ATTACHMENT 1 – BUDGET DATA SHEET
Norby Lane Storm Drain Replacement
Project No.: 52021
Source of Funds
Existing Budget:
$0
Proposed Budget Transfers:

Drainage Capital Outlay Fund from Project 52591 $332,300 TOTAL $332,300
Estimated Expenditures
Staff Design, Administration and Processing $25,000
Construction Contract $236,315.38
Estimated Surveying, Inspection, Testing,
and Contract Administration (15%) $35,450
Contingencies (15%) $35,450
TOTAL $332,215.38
Summary of Bids
Bid Opening: September 8, 2022
Engineer’s Estimate: $266,900
Contractor
Location
Bid Total

1. Aguilar & Calderon Corp*
Whittier
$236,315.38

2. Bonadiman Water, Inc
Perris
$319,520.00

3. Lucas Builders, Inc
La Habra
$398,586.00
(1) = Submitted bid amount was $236,315.40, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $236,315.38.