Agenda Report
Fullerton City Council
MEETING DATE: April 18, 2023
TO: CITY COUNCIL / SUCCESSOR AGENCY
SUBMITTED BY: STEPHEN BISE, CITY ENGINEER / ASSISTANT PUBLIC WORKS DIRECTOR PREPARED BY: david grantham, principal civil engineer
Nick Esposito, associate civil engineer
SUBJECT: GILBERT PARK REPAIRS AND VOLUNTARY ACCESSIBILITY IMPROVEMENTS
SUMMARY
Award $269,276 construction contract to Towo Enterprise Inc. for the Gilbert Park Repairs and Voluntary Accessibility Improvements project.
RECOMMENDATION
Approve plans and specifications for Gilbert Park Repairs and Voluntary Accessibility Improvements project.
Approve $115,000 budget transfer from Project 55057 Citywide ADA Improvements to Project 54052 Gilbert Park Repairs and Voluntary Accessibility Improvements (Fund 74).
Award $269,276 construction contract for Gilbert Park Repairs and Voluntary Accessibility Improvements Project to Towo Enterprise Inc. and authorize City Manager, or designee, to execute the contract, in a form approved by the City Attorney.
Authorize Public Works Director, or designee, to approve any future change orders for construction and professional engineering construction support services within the approved project budget.
CITY MANAGER REMARKS
None.
PRIORITY POLICY STATEMENT
This item matches the following Priority Policy Statement:
Infrastructure and City Assets.
FISCAL IMPACT
The FY 2022-23 CIP Budget includes a $250,000 Community Development Block Grant (CDBG) to fund Project 54052 Gilbert Park Repair and Voluntary Accessibility Improvements Project. However, this project requires additional funding to complete the project. Project 55057 Citywide ADA Improvements has available funds for the requested $115,000 budget transfer to Project 54052 Gilbert Park Repairs and Voluntary Accessibility Improvements Project.
Staff has attached a Budget Data Sheet / Summary of Bids and the Contractor Bid Schedule for reference (Attachments 1 and 2).
DISCUSSION
Gilbert Park is a neighborhood park located at 2120 Orangethorpe Avenue and shown on Attachment 3. The improvements would repair damaged hardscape and create an accessible pathway throughout the park. The improvements include, but are not limited to:
new sidewalk installation connecting the park and Community Building to Orangethorpe Avenue concrete walkways and drainage gutter repairs
new accessible ramps
basketball court repair
new water fountain and bike rack
accessible parking stall relocation
parking lot repairs
new ADA signage.
The City utilized its ADA Transition Plan in the planning and design of the park repairs.
The City received four bids for the Gilbert Park Repairs and Voluntary Accessibility Improvements Project and publicly opened them on March 29, 2023. Towo Enterprise Inc. submitted the lowest responsible bid in the amount of $269,276. The low bid is approximately 4% lower than the engineer’s estimate of $280,000. Staff evaluated the bid and found it acceptable. Staff recommends awarding the project to Towo Enterprise Inc.
Staff anticipates construction to begin in late May and take six weeks to complete.
Staff has prepared an environmental assessment in accordance with the California Environmental Quality Act guidelines and determined the project categorically exempt.
Attachments:
Attachment 1 – Budget Data / Summary of Bids
Attachment 2 – Bid Schedule
Attachment 3 – Project Location Map
Attachment 4 – Draft Agreement