ATTACHMENT 1 – BUDGET DATA SHEET
Miscellaneous Storm Drain Repair FY 2021-22
Project No.: 52019
Source of Funds
Existing Budget:
$0
Proposed Budget Transfers:
Drainage Capital Outlay Fund from Project 52591 $335,000 TOTAL $335,000
Estimated Expenditures
Staff Design, Administration and Processing $15,000
Construction Contract $223,746
Estimated Surveying, Inspection, Testing,
and Contract Administration (20%) $44,800
Contingencies (20%) $44,800
Miscellaneous Construction – Private Property Compensation $4,500 TOTAL $332,846
Summary of Bids
Bid Opening: February 10, 2022
Engineer’s Estimate: $204,100
Contractor Location Bid Total
Lucas Builders, Inc La Habra $223,746
GRBCON, Inc Baldwin Park $392,820