MEASURE M2 FUNDING ELIGIBILITY RENEWAL
1 Measure M Funding
Measure M funding is a ½ cent sales tax within Orange County.
In 2006, over 70% of voters approved extension of the funding until 2041.
This funding extension is known as Measure M2 or OC Go.
Revenue from the sales tax is currently allocated to:
Freeways
Streets
Transit
Environmental Programs
2 Measure M Funding
In general, funding is allocated for:
OCTA projects
Direct allocations to local agencies
Competitive grant programs
Direct annual allocation received by the City:
Street Local Agency Funding
Project Q – Local Fair Share – approximately $2.7M for FY2022-23 Senior Mobility Program
Approximately $130,000 for FY2022-23
3 Measure M Eligibility Requirements
Local agencies must meet eligibility requirements to continue receiving annual funding and award of funds from competitive grant programs.
OCTA requires an annual eligibility process relying upon a variety of reporting methods to verify local jurisdiction adherence to the eligibility requirements.
Every year, the City provides the necessary documentation to certify compliance with the eligibility requirements.
The required documentation is shown on the following slides. 4 Eligibility Requirements for FY22/23
Compliance Category
Schedule
Summary
Capital Improvement Program (CIP)
Annual
CIP project list for street and M2-funded projects.
Maintenance of Effort (MOE)
Annual
Certification that City has expended a minimum amount of general revenue funds on street related activities.
No Supplanting Existing Commitments
Annual
Certification that City will not use M2 funding to supplant existing or future development funding commitments for transportation projects.
Pavement Management Plan (PMP)
Every Even Year
Inspection and rating of City street pavement conditions.
Timely Expenditure of Funds
Annual
Funds must be used within 3 years of receipt.
Traffic Forums
Annual
Attendance at meetings.
Transit/Non-Motorized Transportation in General Plan
Annual
Land Use Planning Strategies that accommodate transit and non-motorized transportation.
Eligibility Requirements for Future Fiscal Years
Compliance Category
Schedule
Summary
Circulation Element/MPAH Consistency
Every Odd Year
Certification that City’s Circulation Element is consistent with OCTA Master Plan of Arterial Highways Congestion Management Plan (CMP)
Every Odd Year
Includes Mobility and Air Quality objectives through the effective use of transportation funds, coordinated land use, and development practices.
Expenditure Report
Annual
Certification of use of funds received by the City.
Local Signal Synchronization Program (LSPP)
Every Three Years
A 3-year plan that identifies traffic signal synchronization, street routes and traffic signals to be improved.
Mitigation Fee Program (MFP)
Every Three Years
A program that assesses fees used to mitigate the effects of new development on transportation infrastructure.
Project Final Report
At Project Completion
For projects awarded grant funds
Pavement Management Plan (PMP) Background
The Pavement Management Plan (PMP) is required by OCTA in order for the City to be eligible for Measure M2 (also known as OC Go) funds.
Public Works prepares and updates the PMP every two years.
The plan determines the typical existing roadway condition and assigns a Pavement Conditions Index (PCI) rating from 0-100 for each roadway segment.
Certification from OCTA is required to prepare the Pavement Management Plan.
City contracted with Bucknam Infrastructure Group, Inc. to prepare the 2022 update.
Bucknam also prepared the 2016, 2018 and 2020 PMP updates. 7 Pavement Management Plan
City maintains approximately:
70 miles of arterial (major) roads
228 miles of local roads (residential/industrial roads) Arterial roads must be visually inspected every two years (every update) Local roads must be visually inspected every six years
The PMP objective is to:
Determine typical existing pavement conditions for roadway segments Assist with development of pavement rehabilitation strategies Assist with forecasting future pavement rehabilitation projects Assist with future budget needs
8 The PCI is a function of overall condition of the pavement. Condition problems include potholes, cracking, failures, rutting, etc.
Fewer problems = higher PCI rating
Pavement Condition Index
9 Factors That Impact Pavement Life
Delay of Preventive Maintenance
Traffic Volume and Loading
Age of Pavement
Type of Pavement (PCC vs AC)
Soil and Base Material Under Pavement
Storm Water Infiltration into Subgrade
Utility Trench Cuts
* The above factors will not impact all streets in the same manner 10 PMP Update - PCI Rating Summary
Item
2011 PCI
2013 PCI
2016 PCI
2018 PCI
2020 PCI
2022 PCI
(Current)
Arterial Streets
64.2 65.0
65.6 69.4
68.1 74.5
Local Streets
61.3 62.0
59.2 61.8
60.7 62.2
Citywide
62.3 63.0
61.6 64.7
63.5 66.8
11 PMP Update – 2022 PCI Rating Summary
Overall Weighted City Average
PCI = 66.8 (Fair)
Weighted Average
PCI = 74.5 (Fair)
Weighted Average
PCI = 62.2 (Fair)
12 Very Good PCI = 86-100
13 Good PCI =75-85
14 Fair PCI =60-74
15 Poor PCI =41-59
16 Very Poor PCI =0-40
17 PMP RecommendationsTo maintain roads in current condition – an increase in annual investment is required Arterials
Develop proactive fiscal and planned approach to identify overlay projects Approx. 37% of arterials (22 miles) qualify for rehabilitation/reconstruction Provide minimum budget of approximately $4.5M/yr to maintain PCI Locals
Develop proactive fiscal and planned approach to identify overlay projects and preventative maintenance projects Approx. 52% of locals (117 miles) qualify for rehabilitation/reconstruction Provide minimum budget of approximately $7.2M/yr to maintain PCI Note:
On February 15, 2022, Council allocated $13.1M of APRA funds to street rehabilitation. 18 Projected Conditions with Current Funding
19 Budgetary Street Construction Costs
Road Type
Treatment Type
PCI
Cost per Mile
Local
Slurry Seal
75-85
$176,000
Edge Grind & 2” Overlay
60-74
$810,000
Full Grind & 2” Overlay
$900,000
ARAM & 2” Overlay
$1,100,000
Full Grind & 4” Overlay
$1,250,000
Full Depth Reclamation
0-59
$1,600,000
Full Reconstruction
$1,860,000
Arterial
Full Grind & 2” Overlay
60-74
$1,700,000
Full Grind & 4” Overlay
$2,265,000
ARAM & 3” Overlay
$2,435,000
Full Depth Reclamation
0-59
$3,305,000
Full Reconstruction
$4,285,000
Note: Costs are budgetary guides only. Actual roadway treatment type and cost determined by multiple factors including geotechnical investigation. 20 Recommendation
21 Adopt Resolution No. 2022-XX.
RESOLUTION NO. 2022-XX – A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF FULLERTON, CALIFORNIA, CONCERNING THE STATUS AND UPDATE OF THE PAVEMENT MANAGEMENT PLAN FOR THE MEASURE M2 (M2) PROGRAM Approve and authorize Staff to submit the Measure M2 Seven-Year Capital Improvement Program for Fiscal Years 2022-23 through 2028-29 to Orange County Transportation Authority (OCTA) to comply with Measure M2 eligibility criteria.
Authorize Public Works Director to make administrative changes, including those advised by OCTA, if necessary.