ROAD MAINTANANCE AND REHABILITATION ACCOUNT (RMRA)/ SENATE BILL 1 (SB 1) RESOLUTION APRIL 18, 2023
SB1 FUNDS ALLOCATION
Background
Senate Bill 1 (SB 1), known as the Road Repair and Accountability Act (RMRA) of 2017, which established the Road Maintenance & Rehabilitation Account.
Intent is to address/fund basic roadway maintenance, rehabilitation and critical safety needs.
RMRA revenues are the result of increases in the fuel excise taxes, diesel fuel sales taxes and vehicle registration fees.
We have programmed and completed projects since 2018 using SB 1 funds.
Expected SB 1 funding for FY 2023-24 is approximately $3.5 million.
Previous SB1 Projects
3 FY 2017-18
Project 1 - Chapman Avenue (Acacia Ave to SR-57)
FY 2018-19
Project 2 - Commonwealth Avenue (Balcom Ave to Montegue Ave) Raymond Avenue (Commonwealth Ave to Chapman Ave)
FY 2019-20
Project 3 - Euclid Street (Williamson Ave to Fern Dr)
FY 2020-21
Project 4A - Euclid Street (Fern Dr to Bastanchury Rd) & Valley View Pl Project 4B - Orangethorpe Avenue (Woods Ave to Highland Ave) FY 2021-22
Project 5A – Rosecrans Avenue (City Limits to Sunny Ridge) Project 5B - Valencia Avenue (Magnolia Ave to Gilbert St) FY 2022-23
Project 6A – Orangethorpe Avenue (State College to Placentia Ave) Project 6B - Associated Road (Rolling Hills to Imperial Hwy)
Funding Requirements
To receive funds, the California State Commission (CTC) requires City submit a list of proposed projects utilizing SB1 revenue by July 1, 2023.
CTC submittal requirements include:
Public review of proposed projects.
Infrastructure and Natural Resources Advisory Committee (INRAC) reviewed and recommended these projects at their February 27, 2023 meeting.
Use of Pavement Management Plan (PMP) to develop the list of potential projects.
City Council approval of Resolution identifying the list of projects.
Potential Arterial Street Projects
5 Project 1 – Palm Street
Imperial Hwy to Lambert
Project 2 – Rosecrans Avenue
Camino Centraloma to Parks Rd
Project 3 – State College Boulevard
Bastanchury Rd to City Limits
Project 4 - State College Boulevard
Yorba Linda Blvd to Bastanchury Rd
Project 5 – Yorba Linda Boulevard
Associated Rd to Placentia Ave
Project 6 - Harbor Boulevard
Chapman Ave to Berkeley Ave
Project 7 – Gilbert Street
Valencia Ave to Commonwealth Ave
Project 8 – Valencia Avenue
Euclid St to Woods Ave
Project 9 – Commonwealth Avenue
Acacia Ave to State College Blvd
Project 10 – Commonwealth Avenue
State College Blvd to Chapman Ave
Project 11 – Raymond Avenue
SR-91 to Orangethorpe Ave
Project 12 – Acacia Avenue
City Limits to Orangethorpe Ave
Projects 2, 8, 9, 10 are not recommended at this time as they are programmed for future water main replacement
Potential Local Street Projects
6 Project 1 – Las Palmas Area (no water or sewer)
Project 2 – Sunny Hills-Twilight Area (water main replacement) Project 3 – Hermosa Area (water main replacement)
Project 4 – Rancho-Verona Area (water main replacement) Project 5 – Firethorne Area (water main replacement)
Project 6 – Cannon-Shepard Area (water main replacement) Project 7 – Costa Ct Area (no water or sewer)
Project 8 – Slurry Seal – Various Streets
Staff Recommended SB 1 Project #1
7 STATE COLLEGE BLVD
Yorba Linda Blvd to City Limits
Estimated Construction Cost = $2.40M
Estimated Total Project Cost = $2.85M
Pavement Rehabilitation
3” Grind & Overlay (assumed)
Concrete curb ramps, curb & gutter repair, sidewalk repair, driveway repair.
Project is not expected to include utility improvements
Staff Recommended SB1 Project #2
8 CITYWIDE SLURRY SEAL
Slurry seal of good condition streets that were subject to previous water main or sewer main replacement projects, except Pritchard Area and Wilshire-Lillie Area Project 1 – Pritchard Area
Project 2 – Fern-Casa Blanca Area
Project 3 – Union Ave and Glenwood Ave
Project 4 – Lincoln Ave
Project 5 – Marion Area
Project 6 – Hollydale Ave
Project 7 – Wilshire-Lillie Area
Estimated Construction Cost = $500,000
Estimated Total Project Cost = $600,000
Additional locations may be added as bid alternates
Recommendation
Adopt the proposed Resolution Listing State College Boulevard and Citywide Slurry Seal for pavement rehabilitation for Fiscal Year 2023-24 funded by SB1, the Road Repair and Accountability Act of 2017.