ROAD MAINTANANCE AND REHABILITATION ACCOUNT (RMRA)/ SENATE BILL 1 (SB1) RESOLUTION APRIL 5, 2022
SB1 FUNDS ALLOCATION
Background
Senate Bill 1 (SB 1), known as the Road Repair and Accountability Act (RMRA) of 2017.
Intent is to address/fund basic roadway maintenance, rehabilitation and critical safety needs.
RMRA revenues are the result of increases in the fuel excise taxes, diesel fuel sales taxes and vehicle registration fees.
We have programmed and completed projects since 2018 using SB1 funds.
Expected SB 1 funding for FY 2022-23 is $3,178,282.
Previous Projects
Project 1 - FY 2017-18
Chapman Avenue (Acacia Ave to SR-57)
Project 2 - FY 2018-19
Commonwealth Avenue (Balcom Ave to Montegue Ave)
Raymond Avenue (Commonwealth Ave to Chapman Ave)
Project 3 - FY 2019-20
Euclid Street (Williamson Ave to Fern Dr)
Project 4A - FY 2020-21
Euclid Street (Fern Dr to Bastanchury Rd)
Valley View Place
Project 4B - FY 2020-21
Orangethorpe Avenue (Woods Ave to Highland Ave)
Project 5A - FY 2021-22
Rosecrans Avenue (City Limits to Sunny Ridge)
Project 5B - FY 2021-22
Valencia Avenue (Magnolia Ave to Gilbert St)
Funding Requirements
To receive funds, the California State Commission (CTC) requires City submit a list of proposed projects utilizing SB1 revenue by July 1, 2022.
CTC submittal requirements include:
Public review of proposed projects.
Infrastructure and Natural Resources Advisory Committee (INRAC) reviewed and recommended these projects at their February 28, 2022 meeting.
Use of Pavement Management Plan (PMP) to develop the list of potential projects.
City Council approval of Resolution identifying the list of projects.
Recommended Projects
Project #1
Associated Road
(Rolling Hills Dr to Imperial Hwy)
Project #2
Orangethorpe Avenue
(State College Blvd to Placentia Ave)
Recommended Project #1
ASSOCIATED ROAD
Rolling Hills Dr to Imperial Highway
Length of project is approximately 0.54 mile.
Current PCI ranges from 28-30
Estimated roadway cost is $1.1M
Rehabilitation method will be grind and overlay.
Work will also involve curb ramps, sidewalk repair, driveway repair, curb & gutter repairs.
Project will be coordinated with the replacement of the water main and repairs to segments of the sewer main.
Recommended Project #2
ORANGETHORPE AVENUE
State College Blvd to Placentia Ave
Length of project is approximately 0.34 mile.
Current PCI is 23
Estimated roadway cost is $2.15M
Rehabilitation method will be complete reconstruction.
Work will also involve curb ramps, sidewalk repair, driveway repair, curb & gutter repairs.
No water main replacement is planned.
Sewer main replacement will be coordinated with this project.
Coordination with City of Anaheim and Placentia is required.
Recommendation
Adopt the proposed Resolution Listing Associated Road and Orangethorpe Avenue for pavement rehabilitation for Fiscal Year 2022-23 funded by SB1, the Road Repair and Accountability Act of 2017.