BID PROPOSAL

MORELIA AVENUE & JUANITA COOKE TRAIL IMPROVEMENTS
PROJECT NO. 54044

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
1 MOBILIZATION LS $35,000.00 $35,000.00
2 WATER POLLUTION CONTROL 1 LS $5,000.00 $5,000.00
3 TRAFFIC CONTROL 1 LS $15,000.00 $15,000.00
4 REMOVE CONCRETE CURB AND GUTTER 940 $15.00 $14,100.00 5 CONSTRUCT 6" CURB AND GUTTER 940 LF $60.00 $56,400.00 REMOVE AND RECONSTRUCT PCC CURB AND 65 LF
GUTTER $75.00 $4,875.00
REMOVE AND RECONSTRUCT PCC SIDEWALK 850 SF $12.00 $10,200.00

REMOVE EXISTING AND CONSTRUCT ADA
8 EA $4,800.00 $33,600.00

ACCESS RAMP

REMOVE & RECONSTRUCT PCC CROSS SF
GUTTER & SPANDREL 1,800 $30.00 $54,000.00
REMOVE EXISTING AND CONSTRUCT 42"
10 50 LF $150.00 $7,500.00

DOWN DRAIN
11 CONSTRUCT 24" PARKWAY DRAIN 2 EA $3,000.00 $6,000.00 12 CONSTRUCT 2' - 4' HIGH GRAVITY WALL 95 LF $240.00 $22,800.00 REMOVE EXISTING AND CONSTRUCT 3" THICK SF
13 8,600 $10.00 $86,000.00

AC SIDEWALK/ TRAIL
14 ROADWAY EXCAVATION 118 CY $150.00 $17,700.00
15 AGRREGATE BASE 180 cY $85.00 $15,300.00
16 COLD MILL - 4-INCH 50,500 SF $1.25 $63,125.00
17 PAVEMENT DIGOUTS/REPAIRS (AS NEEDED) 5,000 SF $6.00 $30,000.00 18 ASPHALT CONCRETE 1,250 TON $127.00 $158,750.00
19 ADJUST MANHOLE COVER TO GRADE 4 EA $2,500.00 $10,000.00 20 ADJUST WATER VALVE COVER TO GRADE 6 EA $1,600.00 $9,600.00 21 TRAFFIC SIGNING AND STRIPING 1 LS $15,000.00 $15,000.00 22 STREET LIGHT CONDUIT REPAIR 50 LF $50.00 $2,500.00
23 Base Bid Total $ 672,450.00

TO BE SUBMITTED WITH BID
BD-16

BID PROPOSAL

MORELIA AVENUE & JUANITA COOKE TRAIL IMPROVEMENTS
PROJECT NO. 54044

ESTIMATED
NO. ITEM QUANTITY UNIT UNIT PRICE AMOUNT
Unit prices are required for all bid items.

The Bidder shall total his/her bid. Unit prices shall prevail in case amount disagrees with extension.

Project shall be awarded on the Base Bid. If applicable, the City may elect to use Bid Alternates after award.

Changes to either Unit Price or Amount shall be striked-out and initialed Items of work not specifically listed shall be included in the bid prices for related work. For all work required and shown on the construction plans and specifications for which no specific bid item or price is listed in the bid schedule, it shall be understood that such work, equipment, labor, tools, and materials shall be provided as part of the listed bid items and no additional compensation will be paid therefor.
if the City determines that any of the unit bid prices are significantly unbalanced to the potential detriment of the City, the bid may be considered non-responsive.

Company Towo Enterprise Inc
Name Yun Su Chung
Signature
Address 2536 Fender Ave Suite D
City & Zip Code Fullerton, CA 92831
Phone Number 714-770-0379
License Number 986567

TO BE SUBMITTED WITH BID