ATTACHMENT 1 – BUDGET DATA SHEET

ASSOCIATED ROAD STREET IMPROVEMENTS PROJECT
Project No.: 44060
Source of Funds
Existing Budget:

Measure M2 Funds $148,146
Proposed Budget Transfers:
2021 Pavement Management Relief Funds from Project 44400 $409,362 ARPA Revenue Replacement Funds from Project 44589 $330,200 TOTAL $887,708
Estimated Expenditures
Design, Administration and Processing $78,468
Construction Contract $688,695
Estimated Surveying, Inspection, Testing,
and Contract Administration (7.5%) $51,652
Contingencies (10%) $68,870
TOTAL $887,685
Summary of Bids
Bid Opening: June 1, 2023
Engineer’s Estimate: $569,054
Contractor
Location
Bid Total

1. RJ Noble Company
Orange, CA
$688,695

2. Onyx Paving Company
Anaheim, CA
$808,000

3. Hardy & Harper
Lake Forest, CA
$810,000

4. All American Asphalt
Corona, CA
$1,172,068