ATTACHMENT 1 – BUDGET DATA SHEET
CURB/GUTTER AND SIDEWALK RECONSTRUCTION FISCAL YEAR 2021-22 Project No.: 44793
Source of Funds
Existing Budget:
Drainage Capital Outlay Fund $400,000
Infrastructure Fund $400,000
TOTAL $800,000
Estimated Expenditures
Staff Design, Administration and Processing $32,000
Construction Contract $389,330
Tree Removals $50,000
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $29,200
Contingencies (10%) $40,000
TOTAL $540,530
Summary of Bids
Bid Opening: July 12, 2022
Engineer’s Estimate: $390,000
Contractor Location Bid Total
FS Contractors, Inc. Sylmar $389,330
Gentry Genera Engineering, Inc. Rancho Cucamonga $423,815 CT&T Concrete Paving, Inc. Diamond Bar $516,190
Onyx Paving Company, Inc. Anaheim $627,000