ATTACHMENT 1 – BUDGET DATA SHEET
BROOKHURST ROAD AT SR-91 STREET REHABILITATION PROJECT
Project No.: 44063
Source of Funds
Existing Budget:
Infrastructure Fund $50,000
Proposed Budget Transfers:
Infrastructure Funds from Project 44400 $395,000
TOTAL $445,000
Estimated Expenditures
Staff Design, Administration and Processing $35,000
Construction Contract $325,825
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $32,590
Contingencies (15%) $49,000
TOTAL $442,415
Summary of Bids
Bid Opening: March 22, 2023
Engineer’s Estimate: $355,000
Contractor
Location
Bid Total
1. All American Asphalt
Corona
$325,825
2. R.J. Noble Company
Orange
$329,498
3. Palp, Inc. DBA Excel Paving
Long Beach
$337,612
4. Hardy & Harper, Inc.
Lake Forest
$350,000