Project Name:G1 Service Elevator (Elevator No. 3) Project Area: 512SF Department: Airport Projects AC-00413 Paving Work: 729SF Prepared by: Hill International Project Duration: 12Mo Date: 6/25/2026 Building Area: G1
OWNER COSTS
01.) Architectural Design Fees Project Documents Architect 85,000
02.) Structural Design Fees Project Documents Engineer 60,000
03.) Survey Services Survey Surveyor 18,000
04.) Permit Fees City of Fresno Included 0
05.) Moving costs Moving NA 0
06.) ADA Review ADA Compliance Included 0
07.) Asbestos Testing City of Fresno Included 0
CONSTRUCTION DIRECT COSTS
08.) Construction
General Conditions Site Management General Contractor 1,200,000 Contruction Contingency Scope Increase General Contractor 200,000 Temporary Facilities Site Offices General Contractor 12,000 Demolition Demo General Contractor 60,000
Geotechnical Investigation Soils Report General Contractor 12,000 Concrete & Earthwork Foundation General Contractor 180,000 Structural Steel Steel framing General Contractor 210,000 Miscellaneous Metals Interior walls General Contractor 15,000 Fireproofing Steel beams General Contractor 55,000
Insulation R-Value General Contractor 8,000
EIFS Stucco General Contractor 75,000
Roofing & Flashing Roofing and trim General Contractor 38,000 Doors, Frames, Hardware Door assembly complete General Contractor 95,000 Acoustical Ceilings Grid and Tile General Contractor 75,000 Paint and Finishes Painting General Contractor 21,000
Drywall Drywall, Tape, Float General Contractor 160,000 Patching and Repairs Cut into new building General Contractor 32,000 Flooring As selected General Contractor 8,500
Signage Wayfinding General Contractor 4,500
Elevator Hydraulic Elevator, 2 StopsGeneral Contractor 180,000 Fire Protection Existing Cast Iron to ABS General Contractor 16,000 Mechanical Tie in supply and return General Contractor 85,000 Electrical 330 Amp Service General Contractor 180,000
Exterior Improvements As Required General Contractor 53,000
ORDER MAGNITUDE ESTIMATE
Project Description and Estimate Basis: Provide a new two-stop service elevator at Building G1, including the elevator shaft, machine room, elevator lobbies, required building modifications, and supporting systems for a complete and operational installation. This Order of Magnitude Estimate is provided for budgeting and funding authorization based on current project information. Actual costs may vary as the project develops. Inclusion of costs in this estimate does not constitute approval of any contractor proposal, change order, claim, or entitlement request.
Hill International 100 Spectrum Center Dr. Suite 550, Irvine, CA 92618
GC OVERHEAD, PROFIT, AND INSURANCE
09.) Overhead Overhead & Profit 5% General Contractor 148,750
10.) Insurance General Liability 3.5% General Contractor 104,125
11.) Bond Bond 5% General Contractor 148,750
12.) B/R Builder's Risk General Contractor 24,057
PROJECT CONTINGENCY AND DEVELOPMENT COSTS SUB TOTAL 3,563,682
13.) Owner Budget Development Reserve 3% of Project Cost Airports 106,910
14.) Owner Contingency Reserve 8% of Project Cost Airports 285,095 TOTAL ORDER OF MAGNITUDE3,955,687
Qualifications: Estimate assumes a standalone G1 Service Elevator project within an active airport environment over approximately 12 months with existing utilities and building systems available for connection. Costs may be reduced through shared mobilization, management, temporary facilities, and procurement if performed with other airport projects. Owner Budget Development and Owner Contingency Reserves are Airport-controlled and not available for contractor use.
Hill International 100 Spectrum Center Dr. Suite 550, Irvine, CA 92618