2 Jun 26, 2025
PROJECT: SHEET 1 of 1
12500160
N/A
Description:
I.
A.
-$
B.
67,544.98$
C.
331,000.00$
D.
42,651.00$
II.
Estimated Increase in Contract Price…….………………………………………………........................ 441,195.98$ III.
Change In Contract Time………………………………………………………………………………....... 26 Days 441,195.98$ Increase
Estimated X Decrease NUMBER
Exact OF DAYS DATE
945,288.00$ Sep 29, 2025
94,170.00$ 75
Jan 16, 2026
535,365.98$ 26
44 Net change in Contract Price is 0
of the original Contract Price 56.64% 0
Mar 23, 2026
1,480,653.98$ Mar 20, 2026
Contractor:
Signed By: Title:
Approval
Recommended Date
Construction Manager
Authorized: Chief Administrative Officer Date
(if change orders or total of change orders exceed 5% of contract price) Authorized: City Council
(if change order or total change orders exceed 10% of contract price or if change order exceeds Fresno City Charter limit or Section 33422 Health and Safety Code for Agency contracts.) Approved: Capital Projects Assistant Director Date Approved: Capital Projects Director Date
Cc: Project Manager, Armando Cervantes
Senior Inspector, Robert D. Cron Sr.
Chief Inspector, Richard Stockwell
Weather Days through 05/05/2026
Suspended Days through 05/05/2026
Extended Date for Completion
Substantial Completion
STATEMENT OF CONTRACT TIME Cost of this Change Order
Ashron Construction and Restoration, Inc.
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefor the price shown above.
Revised Contract Price
Minutes of Meeting Dated:
Matt Woodell
Accepted Date
Submitted By:
If the contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work.
Inspector
You are hereby requested to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on this contract.
Total time extension days all CCO's
Computed Date for Completion
Contract X Working Calendar Days
including this Change Order
Total of all Contract Changes
Approved Cost Changes to Date
Original Contract Price Date of Notice to Proceed
Time extension days this CCO
Provide all labor, equipment, materials, and incidentals to repair two (2) post tensioned tendons located in the Green Level, and one (1) post tensioned tendon in the Blue Level in accordance with the City of Fresno's Response to RFI's No. 08.0 and 08.2, and Ashron Construction's cost proposal No. 06, dated March 16, 2026.
NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED. Change requested by:
EMAIL: [email protected]
City of Fresno
CONTRACT CHANGE ORDER NO.
Fresno, CA 93721
CAPITAL PROJECTS DEPARTMENT
CONSTRUCTION MANAGEMENT DIVISION
747 R Street, 2nd Floor
CONTRACTOR/ADDRESS: Ashron Construction and Restoration, Inc. 9801 Orr Road Galt, CA 95632
CITY COUNCIL REDEVELOPMENT AGENCY INFORMAL
CONTRACT:
CONTRACT AWARDED BY:
FEDERAL PROJ. ID.
DATE OF AWARD
Garage 8 High Priority Repairs
PROJECT I.D. 32500510 FA00007
BID FILE NO.
Provide all labor, equipment, materials, and incidentals to perform exploratory work inside the old Club One Casino for the overhead repair to be performed on the Green Level at Grid Lines 7/D, including any required shoring and revised insurance requirements in accordance with the City of Fresno's Response to RFI's No. 24 and 25, and the City of Fresno's Request for Proposal No. 05, dated April 23, 2026. This work is to be performed as Extra Work in accordance with City of Fresno Standard Specifications Section 3-3 Extra Work and State Standard Specification Section 9-1.04 Force Account and directed by the Engineer. Actual payment will be determined by the Engineer's approved Daily Extra Work Reports.
Estimated Increase to Contract Price shall include all costs for above noted work and shall be considered full compensation for all material, equipment, labor, applicable mark-up and overhead. All work noted above to be performed in accordance with the pertinent Specifications.
Estimated Increase in Contract Price…...............................................................................................
Provide all labor, equipment, materials, and incidentals for additional concrete spall repairs at various locations on the Blue, Green, and Yellow Levels in accordance with the City of Fresno's Request For Proposal No. 03, dated December 01, 2025, Ashron Construction's cost proposal, dated December 15, 2025, and the Engineer of Record's Quantity/Location Determinations, dated April 17, 2026.
Lump Sum Increase in Contract Price…..............................................................................................
CHANGES TO CONTRACT PLANS AND SPECIFICATIONS
CONTRACT TIME
CITY OF FRESNO
Provide an additional twenty-six (26) contract working days in accordance with the City of Fresno's letter titled "Response to Time Impact Analysis", dated April 03, 2026.
CONTRACT PRICE
Lump Sum Increase in Contract Price…..............................................................................................
No Change in Contract Price…...........................................................................................................
R:\02 PROJECTS\FA PROJECTS (FACILITIES)\FA00007 GARAGE 8 HIGH PRIORITY REPAIRS\07 CONSTRUCTION\04 CONTRACTS\02 CHANGE ORDERS\CCO No.2\FA00007 CCO 02 5/15/2026 Docusign Envelope ID: 2EC5C5CD-B425-8BC8-8325-556A62962D3A 5/15/2026
5/15/2026
President