index.
26-574 Contract Change Order No. 6

Fresno City Council
May 21, 2026

Document
26-574 Contract Change Order No. 6
Meeting
May 21, 2026
Body
Fresno City Council
Original file
199 KB
Text extracted from the city's file for reading and search. Open the original on legistar2.granicus.com. That file is the official record.





6 Oct 19, 2023
PROJECT: SHEET 1 of 1
12302905
N/A
Description:

I.

A.
24,292.00$
B.
6,136.82$
C.
50,549.50$
D.
5,500.00$
E.
2,000.00$
F.
10,000.00$
G.
14,000.00$
II.
112,478.32$
III.
60 Days
112,478.32$ Increase
Estimated X Decrease NUMBER
Exact OF DAYS DATE
8,646,293.00$ Mar 25, 2024
2,234,123.92$ 140
Oct 9, 2024
2,346,602.24$ 60
316
Net change in Contract Price is 14
of the original Contract Price 27.1% 0
Feb 5, 2026
10,992,895.24$
Contractor:

Signed By: Title:

Approval
Recommended Date
Construction Manager
Authorized: Chief Administrative Officer Date
(if change orders or total of change orders exceed 5% of contract price) Authorized: City Council
(if change order or total change orders exceed 10% of contract price or if change order exceeds Fresno City Charter limit or Section 33422 Health and Safety Code for Agency contracts.) Approved: Capital Projects Assistant Director Date Approved: Capital Projects Director Date
Cc: Project Manager, Nathan Sanchez
Senior Inspector, Devin Wiley
Chief Inspector, Darden Roche
NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED. Change requested by: CITY OF FRESNO

CITY COUNCIL REDEVELOPMENT AGENCY INFORMAL
CONTRACT:

CONTRACT AWARDED BY:

FEDERAL PROJ. ID.

DATE OF AWARD
TCC Park at MLK Magnet Core
PROJECT I.D. 32400343 PW00857
BID FILE NO.

City of Fresno
CONTRACT CHANGE ORDER NO.

Fresno, CA 93721

CAPITAL PROJECTS DEPARTMENT

CONSTRUCTION MANAGEMENT DIVISION
747 R Street, 2nd Floor

CHANGES TO CONTRACT PLANS AND SPECIFICATIONS

CONTRACT TIME
Change In Contract Time……………………………………………………………………………….....

CONTRACT PRICE
Estimated Increase in Contract Price…….……………………………………………….....................

Increase to Contract Price shall include all costs for above noted work and shall be considered full compensation for all material, equipment, labor, applicable mark-up and overhead. All work noted above to be performed in accordance with the pertinent Specifications.

Provides for all labor, equipment, materials, and incidentals to install a step-up transformer between the existing booster pump and the master switch board per the City of Fresno Request For Proposal No. 16, dated September 23, 2025, and Avison Constructions, Inc. Proposed Change Order No. 24, dated October 21, 2025.

EMAIL: [email protected]; [email protected]
CONTRACTOR/ADDRESS: Avison Construction, Inc. 40434 Brickyard Drive Madera CA 93636 You are hereby requested to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.

Minutes of Meeting Dated:

Luis Aguilar
Accepted Date
Submitted By:

Weather Days through 12/13/25
Suspended Days through 12/13/25
Extended Date for Completion
Substantial Completion
Avison Construction, Inc.

We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the price shown above.

If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work.

Revised Contract Price
Date of Notice to Proceed
Time extension days this CCO
Inspector
Total time extension days all CCO's
Computed Date for Completion
Contract X Working Calendar Days
including this Change Order
Total of all Contract Changes
Approved Cost Changes to Date
Original Contract Price
Cost of this Change Order STATEMENT OF CONTRACT TIME
Increase in Contract Price…...................................................................................................

Provides for all labor, equipment, materials, and incidentals to install temporary battery controllers for the irrigation of plants and trees site wide per Avison Construction, Inc. Proposed Change Order No. 25, dated November 13, 2025. All temporary material to be removed once Contract Work is completed.

Increase in Contract Price…...................................................................................................

Provides for all labor, equipment, materials, and incidentals to install 6 solar lights with foundations around the play area per the City's Request For Proposal No. 17, dated October 10, 2025, and Avison Construction, Inc. Proposed Change Order No. 26, dated November 18, Increase in Contract Price…...................................................................................................

Estimated Increase in Contract Price…...........................................................................................

Provides for all labor, equipment, materials, and incidentals to locate an existing 4" drain pipe and install a bubbler in a bio-swale omitted from Bulletin 2 - Bio-swale adjustments. Work to be performed as Extra Work in accordance with Section 3-3 of the City Specifications, Section 9-

1.04 of the California State Standard Specification, and as directed by the Engineer. Actual payment will be determined by the Engineer's Approved Daily Extra Work Reports.

Estimated Increase in Contract Price…...........................................................................................

Provides for all labor, equipment, materials, and incidentals to backfill, regrade and compact the valley gutter and tie-in at the intersection of Church and West Creek. Work to be performed as Extra Work in accordance with Section 3-3 of the City Specifications, Section 9-1.04 of the California State Standard Specification, and as directed by the Engineer. Actual payment will be determined by the Engineer's Approved Daily Extra Work Reports.

Estimated Increase in Contract Price…...........................................................................................

Provides for all labor, equipment, materials, and incidentals to excavate, grade and compact the new location of the monument sign. Work to be performed as Extra Work in accordance with Section 3-3 of the City Specifications, Section 9-1.04 of the California State Standard Specification, and as directed by the Engineer. Actual payment will be determined by the Engineer's Approved Daily Extra Work Reports.

Estimated Increase in Contract Price…...........................................................................................

Provides for all labor, equipment, materials, and incidentals to demolish, regrade and compact sidewalk and relocate conduit at the new drain inlet location. Work to be performed as Extra Work in accordance with Section 3-3 of the City Specifications, Section 9-1.04 of the California State Standard Specification, and as directed by the Engineer. Actual payment will be determined by the Engineer's Approved Daily Extra Work Reports.

Docusign Envelope ID: AE7195EF-C2F1-4E5C-9D33-2F197BFFB1E4 12/23/2025
President
12/23/2025
12/23/2025
Docusign Envelope ID: 1D0B18DE-4330-4235-B1CE-CE82FB78B62E 1/21/2026

← All documents from this meeting