MAYOR’S PROPOSED BUDGET FY 2027Airports DepartmentBudget PresentationJUNE 11, 2026 Enterprise Fund
Airports DepartmentFY 2027 Total Budget2
FY 2027 ProposedFY 2026 AmendedFY 2025 ActualsFY 2024 ActualsCategory$ 20,284,800$ 17,778,300$ 13,577,161$ 12,421,869Personnel110,877,000100,198,89059,078,42324,901,567Non-Personnel6,674,0007,151,2105,531,4025,806,970Interdepartmental$ 137,835,800$ 125,128,400$ 78,186,985$ 43,130,407TotalJ U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7Notes1. Proposed budget includes $38,846,500 in Operating Funds and $98,989,300 in Capital and Debt Service Funds.

Airports DepartmentFY 2027 Budgeted Positions3
FY 2027 ProposedFY 2027 ChangesFY 2026 AmendedFY 2026 AdoptedFY 2025 AdoptedCategory24.20 0.0024.2022.2021.70 Sworn Positions137.20 0.00137.20 127.20 124.45 Civilian Positions161.400.00 161.40149.40146.15 TotalJ U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7 Airports DepartmentOperational Impacts4
FY 2027 ProposedDescription$ 428,000Customs and Border Patrol (CBP)1.$ 400,000Utilities2.$ 150,000Marketing3.$ 87,600Standard Parking 4.$ 82,200Service Aides 5. $ 61,700Amadeus6. Notes:1. The new terminal expansion will require an increased number of Customs Border Patrol (CBP) agents to support Airport operations2. PG&E costs are budgeted to rise due to an addition of more than 98,000 square feet associated with the terminal expansion3. Expanded marketing needs, including additional consultant services and media buys to further support passenger growth4. Contracted increase for parking services 5. Appropriations for two additional Service Aides to assist with new terminal baggage system 6. Contracted increase for additional biometric services and Software as a Service (SaaS) fees J U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7 Airports DepartmentFederal Grants5
J U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7 FY 2027 ProposedDescriptionFederal Grants$1,466,300 FAT Terminal/FIS Expansion1)FAT Runway 11L/29R Reconstruction 2)$28,506,800 •AIP Discretionary $4,500,000 •AIP Entitlement $3,150,000 FAT East Terminal Expansion3)$5,099,600 FAT Taxiway B Minor Rehab4)$862,000 FAT Noise Homes Part 1505)$1,865,000 FAT DOD Sound Mitigation-Residential6)FCH Runway 12-30 Reconstruction7)$587,000 •BIL AIG $138,800 •AIP Entitlement - Runway 12-30 Reconstruction$149,000 FCH Replace Runway 12 PAPI8)$149,000 FCH Airfield Security Upgrade Ph 19)$495,000 FCH Reconstruct Taxiway A Ph 110)Notes:FAT - Terminal/FIS Expansion for 2ndElevator is currently under construction 1.FAT - Runway 11L/29R Reconstruction is currently in Phase1 of Construction2.FAT – East Terminal Project Expansion is currently in planning 3.FAT – Taxiway B Minor Rehab is currently in planning & Design4.FAT - Sound Mitigation - Residential Homes currently in construction5. & 6.FCH - Runway 12-30 Reconstruction currently in planning7.FCH - Replace Runway 12 PAPI currently in planning8.FCH - Airfield Security upgrade ph1 currently in planning9.FCH - Reconstruct Taxiway A ph1 currently in planning10.

Airports DepartmentProgram & Project Highlights6
Notes:1. Runway 11L/29R project is moving to the construction of phase 12. Air Traffic Control Tower is pending Design & Construction phases, awaiting FAA funding award3. Taxiway B Minor Rehab is in the Design phase4. Terminal/FIS Construction remaining costs are budgeted at $4.0 million in FY2027 for a second elevator5. East Terminal Project is in the initial planning & Environmental phase6. Chandler Runway Reconstruction design is complete and beginning constructionSources: Grants & Airport MatchFY 2027 ProposedDescription$ 36,407,2001) AIP Recon Rwy 11L/29R$ 18,000,0002) AIP FAT Tower Replacement$ 5,625,000$ 4,000,000$ 3,474,500$ 806,5003) AIP Taxiway B Minor Rehab4) Terminal/FIS Expansion5) East Terminal Project6) FCH Runway ReconstructionJ U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7 Airports DepartmentHighlights7
•FAT closed out the calendar year (CY) 2025 with its highest passenger volume on record,from 2.6 million to 2.7 million, a 2.97% increase over the previous year.•International travel saw even greater growth, rising 3.25% over the prior year.•Passenger growth is expected to continue into calendar year 2026, but at a moremoderate pace, with boardings projected to remain largely in line with levels seen duringthe same period in 2025. Therefore, FY 2027 enplanements are forecast to experienceslower growth.•In 2026, the Airport anticipates higher airline revenues driven by additional terminal spacerentals, along with increased non-airline revenues from concessions, rental car activity,and parking demand. At the same time, airlines nationwide are experiencing slowergrowth and implementing selective flight reductions in response to broader economicconditions.•Airlines have a limited tolerance for year-over-year cost increases above 3.00%, theproposed budget reflects results a 4.20% overall increase in airline rates.•Because FAT has historically performed well compared to similar markets, airlines areexpected to maintain service where feasible. Even so, a weakening economicenvironment or continued escalation in operating costs could lead carriers to adjustschedules or reduce service levels.J U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7 Airports DepartmentCommunity Outreach Highlights8

1. Annual Airport Job Fair 2. Reedley College Tiger Job Fair 3. Parlier High School College & Carrer Fair 4. Clovis Community College Spring Job Fair 5. Grizzlies Partnership 6. Fresno Area Hispanic Foundation7. Fiestas Patrias 8. Central California Women’s Conference 9. Parcs Department Kids Fest 10. Beautify Fresno Neighborhood Clean-Up 11. Clovis Fest 12. FUSD Aviation Academy Partnership13. Support Blue Run 14. Fresno State Internship J U N E 1 1 , 2 0 2 6 M A Y O R ' S P R O P O S E D B U D G E T F Y 2 0 2 7