7 Oct 19, 2023
PROJECT: SHEET 1 of 1
12302905
N/A
Description:
I.
A.
106,642.80$
B.
1,187.89$
II.
107,830.69$
III.
50 Days
107,830.69$ Increase
Estimated Decrease NUMBER
Exact X OF DAYS DATE
8,646,293.00$ Mar 25, 2024
2,346,602.24$ 140
Oct 9, 2024
2,454,432.93$ 50
366
Net change in Contract Price is 10
of the original Contract Price 28.4% 74
Jul 27, 2026
11,100,725.93$
Contractor:
Signed By: Title:
Approval
Recommended Date
Construction Manager
Authorized: Chief Administrative Officer Date
(if change orders or total of change orders exceed 5% of contract price) Authorized: City Council
(if change order or total change orders exceed 10% of contract price or if change order exceeds Fresno City Charter limit or Section 33422 Health and Safety Code for Agency contracts.) Approved: Capital Projects Assistant Director Date Approved: Capital Projects Director Date
Cc: Project Manager, Nathan Sanchez
Senior Inspector, Devin Wiley
Chief Inspector, Darden Roche
NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED. Change requested by: CITY OF FRESNO
CITY COUNCIL REDEVELOPMENT AGENCY INFORMAL
CONTRACT:
CONTRACT AWARDED BY:
FEDERAL PROJ. ID.
DATE OF AWARD
TCC Park at MLK Magnet Core
PROJECT I.D. 32400343 PW00857
BID FILE NO.
City of Fresno
CONTRACT CHANGE ORDER NO.
Fresno, CA 93721
CAPITAL PROJECTS DEPARTMENT
CONSTRUCTION MANAGEMENT DIVISION
747 R Street, 2nd Floor
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS
CONTRACT TIME
Change In Contract Time……………………………………………………………………………….......
CONTRACT PRICE
Increase in Contract Price…….……………………………………………….................................
Increase to Contract Price shall include all costs for above noted work and shall be considered full compensation for all material, equipment, labor, applicable mark-up and overhead. All work noted above to be performed in accordance with the pertinent Specifications.
Increase in Contract Price…...................................................................................................
Increase in Contract Price…...................................................................................................
Provides for all labor, equipment, materials, and incidentals to install two (2) additional No. 7 vaults and intercept the newly installed conduit along Church Avenue in accordance with the revised Rule 16 Delta 1 and Delta 2 per the City of Fresno Request for Proposal No. 19 dated February 19, 2026 and Avison Constructions, Inc. Proposed Change Order No. 31, dated February 23, 2026.
Provides for all labor, equipment, materials, and incidentals for the renewal of the State Water Board Permit 5F10C403358, payment will be made per Avison Constructions, Inc. Proposed Change Order No. 29, dated January 26, 2026.
EMAIL: [email protected]; [email protected]
CONTRACTOR/ADDRESS: Avison Construction, Inc. 40434 Brickyard Drive Madera CA 93636 You are hereby requested to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.
Minutes of Meeting Dated:
Luis Aguilar
Accepted Date
Submitted By:
Weather Days through 4/4/26
Suspended Days through 4/4/26
Extended Date for Completion
Substantial Completion
Avison Construction, Inc.
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the price shown above.
If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work.
Revised Contract Price
Date of Notice to Proceed
Time extension days this CCO
Inspector
Total time extension days all CCO's
Computed Date for Completion
Contract X Working Calendar Days
including this Change Order
Total of all Contract Changes
Approved Cost Changes to Date
Original Contract Price
Cost of this Change Order STATEMENT OF CONTRACT TIME
C
Docusign Envelope ID: B05C3090-0E5E-816A-8319-33771DF7BFF0 4/28/2026
President
4/30/2026