ATTACHMENT 1 – BUDGET DATA SHEET
ASSOCIATED ROAD WATER MAIN REPLACEMENT
YORBA LINDA BOULEVARD TO BASTANCHURY ROAD
Project No.: 53046
Source of Funds
Existing Budget:
Water Fund $30,000
Proposed Budget Transfers:
Water Fund from Project 53250 $1,685,000
TOTAL $1,715,000
Estimated Expenditures
Construction Contract $1,339,100
Project Design $20,000
City Supplied Materials $20,300
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $133,910
Contingencies (15%) $200,865
TOTAL $1,714,175
Summary of Bids
Bid Opening: December 14th, 2022
Engineer’s Estimate: $1,600,000
Contractor
Location
Bid Total
1. Big Ben, Inc.
Irvine, CA
(1) $1,339,100
2. Dominguez General Engineering
Pomona, CA
$1,436,250
3. Stephen Doreck Equipment Rentals, Inc.
Pico Rivera, CA
$1,686,665
4. Bonadiman Water, Inc.
Riverside, CA
$1,745,175
5. GCI Construction, Inc.
San Clemente, CA
$1,822,428
6. Kana Pipeline, Inc.
Riverside, CA
$2,495,996
(1) = Submitted bid amount was $1,329,100, however, miscalculation of the total amount was submitted by the Contractor. The correct bid total is $1,339,100.