ATTACHMENT 1 – BUDGET DATA SHEET
GILBERT PARK REPAIRS AND VOLUNTARY ACCESSIBILITY IMPROVEMENTS Project No.: 54052
Source of Funds
Existing Budget:
Community Development Block Grant Funds $250,000
Proposed Budget Transfers:
Infrastructure Funds from Project 55057 $115,000
TOTAL $365,000
Estimated Expenditures
Construction Contract $269,276
Staff Design, Administration and Processing $25,000
Estimated Surveying, Inspection, Testing,
and Contract Administration (10%) $27,000
Contingencies (15%) $40,000
TOTAL $361,276
Summary of Bids
Bid Opening: March 29, 2023
Engineer’s Estimate: $280,000
Contractor
Location
Bid Total
1. Towo Enterprise Inc.
Fullerton
$269,276
2. Vido Samarzich Inc.
Rancho Cucamonga
$366,080
3. Falkon Construction
Diamond Bar
$544,360
4. CS Legacy Construction
Walnut
$562,603